"Last" dialogue on the Central Highlands connection project

Xuân Nhàn |

Binh Dinh - More than 20 households in Tay Son district affected by the Central Highlands connection project have yet to receive compensation.

Not stopping the lawsuit

The left side of Bau Sen bridge, in the direction of Phu Phong - An Khe, suddenly stopped in front of the house of Nguyen Ngoc Tam - Vo Thi Kieu (Ta Giang 1 village, Tay Giang commune). It marked the long-standing complaint that had not been completely resolved.

The incident occurred at the end of June 2024. In a petition sent to the Central Internal Affairs Committee, Ms. Vo Thi Kieu stated: Construction and upgrading activities on National Highway 19 caused cracks in the wall and the foundation of a 3-storey house to break. When the residential road (access road) opened, the construction vehicle hit part of the foundation of the house in front. The plaster ceiling fell off, the walls cracked...

Mot so doan chua the tham be tong be mat do bi can tro. Anh: Xuan Nhan.
Some sections cannot be paved with concrete due to obstruction. Photo: Xuan Nhan

In the minutes dated July 1, 2024, with the presence of representatives of local authorities, investors, and contractors, the parties agreed to temporarily suspend construction, request the insurance agency to appraise and assess the damage and find a satisfactory solution.

Ms. Kieu's family requested "compensation based on a percentage" (ie based on the actual level of damage - PV), while the solution they received was only to patch the cracked areas.

Ms. Vo Thi Kieu was upset: “The damage was from the foundation, pillars to walls, but the insurance company surveyed and gave a figure of 17 million VND. What can be done to restore the safety of my house?”

Hien truong ngon ngang. Anh: Xuan Nhan.
The scene was chaotic. Photo: Xuan Nhan

On the other side of Highway 19, another feeder road has not even started yet, even though all 10/10 households, after much persuasion, finally "agreed in principle".

There are 6 households that are dismantling part of their houses and structures and handing over the land; the remaining 4 households are still stubbornly protesting and have not received compensation, meaning they have not given up their intention to obstruct the remaining work of the project on both the main route and the service road.

Ready to protect construction

Mr. Cao Van Hoa, Executive Director of Package XL01, Central Highlands Regional Traffic Connection Project, section through Binh Dinh, said: “In the two communes of Tay Thuan and Tay Giang, there are 1,085 households complaining about damaged houses and structures. All have been assessed. 410 households have received compensation; the rest will be paid in October 2024.”

Vice Chairman of Tay Son District People's Committee Nguyen Van Khanh announced: "Time is running out. All compensation files must be closed by October 31. The district has handed over the main road and the service road. Within the framework of current regulations, we have flexibly applied whatever can support the people. Most of the people have responded."

Thi cong cau Ba La o “diem nghen” Tay Giang. Anh: Xuan Nhan.
Ba La Bridge, a long-standing “bottleneck” of the Central Highlands connectivity project. Photo: Xuan Nhan

However, some households continue to sue. Earlier this week, we held a dialogue and this is the last dialogue. If we cannot find a common voice, the government will be forced to apply construction protection measures, there is no other way," said Mr. Khanh.

The project to enhance traffic connectivity in the Central Highlands region (upgrading and expanding National Highway 19 through Gia Lai and Binh Dinh) has a length of 143.6km, with a total investment of more than VND 3,654.4 billion (equivalent to USD 155.8 million), of which USD 150 million is borrowed from the World Bank (WB).

Nhoc nhan luu thong, hinh anh quen thuoc moi ngay tren Quoc lo 19. Anh: Xuan Nhan.
Traffic congestion is a familiar daily scene on Highway 19. Photo: Xuan Nhan

After many delays, up to now, 7/8 packages in Gia Lai province have been completed. Package XL01, including 17km passing through 2 communes of Tay Giang and Tay Thuan, Tay Son district, Binh Dinh, has only completed 92% of the volume. The investor (Project Management Board 2, Ministry of Transport) and the construction unit (North Central South Infrastructure Construction Joint Stock Company) are proposing that the sponsor postpone the completion time from October 31 to December 31, 2024.

Xuân Nhàn
RELATED NEWS

"Connecting the Central Highlands" is delayed again

|

Binh Dinh - After many adjustments, the Central Highlands connection project has proposed to postpone its completion date until the end of the year.

The secret to helping Vietnamese karate fighters overcome Thailand

|

Boxer Khuat Hai Nam defeated host Thailand to win the gold medal for Vietnamese karate at the 33rd SEA Games.

Kim Chung CT3 social housing application is paid in large numbers due to lack of salary table photos for the whole company

|

Hanoi - On December 12, many people who came to submit documents at the CT3 Kim Chung social housing project had their documents returned due to the lack of photocopy of the salary table of the whole company.

Lieutenant General Le Van Huong holds the position of Deputy Chief of the General Staff of the People's Army

|

Lieutenant General Le Van Huong - Director of the Department of Military Affairs, General Staff was appointed to the position of Deputy Chief of the General Staff of the Vietnam People's Army.

Strong cold air is about to arrive, the North will have heavy rain, severe cold, some places below 5 degrees Celsius

|

Due to the impact of strong cold air, the mountainous and midland areas of the North will be very cold, with some mountainous areas experiencing severe cold with temperatures below 5 degrees Celsius.

Traffic police officers tell the moment the violator pushed him into the front of the truck

|

Hanoi - The subject was suddenly pushed from behind, fortunately the traffic police officers promptly reacted and avoided the danger.

Officials will receive money if they do not use up their annual leave

|

Officials will be paid a sum of money for days off according to the internal spending regulations of the unit and in accordance with the financial capacity of the unit.

SEA Games 33 Medal Schedule on December 12

|

Updated total medal table of the 33rd SEA Games on December 13.

"Connecting the Central Highlands" is delayed again

Xuân Nhàn |

Binh Dinh - After many adjustments, the Central Highlands connection project has proposed to postpone its completion date until the end of the year.

Bụi bẩn bủa vây cư dân dọc Quốc lộ 19

Xuân Nhàn |

Hàng nghìn xe tải chở đất cát, vật liệu xây dựng nối đuôi, xoay vòng mỗi ngày trên Quốc lộ 19, đoạn qua An Nhơn, Tây Sơn (Bình Định) đã nhấn chìm cư dân ven đường trong những “trận đồ bụi bặm”.

1.156 hộ dân bị hư hại tài sản do thi công Quốc lộ 19

Xuân Nhàn |

Dự án thi công Quốc lộ 19 đoạn qua huyện Tây Sơn, tỉnh Bình Định gây ra những hậu quả không ngờ tới.