On January 12, continuing the series of sunny days, Tan Hai Son Construction Joint Stock Company (Thanh Sen ward) is focusing on asphalting the section expanding to the sidewalk of Nguyen Du street in Thanh Sen ward.
The contractor focusing on asphalt paving construction makes people living on the side of the road very excited. Because Tet Nguyen Dan is approaching, the completion of the road to ensure aesthetics and convenient travel is very important to them.
According to a representative of Tan Hai Son Construction Joint Stock Company, in the past time, the unit has made great efforts to implement the project. However, due to complicated weather dien bien, many prolonged rains have greatly affected the construction progress of the unit.
Currently, taking advantage of favorable weather, the unit is focusing on construction with the determination to complete asphalt paving in about a week; then proceed to draw lines, place signs and complete the handover of the project in January 2026.

The project to renovate and upgrade sidewalks and technical infrastructure of Nguyen Du street (section from Tran Phu street to Nguyen Cong Tru street) is 1.4km long.
The project was approved by the old Ha Tinh City People's Committee according to Decision 3176 dated December 27, 2022, and then adjusted in Decision 2577 dated November 6, 2024.
The project deploys items to expand the road surface, repave asphalt concrete on the road surface, arrange median strips, submerge electrical and cable systems, and install transformer stations.

Previously, during construction, Nguyen Du street during peak hours often experienced traffic jams, causing many people to be upset.
On the afternoon of January 12, a leader of the Project Management Board for Investment and Construction of Transport Works and Urban Development of Ha Tinh said that the project to renovate and upgrade sidewalks and the technical infrastructure system of Nguyen Du street was once behind schedule, and was later adjusted and extended.
Up to this point, the project has entered the final construction phase. According to the plan, it will be completed in January 2026 to ensure convenient travel for people and ensure urban aesthetics during the Binh Ngo Lunar New Year.