The North-South Expressway Project is recommended to be limited to 1 supplier

Xuyên Đông |

Regarding the package of the North - South expressway project, there are recommendations that the package has limited criteria for one supplier.

Lao Dong Newspaper has just informed: "A package of the North - South expressway project received many recommendations after winning the bid".

Accordingly, on May 27, 2025, Mr. Le Minh Nam, Deputy Director of Project Management Board 2 (Ministry of Construction) signed a decision approving the results of the online contractor selection of the TB01 package: Procurement and installation of equipment for the ITS, ETC and KTTTX systems (including construction drawing design). This is one of the packages of the North - South expressway project.

On the national bidding network, there are recommendations for the item requiring "synchronization", items 234, 235, 236 of the reference document: part 2, "technical requirements".

The required content is as follows:

The petition on the national bidding network stated:

"These requirements are likely to limit goods to only one supplier, making it difficult for contractors to meet, leading to high equipment prices and maintenance costs.

Technically, these are also unreasonable requirements:

The device switches, routes, and core switch operates on the network based on network communication standards, routes, and security protocols, not based on the brand name. What is the reason for requiring "synchronization" from a manufacturer?

While network devices have hundreds of large manufacturers, section 236, "weight sensitive devices in lanes" and "balanced data collection and processing ministries" require a supplier/producer.

In the Vietnamese market, there is currently only one manufacturer that meets the requirements, Kists. Is this a limitation of Kisten's goods for the project?

In addition, there are 1-3 suppliers for the lane weighing sensors, but there are many manufacturers for the weighing processors, up to a few dozen in Europe/USA/Asia.

The new balancing processor is the center of the KTTTX system (ectification accounting, software features, maintenance and operation experience), and is responsible for the accuracy of F10 measurements.

Why is there a limit to songronization here? to eliminate other legal suppliers in the world, limit to one supplier/ Manufacturer Kists? ".

In addition to opinions on contractor limitation factors, this package also received recommendations for key personnel positions. The opinion in the document is as follows:

"The officer in charge of Information Security" the bidding documents are required to "have a certificate/certificate/confirmation of available training valid at the time of bidding for governance or a solution or technology of the security equipment manufacturer (fire panels) offered in this bidding package or a commitment from the manufacturer to guide the training".

This opinion said that, at other bidding packages such as: Package No. 20: Supply and install equipment equipment System of traffic supervision System Project Investment Investment component of Phan Thiet - Dau Giay section under the investment project to build some high -speed road sections on the North - South route in the East period 2017-2020 and Package No. 32: Supply and installation of transportation systems for construction and construction projects. The number of highways on the North -South route in the East period 2017-2020 "The investor abandoned that request".

From this evidence, the contractor recommended: request the investor to remove the requirement for the above training certificate/certificate/confirmation.

Xuyên Đông
TIN LIÊN QUAN

Will make recommendations to higher level if the investor intentionally eliminates the highway project contractor

|

Regarding the bidding package of the expressway project, a contractor commented that if the bidding party intentionally selects the type of contractor, it will resolutely propose to a higher level.

The case of a candidate whose supervisor delayed the competency assessment test time, VNU-HCM spoke up

|

HCMC - Ho Chi Minh City National University (VNU-HCM) has had initial handling results in the case of candidates being late for the second round of the competency assessment test (GAP).

Japanese spacecraft fails again, risk of disruption to international cooperation

|

On June 6, a Japanese-made moon landing ship had a problem and crashed while trying to land, with the producer officially declaring the mission a failure.

A restaurant in Dak Nong accuses commune and town officials of owing money for 9 years without paying

|

Dak Nong - A restaurant in Dak R'lap district accused the officers of the People's Committees of communes and towns of owing nearly 180 million VND in rice and water for 9 years but still have not paid.

Will make recommendations to higher level if the investor intentionally eliminates the highway project contractor

Xuyên Đông |

Regarding the bidding package of the expressway project, a contractor commented that if the bidding party intentionally selects the type of contractor, it will resolutely propose to a higher level.

Thi công Cao tốc Đồng Đăng - Trà Lĩnh gặp khó vì giá cát tăng mạnh

An Khánh |

Lạng Sơn - Mỏ cát, sỏi Hùng Sơn liên tục điều chỉnh giá bán trong thời gian ngắn khiến nhiều doanh nghiệp xây dựng và người dân tại huyện Tràng Định điêu đứng.