The hundred billion industrial cluster in Thai Nguyen is in ruins

Việt Bắc |

Thai Nguyen - After more than 5 years of implementation, the Ba Xuyen Industrial Cluster project (Song Cong City) with a total investment of over 431 billion VND is still unfinished, falling into ruin .

Ba Xuyen Industrial Cluster (Ba Xuyen Industrial Park) was implemented at the end of 2018 with a total investment of over 431 billion VND. Minh Tuan Construction Investment and Trading Joint Stock Company is the Investor.
Ba Xuyen Industrial Cluster (Ba Xuyen Industrial Park) was implemented at the end of 2018 with a total investment of over 431 billion VND. The investor is Minh Tuan Construction Investment and Trading Joint Stock Company.
2
Ba Xuyen Industrial Park has a scale of nearly 50 hectares, located in a prime location next to Provincial Road 262, surrounded by dense residential areas. To implement this project, more than 400 households in Ba Xuyen commune had residential and agricultural land recovered.

Recorded on August 26, after more than 5 years of implementation, Ba Xuyen Industrial Complex is still just an unfinished, desolate area of ​​land.
Recorded on August 26, after more than 5 years of implementation, Ba Xuyen Industrial Complex is still just an unfinished, desolate area of ​​land.
Inside the project, there are no workers and construction vehicles, while construction materials are scattered and weeds are overgrown.
Inside the project, there are no workers and construction vehicles, while construction materials are scattered and weeds are overgrown.
At the project, no items have been completed yet. The drainage system and internal roads are unfinished, falling into a state of sun, dust, and muddy rain.
At the project, no items have been completed yet. The drainage system and internal roads are unfinished, falling into a state of sun, dust, and muddy rain.
According to local people, construction at the project has stopped long ago, the construction site is almost abandoned.
According to local people, construction at the project has stopped long ago, the construction site is almost abandoned.
8
After every rain, many areas at the project become muddy and unkempt.
Mr. Nguyen Van Toan (Ba Xuyen commune, Song Cong city) said that when the Ba Xuyen Industrial Park project began implementation, people were very happy and expected to have jobs right in the locality. But now, more than 5 years later, the industrial cluster is still unfinished, and it is unknown when it will be completed.
Mr. Nguyen Van Toan (Ba Xuyen commune, Song Cong city) said that when the Ba Xuyen Industrial Park project began implementation, people were very happy and expected to have jobs right in the locality. But now, more than 5 years later, the industrial cluster is still unfinished, and it is unknown when it will be completed.
"Many unfinished items, sewer pipes, and deep holes that hold water after heavy rain are not covered, and warning signs are placed, which are very dangerous, especially for young children," Mr. Toan said.
"Many unfinished items, sewer pipes, and deep holes that hold water after heavy rain are not covered, and warning signs are placed, which are very dangerous, especially for young children," Mr. Toan said.
Bdnd
On August 26, talking to reporters, Mr. Do Trong Lu - Chairman of Ba Xuyen Commune People's Committee said that after many years of implementing the Ba Xuyen Industrial Park project, it still cannot be completed.
As expected, the Ba Xuyen Industrial Complex project will have to be completed by the end of 2024, but due to problems with legal documents and the project's recent land allocation, it cannot be completed. Currently, the investor is making a written request to the competent authority to extend the implementation until 2026.
As expected, the Ba Xuyen Industrial Complex project will have to be completed by the end of 2024, but due to problems with legal documents and the project's recent land allocation, it cannot be completed. Currently, the investor is making a written request to the competent authority to extend the implementation until 2026.

Việt Bắc
TIN LIÊN QUAN

Hoang tàn dự án nhà máy sản xuất ôtô ở tỉnh nghèo nhất nước

Văn Tùng |

Dù được đầu tư 42 tỉ đồng nhưng Nhà máy sản xuất ôtô Tralas (TP Bắc Kạn) vẫn không thể hoạt động sau gần 20 năm, rơi vào cảnh hoang tàn và được chuyển đổi thành xưởng gỗ bóc gây lãng phí tài nguyên đất, ô nhiễm môi trường.

Hoang tàn bên trong dự án nông nghiệp trăm tỉ ở Thái Nguyên

Lam Thanh |

Sau 6 năm triển khai, Dự án Trung tâm Nông nghiệp ứng dụng công nghệ cao tại TP. Thái Nguyên vẫn hoang tàn, một số hạng mục xuống cấp nghiêm trọng.

Hoang tàn dự án nghìn tỉ bên bờ sông Cầu

Phong Quang |

Thái Nguyên - Dự án xây dựng cấp bách hệ thống chống lũ lụt kết hợp hoàn thiện hạ tầng đô thị hai bên bờ sông Cầu (TP. Thái Nguyên) với tổng mức đầu tư hơn 18.221 tỉ đồng đã rơi vào tình trạng đắp chiếu từ năm 2019 và đến nay những dấu tích còn lại của đại dự án này chỉ là sự hoang tàn, xuống cấp.

Xe tải bốc cháy ngùn ngụt trên cao tốc Vĩnh Hảo - Phan Thiết

Duy Tuấn |

Bình Thuận - Xe tải đang lưu thông thì bốc cháy ngùn ngụt trên cao tốc Vĩnh Hảo - Phan Thiết.

Tin 20h: Yên Bái kiểm tra nhà hàng "chặt chém" đoàn từ thiện

Nhóm PV |

Tin 20h ngày 19.9: Bà Nguyễn Phương Hằng được ra tù vào hôm nay; Yên Bái kiểm tra nhà hàng bị tố chặt chém đoàn từ thiện...

Phía Miss Universe nói về thông tin Kỳ Duyên chưa tốt nghiệp

Huyền Chi |

Thông tin Hoa hậu Kỳ Duyên chưa tốt nghiệp Trường Đại học Ngoại Thương gây xôn xao mạng xã hội.

Thể Công Tân Cảng bảo vệ thành công chức vô địch giải bóng chuyền U23 Quốc gia 2024

Nhóm PV |

U23 Thể Công Tân Cảng thắng U23 Ninh Bình 3-1 tại chung kết giải bóng chuyền U23 quốc gia vào tối 19.9.

Chậu hoa giấy trên phố đi bộ ở Đà Nẵng đồng loạt "nằm" tránh bão

Nguyễn Linh |

UBND quận Hải Châu, TP Đà Nẵng cho biết đã chủ động đặt nằm các chậu hoa giấy tại phố đi bộ Bạch Đằng để tránh thiệt hại bởi ảnh hưởng của cơn bão số 4.

Desolate car factory project in the poorest province in the country

Văn Tùng |

Despite an investment of 42 billion VND, the Tralas Automobile Factory (Bac Kan City) still cannot operate after nearly 20 years, falling into ruin and being converted into a peeling wood factory, wasting land and air resources. environmental contamination.

Hoang tàn bên trong dự án nông nghiệp trăm tỉ ở Thái Nguyên

Lam Thanh |

Sau 6 năm triển khai, Dự án Trung tâm Nông nghiệp ứng dụng công nghệ cao tại TP. Thái Nguyên vẫn hoang tàn, một số hạng mục xuống cấp nghiêm trọng.

Hoang tàn dự án nghìn tỉ bên bờ sông Cầu

Phong Quang |

Thái Nguyên - Dự án xây dựng cấp bách hệ thống chống lũ lụt kết hợp hoàn thiện hạ tầng đô thị hai bên bờ sông Cầu (TP. Thái Nguyên) với tổng mức đầu tư hơn 18.221 tỉ đồng đã rơi vào tình trạng đắp chiếu từ năm 2019 và đến nay những dấu tích còn lại của đại dự án này chỉ là sự hoang tàn, xuống cấp.