In 2 months, the Hau River overpass girder will be installed for Dai Ngai 2 bridge.

PHƯƠNG ANH |

It is expected that in November 2024, the contractor will install the girder of Dai Ngai 2 bridge .

According to Project Management Board 85 (Ministry of Transport), the project investor informed that up to now, the total value of the Dai Ngai Bridge project's construction output is 633.73/1,543.19 billion VND, reaching 41.1%. 39% of the roadbed construction work and 31% of the drainage wick installation work have been completed.
According to Project Management Board 85 (Ministry of Transport) - the investor of Dai Ngai Bridge project, the value of construction output to date is 633.73/1,543.19 billion VND, reaching 41.1%. 39% of the roadbed construction and 31% of the drainage wick installation have been completed.

Of which, Dai Ngai 2 bridge (crossing Hau river, connecting Cu Lao Dung with the mainland on the Soc Trang province side) has completed 90% of the substructure and 20% of the cantilever span volume. Construction output is over 50%.

Of which, Dai Ngai 2 bridge (crossing Hau river, connecting Cu Lao Dung with the mainland on the Soc Trang province side) has completed 90% of the substructure and 20% of the cantilever span volume. Construction output is over 50%.
Currently, contractors have increased their work to 3 shifts, day and night, to maintain 24/7 construction.
Currently, contractors are increasing their work to 3 shifts to maintain 24/7 construction.
Mr. Nguyen Tien Dung - Project Manager, Dat Phuong Group Joint Stock Company said that it is expected that in November 2024, the girder installation will be carried out, the bridge will be held at the end of April 2025 and the entire bridge will be completed in 2025.
Mr. Nguyen Tien Dung - Project Manager, Dat Phuong Group Joint Stock Company said that Dai Ngai 2 Bridge has now completed 15/15 bridge piers and is speeding up the construction of super T girders at the girder casting yard to start installing bridge girders by November this year, striving to basically complete the span structure by May 2025, and complete the entire Dai Ngai 2 Bridge in 2025.
According to Project Management Board 85, contractors have mobilized 275 personnel, 97 machines and equipment of various types, and deployed 18 construction teams.
According to Project Management Board 85, currently the contractors have mobilized 275 personnel, 97 machines and equipment of various types, and deployed 18 construction teams.
It's been raining heavily these days, but the construction workers are not discouraged. They all focus on their work so that the project can be completed on schedule.
It's been raining heavily these days, but the construction workers are not discouraged. They all focus on their work so that the project can be completed on schedule.
Workers worked enthusiastically day and night to complete the project on schedule.
Workers worked enthusiastically day and night to complete the project on schedule.
The Dai Ngai Bridge project has a total investment of more than 8,000 billion VND, with a total length of more than 15km. Of which, there are 2 main overpasses, including Dai Ngai Bridge 1 and Dai Ngai Bridge 2, connecting Tra Vinh and Soc Trang provinces. When completed, the project will help open the entire National Highway 60, helping the coastal provinces of the Mekong Delta shorten the distance from Ho Chi Minh City by nearly 80km.
The Dai Ngai Bridge project has a total length of more than 15km, including two main bridges crossing the Hau River, Dai Ngai 1 Bridge and Dai Ngai 2 Bridge, connecting Tra Vinh and Soc Trang provinces. The total cost is nearly VND8,000 billion. When completed, the project will help open the entire National Highway 60, helping the coastal provinces of the Mekong Delta shorten the distance from Ho Chi Minh City by about 80km.
PHƯƠNG ANH
TIN LIÊN QUAN

Sửa cầu trên cao tốc TPHCM - Long Thành, ùn tắc khó tránh

MINH QUÂN |

Từ ngày 5.9, cầu Long Thành - cây cầu lớn nhất trên tuyến cao tốc TPHCM - Long Thành - Dầu Giây sẽ bước vào giai đoạn sửa chữa kéo dài trong 18 ngày.

Cầu 1500 tỉ đồng nối Bắc Giang - Hải Dương sắp thông xe

Vân Trường |

Bắc Giang - Sau hơn 2 năm thi công, đến nay, cầu Đồng Việt đã sắp hoàn thành, dự kiến thông xe kỹ thuật trong tháng 9 này.

Cầu vượt sông Đào ở Nam Định trước ngày hợp long

Lương Hà |

Hoàn thành được khoảng 95% khối lượng, cầu Đống Cao vượt sông Đào ở Nam Định dự kiến hợp long trong dịp đầu tháng 9.2024.

Người dân TPHCM thích thú khi tận mắt thấy hàng trăm siêu xe

Anh Tú - Thanh Vũ |

TPHCM - Ngày 14.9, Hành trình Gumball 3000 đã diễn ra ở đường Lê Lợi, Quận 1 thu hút hàng ngàn người đến chiêm ngưỡng 120 siêu xe từ nhiều nước trên thế giới.

Ngôi làng quanh năm tô vẽ, tạo tiếng trống dịp Tết Trung thu

Thanh Bình - Khánh Linh |

Làng nghề ông Hảo (xã Liêu Xá, huyện Yên Mỹ, tỉnh Hưng Yên) là nơi khai sinh của nhiều món đồ chơi Trung thu cổ truyền.

Làm từ thiện không trung thực là vi phạm đạo đức, pháp luật

NHÓM PV |

PGS.TS Phạm Ngọc Trung đã có những chia sẻ xung quanh câu chuyện về tình người và vấn đề làm từ thiện sau cơn bão số 3.

Chưa đóng cửa mỏ vàng cũ, đã giao đất để làm mỏ vàng mới

HƯNG THƠ |

Công ty trây ỳ trả lại đất ở mỏ vàng A Pey A được tỉnh Quảng Trị cho thuê đất để thực hiện dự án mỏ vàng A Vao.

Đình chỉ 2 chủ tịch xã ở Lào Cai do lơ là phòng chống bão lũ

Bảo Nguyên |

UBND huyện Bát Xát, tỉnh Lào Cai vừa ra quyết định đình chỉ công tác đối Chủ tịch UBND xã Trung Lèng Hồ và Pa Cheo do vi phạm quy định phòng, chống bão lũ.