Hanoi leaders have directed that the My Dinh ICD dry port project is still slow to be implemented

Nhóm phóng viên |

Although the leaders of Hanoi City requested to start construction before June 30, 2025, the My Dinh ICD dry port project is still inactive.

The current status of the My Dinh ICD dry port project in the old Duc Thuong commune was recorded by a reporter from Lao Dong Newspaper at the end of July and the beginning of August 2025. Video: PV Group

Declining, slow progress for many years

In March 2025, Lao Dong Newspaper published an article "The unfinished wharf has signs of leasing" reflecting on the My Dinh ICD wharf project in the old Duc Thuong commune, now Hoai Duc commune (hereinafter referred to as the wharf project) invested by International Investment, Trade and Service Joint Stock Company (ILS).

At that time, according to the reporter's survey, the current status of the project was almost still an empty lot, with only a part of the land in the project for machinery, materials and a welcome gate with the words "My Dinh ICD Wharf Port". Here, the reporter did not see any construction moves taking place.

Du an van chi la bai dat trong. Anh: Nhom PV
Many areas of land are abandoned. Photo: PV Group

Faced with this situation, the leaders of Hanoi City held a meeting to review and resolve the difficulties and problems of the project and requested the project to start construction before June 30, 2025.

However, by the end of July and early August, according to the reporter's records, there had been no improvement in the current status of the dry port project.

Grass is still growing wildly, water flooded the entire path, entering and exiting the project site. Construction materials are piled up and lying around.

Loi vao khu dat du an cang can ICD My Dinh. Anh: Nhom PV
Entrance to the dry port project land (images recorded at the end of July 2025). Photo: PV Group

The dry port project has been stalled for many years. On the website of International Investment, Trade and Service Joint Stock Company (ILS), it is introduced: The My Dinh ICD dry port project has an area of 18 hectares. Capacity: 150,000 TEUs. Total investment: VND 1,704 billion

On January 6, 2017, ILS held a groundbreaking ceremony for the project. At that time, the company said the project progress was as follows:

Phase 1: Complete and put into use in 2018 the following items: Yard, inspection house, external warehouse, CFS warehouse, refrigerated warehouse, distribution warehouse, office, security system... with an area of over 10 hectares.

Phase 2: Complete the remaining construction items, complete construction investment to put the entire project into operation in 2020.

Hien trang ngon ngang o du an cang can ICD My Dinh. Anh: Nhom PV
The current state of chaos at the dry port project. Photo: PV Group

It was once expected to be a new customs clearance location for businesses with a full system of standard warehouses: export warehouses, CFS warehouses, refrigeration warehouses, e-commerce warehouses, offices of customs authorities, shipping lines... However, the project has become a real disappointment and frustration for local people.

Failure to comply with the direction of Hanoi City

At a working session with reporters at the end of March 2025, Mr. Trieu Van Bang - Deputy General Director of Interserco - ILS International Investment, Trade and Service Joint Stock Company said that the project has cleared more than 99%. Basically, we have no problems, but regarding the site clearance progress, there are things that need to be done according to the correct process, said Mr. Bang.

Ong Trieu Van Bang - Pho Tong Giam doc Cong ty co phan Dau tu thuong mai va dich vu quoc te (Interserco - ILS) trong cuoc trao doi voi PV Lao Dong thang 3 nam 2025. Anh: Nhom PV
Mr. Trieu Van Bang - Deputy General Director of Interserco International Investment, Trade and Services Joint Stock Company ( Interserserco - ILS) in an interview with Lao Dong reporter in March 2025. Photo: PV Group

On July 28, PV continued to contact ILS to find out why the project had not yet started, an officer of this unit said that the project "is following the progress of relevant parties. This is also related to the progress of departments and branches in handling procedures. The unit is still following that".

The reporter also contacted the Department of Construction and the Hanoi Department of Finance to clarify the incident. However, after many contacts, the leaders of ILS company and the authorities have not yet responded.

In fact, regarding the settlement of problems for the project, the authorities have issued very specific instructions before. In particular, regarding compensation and site clearance, in mid-March 2025, the leaders of Hanoi City assigned local agencies to speed up compensation and site clearance, review and agree with Hanoi Electricity Corporation to resolve problems regarding site clearance funding for the 3 legs of the 110 KV power pole in the project land, and report to the Department of Industry and Trade for synthesis, consultation, proposal and reporting to the City People's Committee.

Request to complete compensation and site clearance before April 30, 2025.

The Department of Agriculture and Environment urgently has a document contributing to the appraisal of the dossier to adjust the investment policy for the dry port construction investment project to the Department of Finance for synthesis and reporting to the City People's Committee according to regulations (requiring the project to be completed no later than 2027).

After the decision to adjust the investment policy for the dry port project is approved, the Departments of Agriculture and Environment and Construction are assigned to guide investors to urgently deploy and complete land procedures and construction permits according to regulations.

The leaders of the City People's Committee emphasized the need for investors to focus resources, send a document to the Department of Finance to commit to the progress of the investment project, to start the investment project before June 30, 2025 and complete it no later than 2027.

Cang can ICD My Dinh khong the khoi cong dung tien do theo chi dao cua TP Ha Noi. Anh: Nhom PV
The dry port project has not seen any new construction. Photo: PV Group

Thus, it can be seen that, although there have been clear instructions from the Hanoi City government on the time of construction (after many delays), the dry port project has not yet seen any construction moves.

Many opinions say that it is necessary to consider the investor's capacity, problems and difficulties related to the project and take strong measures to avoid wasting land resources.

Nhóm phóng viên
RELATED NEWS

Hanoi leaders issue a letter of attainment for 2 dry port projects

|

Hanoi - Lao Dong Newspaper has just reported that 2 dry port projects at ICD My Dinh in Hoai Duc and ICD Co Bi have been approved for many years but are slow to be implemented.

Removing dry port bottlenecks to break through Vietnam's logistics

|

Thanks to the efforts of the Government and businesses, the Vietnamese logistics industry has developed strongly, enhancing the national position. However, to become a regional logistics center, it is necessary to focus on infrastructure development, especially unblocking dry port bottlenecks.

Dry port project in Hoai Duc abandoned for many years

|

The ICD My Dinh dry port project in Hoai Duc, Hanoi has been approved for nearly 10 years but has not been completed. However, the project's land has shown signs of lease.

Deputy Prime Minister Ho Duc Phoc works with Hung Yen on socio-economic development

|

Hung Yen - On the afternoon of August 12, Deputy Prime Minister Ho Duc Phoc worked with Hung Yen province on removing difficulties and promoting economic growth.

Bich Tuyen's new move when wanting to reduce risks in the lawsuit with Dam Vinh Hung

|

The civil lawsuit between singer Dam Vinh Hung and billionaire Gerard Williams in the US has just had a new development.

The secret inside the huge convoy of sand trucks running from Quang Tri to Hue

|

Quang Tri - Inside the huge tractor-trailers covered with tarpaulins was a huge amount of sand. Despite signs of violating the load, this type of vehicle still circulates successfully on many routes.

Hanoi leaders have directed that the My Dinh ICD dry port project is still slow to be implemented

|

Although the leaders of Hanoi City requested to start construction before June 30, 2025, the My Dinh ICD dry port project is still inactive.

South Korea awaits verdict on arrest of former First Lady

|

The five-hour hearing did not yet reach a final decision on the arrest of former First Lady of South Korea Kim Keon Hee.

Hanoi leaders issue a letter of attainment for 2 dry port projects

NHÓM PV |

Hanoi - Lao Dong Newspaper has just reported that 2 dry port projects at ICD My Dinh in Hoai Duc and ICD Co Bi have been approved for many years but are slow to be implemented.

Removing dry port bottlenecks to break through Vietnam's logistics

Anh Vân Trường |

Thanks to the efforts of the Government and businesses, the Vietnamese logistics industry has developed strongly, enhancing the national position. However, to become a regional logistics center, it is necessary to focus on infrastructure development, especially unblocking dry port bottlenecks.

Dry port project in Hoai Duc abandoned for many years

Nhóm phóng viên |

The ICD My Dinh dry port project in Hoai Duc, Hanoi has been approved for nearly 10 years but has not been completed. However, the project's land has shown signs of lease.