Risk of missing the scheduled opening date for the Bien Hoa - Vung Tau expressway

HÀ ANH CHIẾN |

Dong Nai - The risk of not completing the technical traffic of the Bien Hoa - Vung Tau Expressway Component 1 project on December 19 is very high.

On November 10, Chairman of Dong Nai Provincial People's Committee Vo Tan Duc issued a document requesting Mr. Dinh Tien Hai - Deputy Director in charge, Mr. Nguyen Linh - Deputy Director of the Provincial Construction Investment Project Management Board - to directly direct, operate and take full responsibility before the Provincial Party Committee, the Provincial People's Committee and the Chairman of the Provincial People's Committee for the progress, quality, volume and effectiveness of the implementation of the Bien Hoa - Vung Tau Expressway Component 1 project.

The project progress is assessed by the Department of Construction, the current volume is only 51.52% of the contract value, 24.86% behind schedule and 12.48% behind component project 2 invested by Project Management Board 85, especially the volume of land for roadbed filling is still very large, about over 800,000m3.

Du an thanh phan 1 cao toc Bien Hoa - Vung Tau. Anh tu lieu: HAC
Component project 1 of Bien Hoa - Vung Tau Expressway. Documentary photo: HAC

The investor and contractor have not yet had a solution, the risk of not completing the project's technical traffic opening on December 19 as directed by the Prime Minister is very high.

The leaders of the Provincial Party Committee and the Provincial People's Committee have repeatedly affirmed that the completion of the project's technical traffic before December 19, 2025 is a political responsibility, an honor and prestige of Dong Nai province before the Prime Minister and the Ministry of Construction.

The Chairman of Dong Nai Provincial People's Committee also requested the Project Management Board to urgently add additional subcontractors, direct contractors to increase machinery, equipment, gather materials, and labor to speed up construction to compensate for the delayed progress.

At the same time, direct contractors to strictly ensure traffic at existing overpass locations, construction material transport routes, ensure traffic safety, and environmental sanitation.

For the Ho Chi Minh City Ring Road 3 construction project, the construction progress of the 3 packages has reached nearly 51% of the contract value (slow compared to the plan). Therefore, the People's Committee of Dong Nai province requested the Provincial Construction Investment Project Management Board to continue directing contractors to increase human resources, equipment, organize "3 shifts, 4 teams" to complete on schedule, complete the relocation of 8 high-voltage power pole locations in November...

The leaders of the Provincial People's Committee assigned the Department of Home Affairs to monitor and evaluate the capacity, sense of responsibility and the results of the implementation of tasks of the two deputy heads of the Provincial Construction Investment Project Management Board.

HÀ ANH CHIẾN
TIN LIÊN QUAN

Extinguishing the fire at a kindergarten in Dong Nai

|

Dong Nai - The Fire Prevention and Rescue Force of the Provincial Police extinguished the fire at the kindergarten in Nhon Trach commune.

Dong Nai generates nearly 2,700 tons of household waste every day

|

Dong Nai - According to a report by the Department of Agriculture and Environment, the whole province currently generates nearly 2,700 tons of household waste per day.

More than 600 cases of alcohol concentration violations were handled after 1 week of deployment in Dong Nai

|

Dong Nai - The Traffic Police force in the whole province recorded 636 cases of alcohol concentration violations, 118 driver's licenses were revoked and 610 vehicles were temporarily detained.

Extinguishing the fire at a kindergarten in Dong Nai

HÀ ANH CHIẾN |

Dong Nai - The Fire Prevention and Rescue Force of the Provincial Police extinguished the fire at the kindergarten in Nhon Trach commune.

Dong Nai generates nearly 2,700 tons of household waste every day

HÀ ANH CHIẾN |

Dong Nai - According to a report by the Department of Agriculture and Environment, the whole province currently generates nearly 2,700 tons of household waste per day.

More than 600 cases of alcohol concentration violations were handled after 1 week of deployment in Dong Nai

MINH CHÂU |

Dong Nai - The Traffic Police force in the whole province recorded 636 cases of alcohol concentration violations, 118 driver's licenses were revoked and 610 vehicles were temporarily detained.