Removing the final “bottleneck” for the Central Highlands Connection project

Xuân Nhàn |

This morning, November 4, the Tay Son district government (Binh Dinh) mobilized security forces to construct package XL01, the project to enhance traffic connectivity in the Central Highlands region, through the two communes of Tay Giang and Tay Thuan.

As Lao Dong reported, the project to enhance traffic connectivity in the Central Highlands region (143km long, total investment capital of more than 3,654 billion VND, equivalent to 155.8 million USD, of which 150 million USD was borrowed from the World Bank) has been delayed many times, with 7/8 packages in Gia Lai completed. In particular, package XL01 - 17km through Tay Son, constructed by the North-Central-South Infrastructure Construction Joint Stock Company - is still sluggish. In addition to the complicated and strict technical requirements when constructing the An Khe pass section, the remaining reason is the fierce and persistent obstruction from some households.

The construction protection plan was approved by Chairman of Tay Son District People's Committee Phan Chi Hung, implemented on November 4-6, "naming" 3 locations: Km50 + 00 - Km50 + 460, Km50 + 460 - Km50 + 630, Km50 + 630 - Km50 + 940, namely Bau Sen bridge area, hamlet 1, Ta Giang 1 village, Tay Giang commune; Km52 + 460 - KM 52 +487 in hamlet 6, Thuong Giang 2 village, Tay Giang; Km56 + 000 - Km56 + 080, in front of Nui Da motel, hamlet 4, Trung Son village, Tay Thuan commune. At 3 locations, there are about 10 households that have not yet received compensation.

Previously, according to records from local authorities and contractors, the act of obstructing construction has recurred many times, in spontaneous and noisy forms such as gathering, pulling, kneeling, cursing, rolling in front of vehicles... The investor's representative, Deputy Director of Project Management Board 2 (Ministry of Transport) Le Minh Nam said: "The contractor has been directed to prepare materials, equipment, and human resources so that they can be deployed immediately when protected for construction."

The detailed plan is as follows: Morning of the first day: Construction of crushed stone aggregate at the head of Bau Sen bridge, asphalt concrete pavement 12.5 Km50 + 00 - Km50 +460 and Km50 + 630 - Km50 + 940. Afternoon: Pour concrete for the remaining part of the left access road of Bau Sen bridge A2. Morning of the second day, construction of a 27m long U-groove from Km52 + 460 - Km52 + 487, Thuong Giang 2 village, Tay Giang. Afternoon of the second day, implementation of compensation, asphalt concrete pavement 80m along with related items from Km56 + 000 - Km56 + 080 in front of Nui Da motel...

Chairman of Tay Son District People's Committee Phan Chi Hung directed: "The construction protection must be carried out publicly, democratically, objectively, ensuring order and safety, in accordance with regulations". Strengthening traffic connectivity in the Central Highlands region is a project that puts a lot of pressure on community life.

At the National Assembly forum, elected representatives of Binh Dinh and Gia Lai provinces continuously raised questions and recommendations. On October 17, 2024, the Ministry of Transport issued Document 11270/BGTVT-QLDTXD requesting the People's Committee of Binh Dinh province to "direct the complete resolution of existing problems and obstacles in site clearance work". On October 18, Vice Chairman of the People's Committee of Binh Dinh province Nguyen Tu Cong Hoang signed Document 8303/UBND-KT assigning the People's Committee of Tay Son district to "urgently develop a detailed and feasible plan, implement site clearance of all remaining problems, ensuring completion before November 5, 2024".

Xuân Nhàn
RELATED NEWS

Bumpy final stretch of road connecting the Central Highlands

|

After many extensions, the Central Highlands Transport Connectivity Enhancement Project is moving towards its target date of December 31, 2024. The “sprint” stage and efforts to speed up progress still face many challenges.

Central Highlands Connection: Nearly 100 households have not accepted compensation

|

Binh Dinh - The loan agreement is about to expire, but the Central Highlands Connection Project is still "stuck" with nearly 100 households.

"Last" dialogue on the Central Highlands connection project

|

Binh Dinh - More than 20 households in Tay Son district affected by the Central Highlands connection project have yet to receive compensation.

Hanoi Party Secretary requests drastic removal of urban bottlenecks

|

Hanoi - Hanoi Party Secretary Nguyen Duy Ngoc requests the Construction sector to thoroughly handle congestion, flooding, and urban bottlenecks.

Live football U23 Korea vs U23 Australia in the U23 Asian Cup quarter-finals

|

Live broadcast of the match between U23 Korea and U23 Australia in the quarter-finals of the 2026 AFC U23 Championship, taking place at 10:30 PM today (January 17).

Live football Man United vs Man City in the Premier League

|

Live football match Man United - Man City in round 22 of the Premier League, taking place at 7:30 PM on January 17 (Vietnam time).

15-year traffic jam at the eastern gateway of Ho Chi Minh City is about to be removed

|

Ho Chi Minh City - The bottleneck on National Highway 1, the section of the new Mien Dong Bus Station - Tan Van, is expected to be expanded from the end of 2026, helping to eliminate traffic jams at the eastern gateway.

Excavation of an ancient tomb nearly 2,000 years old in Quang Ninh

|

Quang Ninh - During the excavation of an ancient tomb nearly 2,000 years old in Vang Danh, Quang Ninh province, many important artifacts were discovered.

Bumpy final stretch of road connecting the Central Highlands

Xuân Nhàn |

After many extensions, the Central Highlands Transport Connectivity Enhancement Project is moving towards its target date of December 31, 2024. The “sprint” stage and efforts to speed up progress still face many challenges.

Central Highlands Connection: Nearly 100 households have not accepted compensation

Xuân Nhàn |

Binh Dinh - The loan agreement is about to expire, but the Central Highlands Connection Project is still "stuck" with nearly 100 households.

"Last" dialogue on the Central Highlands connection project

Xuân Nhàn |

Binh Dinh - More than 20 households in Tay Son district affected by the Central Highlands connection project have yet to receive compensation.