"Last" dialogue on the Central Highlands connection project

Xuân Nhàn |

Binh Dinh - More than 20 households in Tay Son district affected by the Central Highlands connection project have yet to receive compensation.

Not stopping the lawsuit

The left side of Bau Sen bridge, in the direction of Phu Phong - An Khe, suddenly stopped in front of the house of Nguyen Ngoc Tam - Vo Thi Kieu (Ta Giang 1 village, Tay Giang commune). It marked the long-standing complaint that had not been completely resolved.

The incident occurred at the end of June 2024. In a petition sent to the Central Internal Affairs Committee, Ms. Vo Thi Kieu stated: Construction and upgrading activities on National Highway 19 caused cracks in the wall and the foundation of a 3-storey house to break. When the residential road (access road) opened, the construction vehicle hit part of the foundation of the house in front. The plaster ceiling fell off, the walls cracked...

Mot so doan chua the tham be tong be mat do bi can tro. Anh: Xuan Nhan.
Some sections cannot be paved with concrete due to obstruction. Photo: Xuan Nhan

In the minutes dated July 1, 2024, with the presence of representatives of local authorities, investors, and contractors, the parties agreed to temporarily suspend construction, request the insurance agency to appraise and assess the damage and find a satisfactory solution.

Ms. Kieu's family requested "compensation based on a percentage" (ie based on the actual level of damage - PV), while the solution they received was only to patch the cracked areas.

Ms. Vo Thi Kieu was upset: “The damage was from the foundation, pillars to walls, but the insurance company surveyed and gave a figure of 17 million VND. What can be done to restore the safety of my house?”

Hien truong ngon ngang. Anh: Xuan Nhan.
The scene was chaotic. Photo: Xuan Nhan

On the other side of Highway 19, another feeder road has not even started yet, even though all 10/10 households, after much persuasion, finally "agreed in principle".

There are 6 households that are dismantling part of their houses and structures and handing over the land; the remaining 4 households are still stubbornly protesting and have not received compensation, meaning they have not given up their intention to obstruct the remaining work of the project on both the main route and the service road.

Ready to protect construction

Mr. Cao Van Hoa, Executive Director of Package XL01, Central Highlands Regional Traffic Connection Project, section through Binh Dinh, said: “In the two communes of Tay Thuan and Tay Giang, there are 1,085 households complaining about damaged houses and structures. All have been assessed. 410 households have received compensation; the rest will be paid in October 2024.”

Vice Chairman of Tay Son District People's Committee Nguyen Van Khanh announced: "Time is running out. All compensation files must be closed by October 31. The district has handed over the main road and the service road. Within the framework of current regulations, we have flexibly applied whatever can support the people. Most of the people have responded."

Thi cong cau Ba La o “diem nghen” Tay Giang. Anh: Xuan Nhan.
Ba La Bridge, a long-standing “bottleneck” of the Central Highlands connectivity project. Photo: Xuan Nhan

However, some households continue to sue. Earlier this week, we held a dialogue and this is the last dialogue. If we cannot find a common voice, the government will be forced to apply construction protection measures, there is no other way," said Mr. Khanh.

The project to enhance traffic connectivity in the Central Highlands region (upgrading and expanding National Highway 19 through Gia Lai and Binh Dinh) has a length of 143.6km, with a total investment of more than VND 3,654.4 billion (equivalent to USD 155.8 million), of which USD 150 million is borrowed from the World Bank (WB).

Nhoc nhan luu thong, hinh anh quen thuoc moi ngay tren Quoc lo 19. Anh: Xuan Nhan.
Traffic congestion is a familiar daily scene on Highway 19. Photo: Xuan Nhan

After many delays, up to now, 7/8 packages in Gia Lai province have been completed. Package XL01, including 17km passing through 2 communes of Tay Giang and Tay Thuan, Tay Son district, Binh Dinh, has only completed 92% of the volume. The investor (Project Management Board 2, Ministry of Transport) and the construction unit (North Central South Infrastructure Construction Joint Stock Company) are proposing that the sponsor postpone the completion time from October 31 to December 31, 2024.

Xuân Nhàn
RELATED NEWS

"Connecting the Central Highlands" is delayed again

|

Binh Dinh - After many adjustments, the Central Highlands connection project has proposed to postpone its completion date until the end of the year.

Hanoi Secretary sets deadline for site clearance for Ring Road 4 project

|

Hanoi - Secretary of the City Party Committee Nguyen Duy Ngoc requested that no later than December 31, 2025, the site must be handed over to the construction unit of the Ring Road 4 project.

Hour 9: Love gambling - Part 1

|

Hour 9 No. 178 - A successful couple but apart, both husband and wife have a "third person". How will they face this marriage tragedy?

Dak Lak bans ships from going out to sea before storm No. 15

|

Dak Lak - Chairman of the People's Committees of coastal communes and wards announced a ban on ships going out to sea and fishing activities at sea, before storm No. 15.

Tomorrow night, storm No. 15 Koto will encounter increased cold air, forecast for upcoming developments

|

Storm No. 15 is still likely to strengthen in the next 24 hours when moving in warm ocean waters.

The new land price list in Hanoi takes effect from January 1, 2026, highest at 702 million VND/m2

|

Hanoi officially applied the new land price list from January 1, 2026, an increase of 2-26% compared to the current land price list.

Two men risked their lives to save hundreds of people during the fierce flood night

|

Dak Lak - Amid the imminent danger, two men risked their lives by rowing a boat to save hundreds of people, becoming a life-and-death support for the whole village in the fierce flood.

Deputy Prime Minister requests to work day and night to fight against counterfeit goods

|

The Deputy Prime Minister requested continuous, regular, and tireless deployment with the spirit of "working day, working night, working extra days off" to fight counterfeit goods.

"Connecting the Central Highlands" is delayed again

Xuân Nhàn |

Binh Dinh - After many adjustments, the Central Highlands connection project has proposed to postpone its completion date until the end of the year.

Bụi bẩn bủa vây cư dân dọc Quốc lộ 19

Xuân Nhàn |

Hàng nghìn xe tải chở đất cát, vật liệu xây dựng nối đuôi, xoay vòng mỗi ngày trên Quốc lộ 19, đoạn qua An Nhơn, Tây Sơn (Bình Định) đã nhấn chìm cư dân ven đường trong những “trận đồ bụi bặm”.

1.156 hộ dân bị hư hại tài sản do thi công Quốc lộ 19

Xuân Nhàn |

Dự án thi công Quốc lộ 19 đoạn qua huyện Tây Sơn, tỉnh Bình Định gây ra những hậu quả không ngờ tới.