Removing the final “bottleneck” for the Central Highlands Connection project

Xuân Nhàn |

This morning, November 4, the Tay Son district government (Binh Dinh) mobilized security forces to construct package XL01, the project to enhance traffic connectivity in the Central Highlands region, through the two communes of Tay Giang and Tay Thuan.

As Lao Dong reported, the project to enhance traffic connectivity in the Central Highlands region (143km long, total investment capital of more than 3,654 billion VND, equivalent to 155.8 million USD, of which 150 million USD was borrowed from the World Bank) has been delayed many times, with 7/8 packages in Gia Lai completed. In particular, package XL01 - 17km through Tay Son, constructed by the North-Central-South Infrastructure Construction Joint Stock Company - is still sluggish. In addition to the complicated and strict technical requirements when constructing the An Khe pass section, the remaining reason is the fierce and persistent obstruction from some households.

The construction protection plan was approved by Chairman of Tay Son District People's Committee Phan Chi Hung, implemented on November 4-6, "naming" 3 locations: Km50 + 00 - Km50 + 460, Km50 + 460 - Km50 + 630, Km50 + 630 - Km50 + 940, namely Bau Sen bridge area, hamlet 1, Ta Giang 1 village, Tay Giang commune; Km52 + 460 - KM 52 +487 in hamlet 6, Thuong Giang 2 village, Tay Giang; Km56 + 000 - Km56 + 080, in front of Nui Da motel, hamlet 4, Trung Son village, Tay Thuan commune. At 3 locations, there are about 10 households that have not yet received compensation.

Previously, according to records from local authorities and contractors, the act of obstructing construction has recurred many times, in spontaneous and noisy forms such as gathering, pulling, kneeling, cursing, rolling in front of vehicles... The investor's representative, Deputy Director of Project Management Board 2 (Ministry of Transport) Le Minh Nam said: "The contractor has been directed to prepare materials, equipment, and human resources so that they can be deployed immediately when protected for construction."

The detailed plan is as follows: Morning of the first day: Construction of crushed stone aggregate at the head of Bau Sen bridge, asphalt concrete pavement 12.5 Km50 + 00 - Km50 +460 and Km50 + 630 - Km50 + 940. Afternoon: Pour concrete for the remaining part of the left access road of Bau Sen bridge A2. Morning of the second day, construction of a 27m long U-groove from Km52 + 460 - Km52 + 487, Thuong Giang 2 village, Tay Giang. Afternoon of the second day, implementation of compensation, asphalt concrete pavement 80m along with related items from Km56 + 000 - Km56 + 080 in front of Nui Da motel...

Chairman of Tay Son District People's Committee Phan Chi Hung directed: "The construction protection must be carried out publicly, democratically, objectively, ensuring order and safety, in accordance with regulations". Strengthening traffic connectivity in the Central Highlands region is a project that puts a lot of pressure on community life.

At the National Assembly forum, elected representatives of Binh Dinh and Gia Lai provinces continuously raised questions and recommendations. On October 17, 2024, the Ministry of Transport issued Document 11270/BGTVT-QLDTXD requesting the People's Committee of Binh Dinh province to "direct the complete resolution of existing problems and obstacles in site clearance work". On October 18, Vice Chairman of the People's Committee of Binh Dinh province Nguyen Tu Cong Hoang signed Document 8303/UBND-KT assigning the People's Committee of Tay Son district to "urgently develop a detailed and feasible plan, implement site clearance of all remaining problems, ensuring completion before November 5, 2024".

Xuân Nhàn
RELATED NEWS

Bumpy final stretch of road connecting the Central Highlands

|

After many extensions, the Central Highlands Transport Connectivity Enhancement Project is moving towards its target date of December 31, 2024. The “sprint” stage and efforts to speed up progress still face many challenges.

Central Highlands Connection: Nearly 100 households have not accepted compensation

|

Binh Dinh - The loan agreement is about to expire, but the Central Highlands Connection Project is still "stuck" with nearly 100 households.

"Last" dialogue on the Central Highlands connection project

|

Binh Dinh - More than 20 households in Tay Son district affected by the Central Highlands connection project have yet to receive compensation.

The huge Mid-Autumn Festival lantern worth hundreds of millions of VND lights up the streets of Tuyen Quang ward

|

Tuyen Quang - The Mid-Autumn Festival in Tuyen Quang is famous for its giant lanterns.

Do not let power projects get stuck due to delayed administrative procedures

|

The Deputy Prime Minister requested 3 corporations and 1 military enterprise to resolutely implement the power project and not to let the power project stall due to delayed administrative procedures.

Husband goes to work far away, wife stays at home, has an affair and has a child with another person - Part 1

|

The 9th hour - Husband leaves home to work far away, sending money to support the family. But in loneliness, his wife had an affair and became pregnant with someone else. What will happen to this family?

Vietnam continues to contribute to bringing peace at the Thailand - Cambodia border

|

Vietnam welcomes the positive developments between Cambodia and Thailand, and will continue to strive to contribute to bringing peace at the border between the two countries.

Vietnam General Confederation of Labor guides on collecting union funds

|

Grassroots trade unions are allowed to use 75% of total trade union budget revenue, according to the guidance document of the Vietnam General Confederation of Labor.

Bumpy final stretch of road connecting the Central Highlands

Xuân Nhàn |

After many extensions, the Central Highlands Transport Connectivity Enhancement Project is moving towards its target date of December 31, 2024. The “sprint” stage and efforts to speed up progress still face many challenges.

Central Highlands Connection: Nearly 100 households have not accepted compensation

Xuân Nhàn |

Binh Dinh - The loan agreement is about to expire, but the Central Highlands Connection Project is still "stuck" with nearly 100 households.

"Last" dialogue on the Central Highlands connection project

Xuân Nhàn |

Binh Dinh - More than 20 households in Tay Son district affected by the Central Highlands connection project have yet to receive compensation.