13 BT projects in Khanh Hoa are stuck in planning

Hữu Long |

Khanh Hoa province has 13 BT (build - transfer) projects that are stuck in the process of contract implementation. Due to long-term problems and difficulties in removing them from the grassroots, Khanh Hoa has reported to the Central agencies for guidance.

Many projects have not been paid under BT contracts

3 BT projects include the Ring Road connecting Ngoc Hoi intersection; Ngoc Hoi intersection; routes and intersections connecting Nha Trang airport area. The common problem lies in the land fund used to recover capital for the BT project in the old Nha Trang airport area.

According to the authorities, in order to have a basis to specifically adjust the area, name, symbol, and value of each plot of land recovered for the BT project according to the conclusion of the Government Inspectorate, the Area Consolidation Planning Project must be approved and the value of the land fund of the old Nha Trang airport area must be determined.

However, up to now, the Regional Planning Project has not been updated and adjusted; there has not been a consensus with the Ministry of National Defense on zoning planning. Because there is no basis to determine the value of the counterpart land fund; there is no basis to adjust BT contracts according to the conclusion of the Government Inspectorate.

Or the Cam Ranh Peninsula Northern Tourist Area Wastewater collection and treatment system project has completed 90% of the contract value. Currently, regarding the land fund for capital recovery to pay for the BT project, the authorities in Khanh Hoa province have not yet determined the location of the area used to pay for the BT project to the Prime Minister according to the Inspection Conclusion due to many remaining issues that need to be resolved regarding local planning work.

problem related to the 1/2,000 scale Zoning Plan adjustment project for Zone 7 - Northern District of Cam Ranh Peninsula is being implemented but has not been approved as a basis for organizing the determination of location, area, and value for the recovered land fund. Khanh Hoa also asked for the Prime Minister's opinion on the land fund expected to be paid to the Investor implementing the BT project...

Du an BT Nut giao Ngoc Hoi vuong mac chung nam o quy dat dung de hoan von cho du an BT tai khu vuc san bay Nha Trang cu. Anh: Huu Long
The common problem of the Ngoc Hoi Intersection BT Project lies in the land fund used to recover capital for the BT project in the old Nha Trang airport area. Photo: Huu Long

Proposal for Central guidance

In February 2025, Mr. Tran Hoa Nam - Vice Chairman of Khanh Hoa Provincial People's Committee - signed a document to the Ministry of Planning and Investment (now the Ministry of Finance) regarding the difficulties in resolving BT projects. Khanh Hoa Provincial Government has proposed after the Central agencies issued guidelines related to the content of problems with BT contracts that were signed but not in accordance with the provisions of law at the time of signing the BT contract and issued amendments related to the use of state agency headquarters to pay investors.

Khanh Hoa has proposed that central ministries and branches guide the payment of BT contracts in cases where it was previously expected that the land fund would be paid many times in the BT Contract; not ensuring the principle of price parity; adding problems in cases of calculating interest waiting to be paid to Investors.

The locality also asked for guidance on removing obstacles arising from the provisions of the Law on Payment to Investors; supplementing regulations; on the loan interest payment process...

13 BT projects in Khanh Hoa are stuck in contract implementation, namely Road No. 4 (from Road No. 6 to Road No. 23); Nguyen Thien Thuat Street extension; Khanh Hoa Medical College (phase 1); Nha Trang Vocational College (phase 1); Ngoc Hoi Intersection; Ring Road connecting Ngoc Hoi Intersection; Routes and intersections connecting Nha Trang airport area. There are also some projects such as the Headquarters andmitters of Khanh Hoa Radio and Television Station; Wastewater collection and treatment system of Cam Ranh Peninsula Northern Tourist Area; Branch route system (phase 2) Cam Ranh Peninsula Northern Tourist Area; Rainwater drainage system (phase 2) Cam Ranh Peninsula Northern Tourist Area; Cam Ranh Peninsula Northern Tourist Area Western Tourist Area Road Project.

Hữu Long
TIN LIÊN QUAN

3 BT projects at Nha Trang airport will be extended, waiting for court verdict

|

Khanh Hoa - 3 BT projects of Phuc Son Group at Nha Trang airport will be extended, and will have to wait for handling according to the conclusion of the investigation agency and the court's verdict.

Restart BT project to exchange land for infrastructure from July 1, 2025

|

The implementation of BT projects paid by land funds and BT contracts paid by the state budget shall take effect from July 1, 2025.

Inspector recommends reviewing responsibility for 2 BT projects

|

The Government Inspectorate recommends reviewing responsibilities related to two construction investment projects under the BT contract form.

Hour 9: Playing wildly with Love - Part 1

|

The 9th hour, issue 159 - A beautiful 26-year-old girl, talented, mistakenly fell in love with a dating guy. Can they be happy together?

Supreme leader on TV, declares Iran will not surrender

|

Iran's Supreme Leader Ayatollah Ali Khamenei affirmed on June 18 that "the Iranian people are not a subject nation".

The Minister of Construction talks about private investment in railway development

|

The Minister of Construction said that there should be no need to worry about the possibility of private investors being sold to foreign countries when allowing them to participate in railway development.

Live Vietnam men's volleyball 2-0 New Zealand: Set 3

|

Live Vietnam men's volleyball against New Zealand in the opening match of AVC Nations Cup 2025, taking place at 20:30 on June 18 (Vietnam time).

16 Vietnamese citizens return home from Iran

|

On June 18, 2025, 16 Vietnamese citizens in Iran returned home, the remaining 11 citizens were still kept in touch regularly.

3 BT projects at Nha Trang airport will be extended, waiting for court verdict

Hữu Long |

Khanh Hoa - 3 BT projects of Phuc Son Group at Nha Trang airport will be extended, and will have to wait for handling according to the conclusion of the investigation agency and the court's verdict.

Restart BT project to exchange land for infrastructure from July 1, 2025

CAO NGUYÊN |

The implementation of BT projects paid by land funds and BT contracts paid by the state budget shall take effect from July 1, 2025.

Inspector recommends reviewing responsibility for 2 BT projects

TRÍ MINH |

The Government Inspectorate recommends reviewing responsibilities related to two construction investment projects under the BT contract form.