Set a time to repair damage at Cat Linh - Ha Dong urban railway

Minh Hạnh |

Hanoi - Hanoi Metro is urgently repairing damage at stations of the Cat Linh - Ha Dong urban railway line.

According to the representative of Hanoi Metro One Member Co., Ltd., from May 24 to June 2, the unit coordinated with functional units to inspect the scene, develop a plan to repair and urgently overcome incidents and damage at the stations of urban railway line No. 2A, Cat Linh - Ha Dong.

For the rolling roof and outdoor walkways at some stations, as of June 2, Hanoi Metro has dismantled and replaced all damaged rolling roofs and walkways at stations: Thai Ha, Ring Road 3, Van Quan and Yen Nghia.

Tam lop mai che thang cuon ga Van Quan bi bong bat dang duoc Ha Noi Metro khac phuc. Anh: Huu Chanh
The roof of Van Quan station's stairs has been peeled off and has been repaired by Hanoi Metro. Photo: Huu Chanh

For the roof at Yen Nghia station, Hanoi Metro has purchased materials, repaired and replaced it, expected to be completed before June 5. In addition, the periodic inspection and maintenance of the roof system at stations is still carried out regularly by the Construction Maintenance and Repair Team (under Hanoi Metro), including glue checking, screening and roof cleaning.

For the station equipment items, Hanoi Metro has newly replaced and repaired all 5 camera surveillance screens at Yen Nghia, Ha Dong, and La Thanh stations; completed the repair and replacement of 55 loudspeakers at 12 stations.

Along with that, the unit has adjusted and temporarily fixed the LED PIS system (train running time display) to ensure that passengers can track train arrival and departure times at all 12 stations. The train timing display system is expected to be completely fixed before June 20.

He thong hien thi gio chay tau dang duoc khac phuc tam thoi. Anh: Tuan Khai
The train running time display system is being temporarily fixed. Photo: Tuan Khai

In addition, Hanoi Metro is carrying out procedures to purchase replacement materials and repair defective TVM automatic ticket vending machines as soon as possible. These are materials and components manufactured according to project orders from 2014-2015, not available on the market; it is expected that by October 2025, the repair can be completed.

Regarding the elevator and escalator system at 12 stations, Hanoi Metro technicians continue to inspect and maintain normal operation. On May 30, an elevator at Thuong Dinh station and a escalator at Phung Khoang station had technical problems, which are currently being fixed and are expected to be completed before June 6.

In particular, the public water drinker and phone charging station at La Khe station are part of the pilot model in the model station development stage. After assessing the needs for use, the ability to ensure safety and water quality (because public clean water sources cannot be drunk directly), as well as the short waiting time for ships to wait for battery charging, the investor decided not to continue operating these devices.

In the immediate future, Hanoi Metro will restore, preserve and continue to study the possibility of exploiting these devices again at La Khe station. If it is assessed as suitable, the company will consider implementing it at other terminals in the future.

The representative of Hanoi Metro also said that the company is actively coordinating with the Hanoi Traffic Management and Operation Center to soon sign a contract to order maintenance of the infrastructure of urban railway line No. 2A, Cat Linh - Ha Dong in 2025.

Minh Hạnh
TIN LIÊN QUAN

Hanoi Metro admits delays in repairing damage to Cat Linh - Ha Dong route

|

Hanoi Metro admits the delay in repairing damage to infrastructure, causing negative impacts on passengers and operations of the Cat Linh - Ha Dong route.

Hanoi is about to start construction of 3 bridges across the Red River, 2 urban railway lines

|

Hanoi - It is expected that this year, the city will start construction of 3 bridges across the Red River including Tu Lien, Tran Hung Dao, Ngoc Hoi, along with 2 urban railway lines No. 2 and No. 5.

Research on Vietnamese people playing casino after the pilot period

|

The Deputy Prime Minister requested to study special policies for the development of Phu Quoc Special Zone, allowing Vietnamese people to play casino after the pilot period.

Ho Chi Minh City has a comprehensive tourism space from the city to the sea after the merger

|

Ho Chi Minh City after the merger owns diverse resources, large markets and complete infrastructure, opening up opportunities for a strong breakthrough in tourism.

Continue to reorganize mass organizations assigned by the Party and the State

|

The Party Committee of the Vietnam Fatherland Front and Central organizations will lead and direct the continued reorganization of mass associations assigned by the Party and State to operate under the Vietnam Fatherland Front, in the direction of reducing the number, streamlining the internal apparatus, and operating practically and effectively.

Buying Vietlott lottery on the day of giving birth, a worker won more than 16 billion VND

|

A man has just received the Vietlott Jackpot 2 lottery draw Power 6/55 QSMT No. 01210 with a value of more than 16 billion VND.

Mr. Thaksin declares belief in the integrity of Paetongtarn's daughter

|

Former Thai Prime Minister Thaksin Shinawatra shared his views on the situation in Thailand and the suspension of his daughter, Ms. Paetongtarn, from the position of Prime Minister.

There have been conclusions about the person who shot down the MH17 passenger plane

|

The Malaysia MH17 plane crash due to shelling in 2014, with 298 passengers on board, has been determined.

Ban Quản lý Đường sắt đô thị Hà Nội lên tiếng về việc bùn trào khi thi công metro

Minh Hạnh |

Hà Nội – Ban Quản lý Đường sắt đô thị Hà Nội (MRB) chính thức lên tiếng về hiện tượng bùn phun lên mặt đất trong quá trình thi công.

Hanoi Metro admits delays in repairing damage to Cat Linh - Ha Dong route

HỮU CHÁNH |

Hanoi Metro admits the delay in repairing damage to infrastructure, causing negative impacts on passengers and operations of the Cat Linh - Ha Dong route.

Hanoi is about to start construction of 3 bridges across the Red River, 2 urban railway lines

HỮU CHÁNH |

Hanoi - It is expected that this year, the city will start construction of 3 bridges across the Red River including Tu Lien, Tran Hung Dao, Ngoc Hoi, along with 2 urban railway lines No. 2 and No. 5.