On July 10, the Hanoi People's Committee issued Decision No. 3741 on the investment policy for the project to install additional fire prevention and fighting items on metro line 2A Cat Linh - Ha Dong.
The investment goal of the above project is to ensure fire safety for the 2A railway line. At the same time, promptly handle fires and explosions and support evacuation, promptly comply with fire prevention and fighting regulations according to Decree 136c of the Government.
According to the decision, the investment scale is to install automatic fire fighting systems at 12 stations and depots. Add smoke inhalation systems in battery rooms and electrical rooms; ensure 2 independent smoke in circulation systems for the terminal.
The project has a total investment of about 30 billion VND, using the city budget. The implementation period is 2 years (2025 - 2026).
The City People's Committee assigned Hanoi Railway One Member Co., Ltd. as the investor, responsible for establishing the project, coordinating with departments and branches to ensure progress, savings and compliance with regulations.
The Hanoi Department of Construction is responsible before the law and the City People's Committee for the legality and accuracy of the appraisal documents.