The 10-lane road in Hanoi is about to be completed after many years of sluggish construction

HỮU CHÁNH |

Hanoi - The Ring Road 3.5 section through Hoai Duc is being completed by the contractor after receiving enough land, expected to be completed this year.

In 2017, the Ring Road 3.5 project through Hoai Duc district (Hanoi) began construction. The project is 5.5km long, with a total investment of about VND1,800 billion, invested by the People's Committee of Hoai Duc district.

According to the plan, the project is scheduled to be completed in October 2018. However, up to now, the project has been completed for nearly 7 years but the construction site is still in disarray.

The project's sluggish construction year after year has caused dusty sunlight and muddy rain, affecting people's travel and daily life.

"We hope that the project will be completed soon so that travel will be convenient and people's lives along the route will have many changes" - Ms. Nguyen Thi Ngoc (35 years old, Song Phuong commune, Hoai Duc) said.

According to the investor's representative, the project's progress has been delayed for many years due to problems in site clearance, especially the Vuon Chuoi Archaeological Site (Kim Chung Commune, Hoai Duc).

In March 2024, with the permission of the Ministry of Culture, Sports and Tourism, the People's Committee of Hoai Duc district organized the groundbreaking ceremony for the excavation and relocation of the Vuon Chuoi archaeological site. The package implementation period is 330 days.

Up to now, the excavation and relocation of the Archaeological Site of Vuon Chuoi has been completed. The contractor is mobilizing machinery and workers to complete the remaining sections of the project.

It is expected that the Ring Road 3.5 section through Hoai Duc district will be completed in 2025.

When completed, the route will contribute to connecting the North and South of the Red River conveniently, helping to reduce traffic congestion, creating conditions for socio-economic development of Hoai Duc district in particular and the city in general.

Not far away, the intersection between Ring Road 3.5 and Thang Long Avenue is under construction by the contractor.

The project started on April 19, one of a series of projects that were started and inaugurated nationwide, on the occasion of the 50th anniversary of the Liberation of the South and National Reunification Day.

The scale of the intersection of intersections consists of turbine branches combined with duty tunnel: Trac tunnel in the direction of Le Trong Tan street (now Hoang Tung street) to Highway 32, the heart of the gland with Hoang Tung road, arranging 4 lanes with a total length of 975m. The section walking under Thang Long Boulevard designed a 150m long tunnel. The Hoang Tung road is designed with 157.5m long tunnel, a 220m long wall. On Highway 32, the open tunnel design is 157.5m long, the wall is 200m long.

The turbine branch bridge with a prestressed reinforced concrete beam has a length of 2,357m/4 branches, the width of the bridge is 8.8m, arranged with 2 lanes, the reinforced concrete retaining wall has a total length of 619m.

The project has a total investment of nearly VND 2,400 billion, invested by the Hanoi Civil Works Construction Investment Project Management Board.

Some images of the Ring Road 3.5 project through Hoai Duc:

Diem dau du an tai nut giao voi Dai lo Thang Long. Khu vuc nay dang duoc xay dung nut giao gan 2.400 ti dong de ket noi Vanh dai 3,5 voi Dai lo Thang Long. Anh: Huu Chanh
The starting point of the project is at the intersection with Thang Long Avenue (Hoai Duc district, Hanoi). This area is under construction at an intersection worth nearly VND2,400 billion to connect Ring Road 3.5 with Thang Long Avenue. Photo: Huu Chanh
d
The 3.5 Ring Road section from Thang Long Avenue to the intersection of Provincial Road 422B has basically completed the main items. Photo: Huu Chanh
Co cay moc um tum doc tuyen, thoi gian dai chua duoc ve sinh, don dep. Anh: Huu Chanh
Grass and trees grow wildly along the route, and have not been cleaned or cleaned for a long time. Photo: Huu Chanh
Mot doan via he tro thanh noi tap ket rac thai. Anh: Huu Chanh
A section of the sidewalk has become a garbage collection site. Photo: Huu Chanh
Doan tu cau Hau Ai den cuoi tuyen dang duoc trien khai thi cong. Anh: Huu Chanh
The section from the intersection of Provincial Road 422B to the end of the route is under construction. Photo: Huu Chanh
Trong anh la Khu di chi Vuon Chuoi da duoc khai quat, di doi de ban giao mat bang cho du an. Anh: Huu Chanh
In the photo is the Vuon Chuoi Scenic Area, which has completed the excavation and relocation to hand over the site for the project. Photo: Huu Chanh
May moc, cong nhan duoc huy dong de thi cong hang muc du an. Anh: Huu Chanh
Machinery and workers are mobilized to speed up the project's progress. Photo: Huu Chanh
Mot so cong hop, vat lieu xay dung ngon ngang tren tuyen. Anh: Huu Chanh
Some box culverts and construction materials are scattered on the route. Photo: Huu Chanh
Diem cuoi du an tai nut giao voi Quoc lo 32. Anh: Huu Chanh
The end point of the project is at the intersection with National Highway 32. Photo: Huu Chanh
HỮU CHÁNH
TIN LIÊN QUAN

Signing the EPC general contractor contract for the Tu Lien bridge project, starting construction on May 19

|

Hanoi On May 18, the Hanoi Traffic Construction Investment Project Management Board signed a contract with the EPC general contractor to start the Tu Lien bridge project.

Tomorrow, Hanoi will start construction of a bridge worth more than 20,000 billion VND connecting Tay Ho with Dong Anh

|

Hanoi - The Tu Lien Bridge project and the approach roads at both ends of the Tay Ho bridge connecting Dong Anh, with an investment capital of more than 20,000 billion VND, will start construction tomorrow (May 19).

Hanoi starts construction of a road worth over VND2,000 billion, to be completed in 2027

|

Hanoi - The investment project to build the My Dinh - Ba Sao - Bai Dinh route is 12.5km long, with an investment capital of VND2,080 billion, expected to be completed after 2 years of construction.

The Golden Heart Social Charity Fund supports SGI Vina workers after the factory explosion

|

The Golden Heart Social Support Fund has donated 36 million VND to support 12 workers in distress in the explosion of a magnet factory in Chu Lai, Quang Nam.

Sacombank announces new General Director

|

Sacombank has just officially announced that Ms. Nguyen Duc Thach Diem will cease to be the General Director of this bank and announced senior personnel to replace her.

COVID-19 recurrence is normal, no need for isolation or testing

|

COVID-19's slight increase is a normal process, without the need for isolation or mass testing. People should not store testckets.

Signing the EPC general contractor contract for the Tu Lien bridge project, starting construction on May 19

Minh Hạnh |

Hanoi On May 18, the Hanoi Traffic Construction Investment Project Management Board signed a contract with the EPC general contractor to start the Tu Lien bridge project.

Tomorrow, Hanoi will start construction of a bridge worth more than 20,000 billion VND connecting Tay Ho with Dong Anh

HỮU CHÁNH - KHÁNH AN |

Hanoi - The Tu Lien Bridge project and the approach roads at both ends of the Tay Ho bridge connecting Dong Anh, with an investment capital of more than 20,000 billion VND, will start construction tomorrow (May 19).

Hanoi starts construction of a road worth over VND2,000 billion, to be completed in 2027

HỮU CHÁNH |

Hanoi - The investment project to build the My Dinh - Ba Sao - Bai Dinh route is 12.5km long, with an investment capital of VND2,080 billion, expected to be completed after 2 years of construction.