Compensation progress for the trillion-dong project to renovate 5 Can Tho intersections

YẾN PHƯƠNG |

Can Tho - Compensation for intersections No. 1 and No. 4 has reached a high rate, and the contractor selection work has also been completed. The project is expected to start construction in this quarter.

The investment project to build, renovate and expand 5 key intersections in Ninh Kieu district was approved by the People's Committee of Can Tho City in November 2023, with a total investment of more than 1,196 billion VND.

The 5 renovated intersections include: intersection No. 1 (Mau Than - 3 February - Tran Hung Dao); intersection No. 2 (Mau Than - Nguyen Van Cu - Vo Van Kiet); intersection No. 3 (Nguyen Van Linh - Nguyen Van Cu); intersection No. 4 (Nguyen Van Linh - 3 February) and intersection No. 5 (Nguyen Van Linh - 30/4).

Anh: Ta Quang
Intersection No. 1 (Mau Than - 3 Thang 2 - Tran Hung Dao) in Ninh Kieu District, Can Tho City. Photo: Ta Quang

The project implementation period is from 2021 to 2025. In particular, the two intersections with high traffic volume, intersection No. 1 and intersection No. 4, will be prioritized for implementation first.

Mr. Tran Ngoc Thai - Deputy Director of the Project Management and Land Fund Development Board of Ninh Kieu District - informed that the initial plan was to start construction at intersection No. 1 and intersection No. 4 in the fourth quarter of 2024. However, due to the implementation of the new Land Law, the appraisal of land prices and compensation plans for the project takes a lot of time.

The People's Committee of Ninh Kieu District will pay compensation to households in early December 2024, while the activities to celebrate the Lunar New Year of At Ty will begin in mid-January 2025, so it is not possible to request people to hand over the site before Tet to start construction as planned.

To overcome this situation, the People's Committee of Ninh Kieu District has directed relevant units to strengthen coordination, promptly resolve problems, and at the same time promote propaganda and mobilize people to hand over the site for the project.

Anh: Ta Quang
Intersections have a lot of traffic. Photo: Ta Quang

According to the leader of the Ninh Kieu District Project Management and Land Fund Development Board, the No. 1 intersection has an estimated compensation cost of about 578 billion VND. The total number of households affected by the project is about 122 cases, with more than 480 people. The total area of recovered land is about 5,960m2.

Up to now, intersection No. 1 has paid compensation to 18/28 cases, reaching 52.91% of approved funding; at the same time, it has completed the work of counting, measuring land, houses, architectural objects and announcing land recovery.

Intersection No. 4 has an estimated compensation cost of about 96.5 billion VND. To date, compensation has been paid to 28/31 households, reaching 81% of the approved budget; the work of counting, measuring land, houses, architectural objects and announcing land recovery has been completed; the announcement of site allocation has been implemented to 29 households.

Anh: Ta Quang
The project is expected to start construction in the first quarter of 2025. Photo: Ta Quang

Currently, the selection of construction contractors at intersections No. 1 and No. 4 has been completed. Of which, the construction cost of intersection No. 1 is more than 38.5 billion VND; intersection No. 4 is more than 35.5 VND. The project is expected to start construction in the first quarter of 2025.

The project investment scale consists of 2 phases. In which, phase 1 expands the intersection to the same level, controls with traffic lights, and arranges independent right turns. In the future, phase 2 will consider arranging overpasses or underpasses according to traffic needs.

The project to renovate and expand 5 key intersections is of great significance in reducing traffic congestion, improving traffic capacity, contributing to improving urban aesthetics and promoting the socio-economic development of Ninh Kieu district in particular and Can Tho city in general.

YẾN PHƯƠNG
TIN LIÊN QUAN

Upgrading many central routes of Can Tho

|

Can Tho - The urgent construction atmosphere is covering many central roads of the city, aiming to bring a new look to the city.

New look of Provincial Road 921 in Can Tho

|

Can Tho - After being expanded and paved with asphalt concrete, Provincial Road 921 has been completed, bringing a new, spacious and clean appearance to the locality.

For illegal land exploitation to occur, commune leaders are responsible

|

Quang Tri - The leader of the People's Committee of Quang Tri province affirmed that the leaders of that area must take responsibility for any illegal land exploitation in the area.

Resolving the issue of exemption and reduction of land use fees for NIC

|

The meeting gave opinions on completing relevant regulations to resolve the issue of exemption and reduction of land use fees and land rents for NIC.

Hour 9: returning day - Part 1

|

The 9th hour - Today's story is about a young couple struggling to make a living, facing challenges, loss and regret. Will love help them find happiness again?

LPB Ninh Binh won the Information Corps at Hoa Lu Cup 2025

|

On the evening of March 5, LPB Ninh Binh won 3-2 against the Information Corps at the Hoa Lu Cup 2025 volleyball tournament.

Over 12 banks have reduced deposit interest rates

|

8 commercial banks "received" the investment interest rate for some terms at the beginning of the year after the Lunar New Year when many people deposited money.

Difficulty in liquidation makes redundant offices become abandoned houses

|

Quang Nam - The transfer and liquidation of abandoned offices and land is facing many obstacles due to improper use and regulations.

Upgrading many central routes of Can Tho

YẾN PHƯƠNG |

Can Tho - The urgent construction atmosphere is covering many central roads of the city, aiming to bring a new look to the city.

New look of Provincial Road 921 in Can Tho

YẾN PHƯƠNG |

Can Tho - After being expanded and paved with asphalt concrete, Provincial Road 921 has been completed, bringing a new, spacious and clean appearance to the locality.

Hiện trạng 2/5 nút giao sẽ được ưu tiên cải tạo, mở rộng ở Cần Thơ

Tạ Quang |

Cần Thơ – Nút giao 1 (Mậu Thân - 3/2 - Trần Hưng Đạo) và nút giao 4 (Nguyễn Văn Linh - 3/2) sẽ được ưu tiên thực hiện trước.