"Last" dialogue on the Central Highlands connection project

Xuân Nhàn |

Binh Dinh - More than 20 households in Tay Son district affected by the Central Highlands connection project have yet to receive compensation.

Not stopping the lawsuit

The left side of Bau Sen bridge, in the direction of Phu Phong - An Khe, suddenly stopped in front of the house of Nguyen Ngoc Tam - Vo Thi Kieu (Ta Giang 1 village, Tay Giang commune). It marked the long-standing complaint that had not been completely resolved.

The incident occurred at the end of June 2024. In a petition sent to the Central Internal Affairs Committee, Ms. Vo Thi Kieu stated: Construction and upgrading activities on National Highway 19 caused cracks in the wall and the foundation of a 3-storey house to break. When the residential road (access road) opened, the construction vehicle hit part of the foundation of the house in front. The plaster ceiling fell off, the walls cracked...

Mot so doan chua the tham be tong be mat do bi can tro. Anh: Xuan Nhan.
Some sections cannot be paved with concrete due to obstruction. Photo: Xuan Nhan

In the minutes dated July 1, 2024, with the presence of representatives of local authorities, investors, and contractors, the parties agreed to temporarily suspend construction, request the insurance agency to appraise and assess the damage and find a satisfactory solution.

Ms. Kieu's family requested "compensation based on a percentage" (ie based on the actual level of damage - PV), while the solution they received was only to patch the cracked areas.

Ms. Vo Thi Kieu was upset: “The damage was from the foundation, pillars to walls, but the insurance company surveyed and gave a figure of 17 million VND. What can be done to restore the safety of my house?”

Hien truong ngon ngang. Anh: Xuan Nhan.
The scene was chaotic. Photo: Xuan Nhan

On the other side of Highway 19, another feeder road has not even started yet, even though all 10/10 households, after much persuasion, finally "agreed in principle".

There are 6 households that are dismantling part of their houses and structures and handing over the land; the remaining 4 households are still stubbornly protesting and have not received compensation, meaning they have not given up their intention to obstruct the remaining work of the project on both the main route and the service road.

Ready to protect construction

Mr. Cao Van Hoa, Executive Director of Package XL01, Central Highlands Regional Traffic Connection Project, section through Binh Dinh, said: “In the two communes of Tay Thuan and Tay Giang, there are 1,085 households complaining about damaged houses and structures. All have been assessed. 410 households have received compensation; the rest will be paid in October 2024.”

Vice Chairman of Tay Son District People's Committee Nguyen Van Khanh announced: "Time is running out. All compensation files must be closed by October 31. The district has handed over the main road and the service road. Within the framework of current regulations, we have flexibly applied whatever can support the people. Most of the people have responded."

Thi cong cau Ba La o “diem nghen” Tay Giang. Anh: Xuan Nhan.
Ba La Bridge, a long-standing “bottleneck” of the Central Highlands connectivity project. Photo: Xuan Nhan

However, some households continue to sue. Earlier this week, we held a dialogue and this is the last dialogue. If we cannot find a common voice, the government will be forced to apply construction protection measures, there is no other way," said Mr. Khanh.

The project to enhance traffic connectivity in the Central Highlands region (upgrading and expanding National Highway 19 through Gia Lai and Binh Dinh) has a length of 143.6km, with a total investment of more than VND 3,654.4 billion (equivalent to USD 155.8 million), of which USD 150 million is borrowed from the World Bank (WB).

Nhoc nhan luu thong, hinh anh quen thuoc moi ngay tren Quoc lo 19. Anh: Xuan Nhan.
Traffic congestion is a familiar daily scene on Highway 19. Photo: Xuan Nhan

After many delays, up to now, 7/8 packages in Gia Lai province have been completed. Package XL01, including 17km passing through 2 communes of Tay Giang and Tay Thuan, Tay Son district, Binh Dinh, has only completed 92% of the volume. The investor (Project Management Board 2, Ministry of Transport) and the construction unit (North Central South Infrastructure Construction Joint Stock Company) are proposing that the sponsor postpone the completion time from October 31 to December 31, 2024.

Xuân Nhàn
RELATED NEWS

"Connecting the Central Highlands" is delayed again

|

Binh Dinh - After many adjustments, the Central Highlands connection project has proposed to postpone its completion date until the end of the year.

Hanoi Party Secretary sets deadline for completion of "most expensive road on the planet

|

Hanoi - Regarding the progress of the Ring Road 1 project (Hoang Cau - Voi Phuc section), the Hanoi Party Secretary requested to complete the entire roadbed before September 2, 2026; complete the construction of 2 overpasses on the route before December 31, 2026.

Live volleyball VTV Binh Dien Long An vs Binh Chung Thong Tin

|

Live volleyball match between VTV Binh Dien Long An and Binh Chung Thong Tin, taking place at 5:30 PM today (April 18).

Complete the installation of medical equipment at facility 2 of Bach Mai and Viet Duc Hospitals before June 30

|

Ninh Binh - The investor of Bach Mai Hospital and Viet Duc Friendship Hospital facility 2 project committed to complete the installation of equipment before June 30.

Salary reform from the Central to local levels, implemented in all 3 blocs

|

The Ministry of Home Affairs is assigned to carefully prepare the reform of salaries, allowances and other regimes from the Central to local levels, implemented in all 3 blocs.

Forecast of the risk of receiving strong storms and super typhoons in 2026

|

According to a representative of the meteorological agency, ENSO phase transition along with the impact of climate change leads to the risk of strong storms and super typhoons in 2026.

Circus of nearly 1,400 billion VND, the most modern in Ho Chi Minh City opens for visitors

|

Ho Chi Minh City - For the first time, people can visit and experience the modern architectural space of Phu Tho Multi-purpose Circus and Performance.

Designer Duc Hung: For me, ao dai is perfectly beautiful, it needs to be promoted all over the world

|

In the program "Saturday Afternoon Coffee", designer Duc Hung shared his perspective on Vietnamese fashion in the context of cultural industry development.

"Connecting the Central Highlands" is delayed again

Xuân Nhàn |

Binh Dinh - After many adjustments, the Central Highlands connection project has proposed to postpone its completion date until the end of the year.

Bụi bẩn bủa vây cư dân dọc Quốc lộ 19

Xuân Nhàn |

Hàng nghìn xe tải chở đất cát, vật liệu xây dựng nối đuôi, xoay vòng mỗi ngày trên Quốc lộ 19, đoạn qua An Nhơn, Tây Sơn (Bình Định) đã nhấn chìm cư dân ven đường trong những “trận đồ bụi bặm”.

1.156 hộ dân bị hư hại tài sản do thi công Quốc lộ 19

Xuân Nhàn |

Dự án thi công Quốc lộ 19 đoạn qua huyện Tây Sơn, tỉnh Bình Định gây ra những hậu quả không ngờ tới.