Nearly 2,000 billion VND road in Soc Trang is 12% behind schedule

PHƯƠNG ANH |

Soc Trang - Started construction in January 2022, to date, the East-West economic development axis has reached 78% of the contract value, 12% behind schedule.

According to the reporter's records on December 13, despite the heavy rain, at the construction site of the East-West economic development axis road passing through Nga Nam town, Thanh Tri district, My Xuyen and Vinh Chau town (Soc Trang province), contractors, engineers and workers were working hard, striving to open the technical traffic by the end of this year.

The representative of Project Management Board 2 (Soc Trang province) - the project investor - said that after more than 2 years of construction, the cumulative construction and installation value to date is estimated at about 1,158/1,487.4 billion VND (excluding contingency costs), reaching 78% of the contract value.

The total capital allocated from the beginning of the project to date is 1,589 billion VND, disbursed 1,369 billion VND, reaching 86.1%. Assessing the progress according to the direction of the People's Committee of Soc Trang province (technical traffic opening on December 31, 2024), the whole project is 12% behind schedule.

Nha thau thi cong tren tuyen duong truc phat trien kinh te Dong Tay. Anh: Phuong Anh
Contractors working on the East-West economic development axis. Photo: Phuong Anh

Explaining the reason for the delay, the leader of Project Management Board 2 said that due to the scarcity of aggregate (0x4) and crushed stone materials used for asphalt pavement construction, high prices, some contractors have encountered many difficulties in finding sources of supply because they are implementing many highway projects and key national traffic projects, leading to insufficient road construction materials to supply the market. This has resulted in a prolonged implementation time, lack of volume, and slow disbursement compared to the plan.

At the construction inspection on December 13, Secretary of Soc Trang Provincial Party Committee Lam Van Man emphasized that this is a key project, completed to celebrate the Soc Trang Provincial Party Congress and is very important for the socio-economic development of the locality.

In 2024, the leaders of the Provincial Party Committee and the Provincial People's Committee have repeatedly inspected the progress and promptly removed difficulties for the construction unit; the contractor has also committed to achieving the plan, but so far the progress has not been met.

Ong Lam Van Man (thu 2 tu phai sang) - Bi thu Tinh uy Soc Trang de nghi cac nha thau khan truong thi cong, hoan thanh cong trinh dung han. Anh: Phuong Anh
Mr. Lam Van Man (2nd from right) - Secretary of Soc Trang Provincial Party Committee - requested contractors to urgently construct and complete the project on time. Photo: Phuong Anh

The leaders of Soc Trang Provincial Party Committee requested contractors to mobilize more machinery, equipment, and supplies, especially aggregate stone; increase construction teams, and speed up implementation progress on the entire route.

“By December 31, 2024, the entire route must be completed with graded stone. By March 2025, the road surface and normal roadbed must be completed; unloading of bridges that can be unloaded must be completed. By May 2025, the contract must be completed and the entire route opened to traffic,” the Secretary of the Soc Trang Provincial Party Committee requested the contractors.

The East-West economic development axis route is over 56 km long. The total investment is nearly 2,000 billion VND from the central budget and local budget counterpart. After being put into use, the project will connect the entire western region of Soc Trang province, directly connecting with Quan Lo Phung Hiep National Highway, Nam Song Hau National Highway and National Highway 1A - forming an internal and external traffic axis serving the socio-economic development of Soc Trang province and neighboring areas.

PHƯƠNG ANH
TIN LIÊN QUAN

Cars parked everywhere on sidewalks and roads in Hai Phong

|

Hai Phong - Although Hai Phong City has directed to handle illegal parking, many of these situations still recur, especially at the end of the year.

Road construction is behind schedule, people are miserable because of dust

|

Hanoi - Ngo Thi Sy Street (Ha Dong) has been renovated for many years but is not yet completed. People are miserable because of the dust affecting their lives.

A railway overpass costing nearly 300 billion is under construction in Hanoi

|

Hanoi - Some items of the National Highway 1A overpass and North-South railway project (Thuong Tin district), with a capital of nearly 300 billion VND, are gradually taking shape after more than half a year of construction.

After the merger, the largest province in Vietnam will be 10 times the smallest province

|

After the merger, the newly formed provinces of Lam Dong, Dak Nong and Binh Thuan will become the largest province, with tourism resources from mountains and forests to seas and islands.

Citi raises gold price forecast, many signals of new price increase cycle

|

Citi Research raised its gold price forecast for the next 3 months to $3,500/ounce due to China's purchases and safe-haven demand.

"Tu Dap" Quang Tuan talks about his first time acting in a film with million-dollar actor Thai Hoa

|

Actor Quang Tuan first collaborated with his senior Thai Hoa in the film "Tunnel: Sun in the dark".

Russia declares temporary ceasefire with Ukraine

|

On the evening of April 19, Russian President Vladimir Putin announced a 30-hour humanitarian ceasefire with Ukraine on the occasion of the holiday.

The Ministry of Home Affairs clarifies the allowances included in salary when officials quit their jobs

|

The Ministry of Home Affairs has responded to readers about determining allowances to calculate the regime for cadres, civil servants and public employees when streamlining.

Cars parked everywhere on sidewalks and roads in Hai Phong

Hoàng Khôi |

Hai Phong - Although Hai Phong City has directed to handle illegal parking, many of these situations still recur, especially at the end of the year.

Road construction is behind schedule, people are miserable because of dust

Đền Phú |

Hanoi - Ngo Thi Sy Street (Ha Dong) has been renovated for many years but is not yet completed. People are miserable because of the dust affecting their lives.

A railway overpass costing nearly 300 billion is under construction in Hanoi

HỮU CHÁNH |

Hanoi - Some items of the National Highway 1A overpass and North-South railway project (Thuong Tin district), with a capital of nearly 300 billion VND, are gradually taking shape after more than half a year of construction.