"Connecting the Central Highlands" is delayed again

Xuân Nhàn |

Binh Dinh - After many adjustments, the Central Highlands connection project has proposed to postpone its completion date until the end of the year.

Constantly late

The project to enhance traffic connectivity in the Central Highlands region (upgrading and expanding National Highway 19 through Gia Lai and Binh Dinh) has a length of 143.6 km, with a total investment of more than VND 3,654.4 billion (equivalent to USD 155.8 million), of which USD 150 million is borrowed from the World Bank (WB).

Construction started in June 2021, the project was initially committed to be completed in June 2023, but due to delays, it was adjusted to June 30, 2024.

Up to now, 7/8 packages of the project have reached the finish line. The remaining package - XL01 - is still unfinished and in disarray.

Joining the project 1 year later, XL01 is 17km long through Tay Son, Binh Dinh, including the An Khe pass section, which is the most difficult part.

In the recent extension, XL01 was allowed to be “extended” until October 31, 2024. The “target” was too much for the actual construction site, so it was not difficult to understand why it was… replaced by an official proposal from the contractor, Bac Trung Nam Infrastructure Construction Joint Stock Company. This time, the proposed completion date was postponed to December 31.

Vua thi cong, vua dam bao giao thong. Anh: Xuan Nhan.
Construction while ensuring traffic. Photo: Xuan Nhan.

Contractor's reason

XL01 is now 92% complete. Package manager Cao Van Hoa listed the remaining items: “C19, C12 asphalt concrete pavement; excavation and filling of 300m of special intersection on An Khe Pass; completion of drainage system, additional slope protection…”.

In the plains, through the two communes of Tay Thuan and Tay Giang, Mr. Hoa said that there are still about 20-30 households who have not agreed with the land clearance policy or objected to the results of the assessment of compensation for houses and properties damaged by construction impacts. Tay Giang is a "bottleneck" that has lasted for 2 years; where some households living near Bau Sen and Ba La bridges have shown no signs of stopping in their efforts to obstruct and slow down construction activities.

“Un tac nhu com bua“. Anh: Xuan Nhan.
“Traffic jams are a daily occurrence.” Photo: Xuan Nhan.

Mr. Hoa, who was just mobilized to the scene in September during the “troop increase, general change” of the North, Central and South (abbreviated), described the current situation: “We have lost tens of billions of dong due to broken progress. How can a contractor accept delays that waste money and affect their reputation? There are many unpredictable situations. An Khe Pass is a unique road, with high traffic density, many trucks weighing up to 60-100 tons, traffic jams happen like clockwork. We are struggling to work and ensure traffic flow at the same time.

The concrete pavement must be “torn apart” into 200-300m pieces instead of being continuous for kilometers. At special intersections, km 64+600, km 64+900, the process of breaking rocks, blasting, lowering the roadbed to a depth of 6-12m compared to the existing ground level, must strictly comply with the regulations of the authorities to ensure the safety of traffic participants below and the national power grid above. Blasting passports are issued in limited batches, 20kg of chemicals per day, if you want to be fast, you have to give up. Then there is the level of cooperation of the people, conflicts on forestry roads, the emergence of technical solutions to ensure safety”.

Ca tham be tong phai “lam lai tu dau“. Anh: Xuan Nhan.
The concrete floor had to be “remade from scratch”. Photo: Xuan Nhan.

Mr. Hoa admitted that the unit was subjective and “lack of focus” in the initial stages of implementing the package. There were times when the coordination with local authorities was not really in sync!

No way back

100 machines and equipment, 200 officers and workers present every day at the construction site are the noticeable changes in the XL 01 package in late October. “December 31 is the final deadline according to the loan agreement with the sponsor. There is no way back,” Director Cao Van Hoa expressed his determination.

Not only the contractor, the investor, Project Management Board 2, the Ministry of Transport also sent a deputy director to the "front line".

“Soi toi chon“, nguoi doi mu coi, dung giam sat la lanh dao Ban Quan ly du an 2, Bo Giao thong - Van tai. Anh: Xuan Nhan.
“Looking closely”, the person wearing a pith helmet, standing supervising is the leader of Project Management Board 2, Ministry of Transport. Photo: Xuan Nhan.

At km 62 + 600, where a part of the road surface is being cleaned and sprayed with adhesive before laying C19, the leader of Project Management Board 2, after a "red-faced" work discussion with the contractor and the consulting and supervisory team, turned to explain: "The day before yesterday, it rained while we were working, so I asked to stop. This morning, we have to start over, accepting the loss of tens of millions. We have to be quick but we cannot be careless, we are not allowed to make design mistakes or technical mistakes."

Mr. Le Ngoc Nam, Project Management Director, thinks that we should have a sympathetic view of the difficulties of the construction unit:

“North Central South Infrastructure Construction Joint Stock Company is a strong unit in the transportation industry. The company's name is associated with a series of major projects in the country such as the North-South Expressway, the Hanoi Ring Road 2 elevated railway, My Thuan 2 Bridge, Cai Lon Sluice, Rach Mieu 2 Bridge. XL01 is a package whose technical design and many items must be handled quite specially; much more difficult and complicated than other packages. The delay in progress is the result of many causes. Both the Project Management Board, the contractor and the local government are responsible”.

“Hop” o cong truong. Anh: Xuan Nhan.
"Meeting" at the construction site. Photo: Xuan Nhan.

Mr. Nam assessed: “This progress is also an effort. The construction site aims to basically complete the main items by October 31: Asphalt concrete paving, excavation and filling at the intersection, and opening of Ba La bridge. In addition, the Board is also considering adjusting the time for some items such as ensuring traffic safety...

In the meeting in early October, the project's difficulties and problems were listened to and noted by the sponsor.

Bua trua com hop o cong trinh. Anh Xuan Nhan
Lunch boxes for workers' quick lunches. Photo by Xuan Nhan

Below An Khe Pass, Ba La Bridge, after many times of being “inactive”, is now under construction. On the right, heading towards Phu Phong town, there is also a bustling atmosphere of construction of retaining walls, drainage systems, and access roads…

Mr. Hoa added: “1,085 households complaining about the damage to their houses and structures due to construction activities have all been assessed. 410 households have received compensation. The remaining will continue to be paid in October.”

Khoi phuc hoat dong thi cong tai “diem nghen” cau Ba La. Anh: Xuan Nhan.
Restoring construction activities at the "bottleneck" of Ba La bridge. Photo: Xuan Nhan.

The Central Highlands regional traffic connection project is witnessing a sprint. However, nothing can be said for sure. In Ta Giang 1 village, Tay Giang commune, while there is no longer any voice opposing the plan to establish a feeder road, people like Ms. Le Thi Bich Van, Mac Thi Do, and Vo Thi Kieu are still determined not to give in until they find a common voice with Project Management Board 2, the contractor, and the insurance company on the compensation value!

Xuân Nhàn
TIN LIÊN QUAN

The gap in education quality in the largest urban area in the Central Highlands

|

Buon Ma Thuot City is the central urban area of ​​the Central Highlands. However, the quality of education to train human resources for the future of this city is having a worrying gap.

Storm Tra Mi is about to strengthen, dangerous areas are forecast

|

This morning (October 23), the meteorological agency provided the latest forecast information on the intensity and path of storm Tra Mi.

The "big guys" mobilize the most bond capital

|

Banks continue to be a bright spot in the corporate bond market, with many banks leading the issuance volume across the market.

Quang Ninh strives to have the 6th city by 2025

|

Quang Ninh - As soon as authorized by the People's Committee of Quang Ninh province, Quang Yen town immediately started working to strive for Quang Yen to become a city by 2025.

Chronic patients hope to be provided with long-term health insurance drugs

|

The Ministry of Health is piloting the outpatient prescription of chronic diseases for a maximum of 90 days. In response to this information, many patients expressed their desire to receive long-term health insurance-covered drugs.

Lo River bank through Tuyen Quang eroded and devastated

|

Tuyen Quang - Many areas of fertile agricultural land in Cap Tien commune, Son Duong district are eroding every day into the Lo river, leaving farmers helpless.

Gold price update on the morning of October 23: Continuing to break new records

|

Gold price update on the morning of October 23: World gold is listed at an all-time high. Domestically, plain gold rings also skyrocketed.

Ho Chi Minh City announces land price list, people worry about high land use fees

|

Ho Chi Minh City People's Committee has just issued Decision 79 regulating the adjusted land price list to be applied from October 31 to December 31, 2025.

The gap in education quality in the largest urban area in the Central Highlands

Thanh Quỳnh |

Buon Ma Thuot City is the central urban area of ​​the Central Highlands. However, the quality of education to train human resources for the future of this city is having a worrying gap.

Tin sáng: Nguy cơ lũ quét, sạt lở diện rộng ở Tây Nguyên

NHÓM PV |

Tin sáng 22.9: Nguy cơ lũ quét, sạt lở diện rộng ở Tây Nguyên; Hơn 20 năm tù cho nhóm dùng gạch đập đầu đứa trẻ vì mâu thuẫn;...

Cao tốc nối Nam Trung Bộ - Tây Nguyên làm trước 2030

Xuyên Đông |

Chính phủ có chỉ đạo triển khai tuyến cao tốc nối Nam Trung Bộ - Tây Nguyên trước 2030.