These include 14 wind power projects, 3 waste-to-energy projects, 1 biomass power project and 5 centralized solar power projects, with a total capacity of about 5,160 MW.
For wind power projects, there are 9 wind power projects on and near the shore, located in many localities, from Ha Long to Binh Lieu, Ba Che, Mong Cai, Co To, with a total capital of more than 30,800 billion VND.
5 offshore wind power projects in the Gulf of Tonkin have not yet determined their location and investment capital.
Meanwhile, 3 waste-to-energy projects are located in Ha Long, Uong Bi, Cam Pha, with a total investment of about VND3,000 billion, total capacity of 30 MW.
The thermal power project is planned in Tien Yen and Ba Che districts, with an investment capital of about VND900 billion and a capacity of 40 MW.
5 solar power projects in Ha Long, Mong Cai, Dong Trieu, Dam Ha, total investment capital of VND 5,850 billion, total capacity of 390 MW.
Except for wind power projects offshore the Gulf of Tonkin that have not yet had a plan to connect to national grid power lines and the expected operation period of 2031-2035, the remaining projects have a plan to connect to national grid power lines and the expected operation period is from 2025 - 2030.
The People's Committee of Quang Ninh province assigns relevant departments, branches, sectors and local People's Committees to be responsible for fully announcing and publicizing the List of power projects attracting investment in Quang Ninh province for the period 2025 - 2030, with a vision to 2050. Implement the completion of legal requirements for construction planning layers to be ready to invite investors; update, supplement, and complete information on power source projects to adjust power planning VIII in the province...
Currently, in Quang Ninh province, there are 7 thermal power plants with a total capacity of 5,640 MW, located in Dong Trieu, Uong Bi, Cam Pha and Ha Long.