Image of the largest bridge on Ho Chi Minh City Ring Road 3 about to reach the finish line

Anh Tú |

Ho Chi Minh City - Nhon Trach Bridge, an important item on Ho Chi Minh City Ring Road 3, is about to close the final span on March 9 and is expected to open to traffic on April 30.

After nearly 2.5 years of construction, component project 1A (including Nhon Trach bridge and roads at both ends of the bridge started in September 2022) has a total length of 8.22km (Dong Nai 6.3km and Ho Chi Minh City 1.92km); roadbed is 20.5m - 26m wide. The project has a total investment of VND 6,955 billion, currently 87% complete, 4 months ahead of schedule and is expected to be completed on April 30 this year.

Day la doan co tien do nhanh nhat trong toan tuyen Vanh dai 3 TPHCM.
The Nhon Trach Bridge package is currently at about 94% progress. This is the fastest section on the entire Ho Chi Minh City Ring Road 3. Photo: Anh Tu

According to the My Thuan Project Management Board, the 2.6km Nhon Trach bridge package currently has about 94% output. At the approach bridge section on the Dong Nai bank, Ho Chi Minh City has completed the entire lower structure and is constructing the bridge surface. It is expected that on March 9, the border connection bridge will mark an important step forward in connecting Ho Chi Minh City with Dong Nai.

After the closure, Nhon Trach Bridge will continue with stages such as extending external cables, constructing parapets, paving asphalt concrete and completing traffic safety items to open to traffic on the occasion of the April 30 holiday.

Tren cau Nhon Trach, cong nhan dang tap trung thi cong lap dat cot thep mat cau. Ảnh: Anh Tu
On Nhon Trach Bridge, workers are focusing on pouring concrete for the bridge railing. Photo: Anh Tu

Connecting with Nhon Trach Bridge is the approach roads at both ends of the bridge and the progress is currently very good. Some sections of the road are being paved with roadbed, some sections have been granted stone, and some sections have been paved with asphalt.

According to the Project Management Board, the 5.6km approach road package at both ends of the bridge is currently over 75% complete, and is being accelerated to complete on April 30 to synchronously connect with the river overpass.

Du kien gan giua thang 3 cau se hop long nhip bien.
It is expected that 9.3 bridges will be closed with border spans, this is also the last span of the Nhon Trach bridge item. Photo: Anh Tu

Along with Nhon Trach Bridge, contractors constructing the intersection between Nhon Trach Bridge and Ho Chi Minh City Ring Road 3, the section passing through Thu Duc City, are also speeding up to complete the two connecting branches up and down the bridge in time to reduce the load on the Ho Chi Minh City - Long Thanh - Dau Giay Expressway.

a
Continuing with Nhon Trach Bridge is the approach roads at both ends of the bridge, and the progress is also very good. On the Dong Nai shore, it is now in shape. Photo: Anh Tu
Cac cong nhan dang lu len nen duong, chuan bi tham nhua. Ảnh: Anh Tu
Workers are rolling the roadbed, preparing asphalt. Photo: Anh Tu

Nhon Trach Bridge is one of the most important items on Ho Chi Minh City Ring Road 3, connecting Ho Chi Minh City with Dong Nai, when completed, it will help shorten the distance from Nhon Trach District (Dong Nai) to Binh Duong and the center of Ho Chi Minh City. This route will also help reduce traffic pressure on National Highway 1A, Ho Chi Minh City - Long Thanh - Dau Giay Expressway, and connect Ho Chi Minh City with Long Thanh Airport and the Eastern and Southwestern provinces.

Anh Tú
TIN LIÊN QUAN

Ho Chi Minh City Ring Road 3 technical traffic opening through Long An in 2025

|

Long An - Strive to basically complete the expressway section of the Ho Chi Minh City Ring Road 3 project in October and will be completed and technically opened to traffic by December 31.

Prime Minister wishes a Happy New Year to workers at the Ho Chi Minh City Ring Road 3 project

|

Dong Nai - Prime Minister Pham Minh Chinh visited and wished a happy new year to engineers and workers working at Nhon Trach Bridge, part of the 1A Ring Road 3 component project in Ho Chi Minh City.

Slow disbursement of public investment capital in the first 2 months of the year

|

Public investment disbursement in the first 2 months of 2025 only reached 6.9% of the plan, lower than the same period in 2024. Many ministries, branches and localities have not disbursed or have disbursed very low.

Vietnam team and the challenge in the 2027 Asian Cup qualifiers

|

The 2027 Asian Cup qualifiers are the next big challenge for coach Kim Sang-sik and the Vietnamese team, after winning the 2024 ASEAN Cup.

Disillusioned with buying billion-dollar land without dividing plots

|

Many investors are stuck when buying disputed plots of land, unable to complete the procedures for land division.

Gold price update on the morning of February 25: Demand increases, record high

|

Gold price update on the morning of February 25: Continue to increase, setting a new peak despite the USD going up. The cautious sentiment is supporting the precious metal's rally.

The scale of Quang Nam Central General Hospital when it becomes the 3rd facility of Hue Central General Hospital

|

The establishment of Hue Central General Hospital, Facility 3 in Quang Nam, is expected to bring many benefits to the people of the Central region.

Storm forecast near the East Sea next week

|

The latest storm forecast shows two trends in storm formation near the East Sea in March.

Ho Chi Minh City Ring Road 3 technical traffic opening through Long An in 2025

Duy Minh |

Long An - Strive to basically complete the expressway section of the Ho Chi Minh City Ring Road 3 project in October and will be completed and technically opened to traffic by December 31.

Prime Minister wishes a Happy New Year to workers at the Ho Chi Minh City Ring Road 3 project

HÀ ANH CHIẾN |

Dong Nai - Prime Minister Pham Minh Chinh visited and wished a happy new year to engineers and workers working at Nhon Trach Bridge, part of the 1A Ring Road 3 component project in Ho Chi Minh City.

Cây cầu lớn nhất Vành đai 3 TPHCM sau gần 2 năm thi công lộ dần hình hài

Anh Tú - Ngọc Ánh |

TPHCM - Sau 17 tháng thi công, tổng khối lượng thực hiện công trình cầu Nhơn Trạch và đường dẫn thuộc dự án đường Vành đai 3 TPHCM đã đạt khoảng 40% so với kế hoạch đề ra. Hàng trăm công nhân vẫn đang miệt mài trên công trường để sớm đưa dự án về đích đúng hẹn.