Many investors in Dak Nong disburse capital at 0 VND

BẢO LÂM |

Dak Nong is facing many challenges in disbursing public investment capital. Currently, there are 6 investors recording 0 VND disbursement.

Mr. Nguyen Ngoc Duc, Deputy Director of the Dak Nong Department of Finance, said that in 2025, Dak Nong province will allocate VND 4,098 billion in public investment capital. Of which, more than VND422 billion in capital in 2024 was transferred.

According to Mr. Duc, up to now, the province has only disbursed more than 430 billion VND, reaching more than 11%. Of which, local budget capital has only disbursed nearly 17% of the plan; central budget capital has reached more than 9%; the central budget has supported with a target of more than 5.6%; ODA capital has only reached more than 3% of the plan.

For the above capital of VND422 billion, only VND43 billion has been disbursed, reaching more than 10% of the plan.

It is worth mentioning that there are currently 6 investors disbursing 0 VND including the Department of Education and Training; Department of Culture, Sports and Tourism; Provincial Youth Union; Provincial Party Committee's Organization Committee; Political School and Community College.

Mr. Nguyen Ngoc Duc further informed about the disbursement situation in some key projects. Accordingly, the Dao Nghia - Quang Khe road project, phase 2, has a total investment of 830 billion VND.

In 2025, VND 285.4 billion has been allocated, but to date, the investor has not had any disbursement data. In package 17 of the project, the site has not been handed over...

For the Dak Nong General Hospital project, with a total investment of 753 billion VND, in 2025, 270.4 billion VND will be allocated, but only more than 3.8 billion VND has been disbursed, reaching more than 1.4% of the plan.

The Gia Nghia City Central Square project, with a total investment of 400 billion VND, in 2025, has allocated 140.8 billion VND but has only disbursed more than 1 billion VND, reaching more than 1% of the capital plan.

Also in 2025, Dak Nong province has allocated 88.9 billion VND for a relocation and resettlement project for 212 households in the central area of Gia Nghia city. Up to now, this item has been included but there are no disbursement figures...

According to Mr. Duc, the reason for the projects not ensuring progress is due to many difficulties in providing fill soil. Some investors are slow to complete documents and carry out payment procedures with the treasury.

In addition, during the implementation process, the projects also encountered many difficulties in site clearance. In particular, payment policies for people in affected areas have changed.

The competent authorities have not yet established an appraisal and approval for crops exceeding the density, encroached land that does not meet the compensation conditions.

On the other hand, there are also cases where people do not cooperate in measuring, receiving compensation for site clearance or people have received compensation but have not yet handed over the site for construction.

"The responsibility belongs to investors and People's Committees of districts and cities that are not proactive and determined in implementing the task of disbursing public investment capital" - Mr. Duc added.

BẢO LÂM
TIN LIÊN QUAN

Many key projects have met the conditions for public investment disbursement

|

The Ministry of Finance has just submitted to the Government a series of solutions to promote the disbursement of public investment capital, ensuring the progress of key projects.

Despite advantages, public investment disbursement in Dak Nong is still slower than expected

|

Dak Nong - Despite many advantages, the progress of public investment disbursement in Dak Nong is still slow.

Can Tho outlines 3 major projects that need to focus on disbursing public investment capital

|

Can Tho - 3 major projects include: Renovation of the remaining 7km of National Highway 91, Chau Doc - Can Tho - Soc Trang Expressway, Western Ring Road...

Starting construction of a bridge worth nearly 500 billion VND to solve traffic congestion in the South of Ho Chi Minh City

|

HCMC - This morning (September 10), the new Rach Tom bridge with an investment capital of nearly 500 billion VND has officially started construction, hoping to solve traffic congestion in the South of HCMC.

The crisis of Lang Ha Thuc summer camp from the way MC Minh Trang apologizes

|

In recent days, Hanh Hung Village, a famous summer camp model, has faced an unprecedented media crisis after negative feedback from parents.

Mr. Trump sends more letters to many countries, promotes tariff agreements

|

President Trump continues to put trade pressure on many countries with letters announcing new tax rates expected to be applied.

Metro No. 2 construction site is bustling after 100% of the site is clean

|

HCMC - Metro Line 2 project has completed site clearance and is urgently constructing the relocation of technical infrastructure, aiming to start construction in December 2025.

Difficulty in clearing the channel to 2 fishing ports that are silted up, boats stranded

|

Ha Tinh - The channel to Thach Kim Fishing Port and Cua Nhuong Fishing Port is silted up, causing ships and boats to strand when the tide goes down.

Many key projects have met the conditions for public investment disbursement

Lục Giang |

The Ministry of Finance has just submitted to the Government a series of solutions to promote the disbursement of public investment capital, ensuring the progress of key projects.

Despite advantages, public investment disbursement in Dak Nong is still slower than expected

BẢO LÂM |

Dak Nong - Despite many advantages, the progress of public investment disbursement in Dak Nong is still slow.

Can Tho outlines 3 major projects that need to focus on disbursing public investment capital

Tạ Quang |

Can Tho - 3 major projects include: Renovation of the remaining 7km of National Highway 91, Chau Doc - Can Tho - Soc Trang Expressway, Western Ring Road...