10,000 billion VND tide prevention project handed over in November 2026, be the final commitment

Lê Thanh Phong |

During the September 2nd holiday, workers and engineers are still working at the 10,000 billion VND tide prevention project, striving to hand over the project in November 2026.

About 800 workers and engineers are present at the 10,000 billion VND tide prevention project construction site. The final items are being completed with the goal of handing over the project according to new commitments.

Behind the urgency of the days of construction throughout the holiday is a question that people have the right to ask, is this time really the last promise.

The project was once stalled for about 5 years, while the implemented volume was already very high. The years the project was waiting were also the years people continued to face flooding due to heavy rain and high tides.

Waste is not only in the incurred costs.

That is also a waste of opportunity, a waste of a project that is near completion but has not been able to promote its function, and more sadly, trust is eroded.

Currently, the project has entered the final sprint phase, and the projects are moving towards the finish line. But 94%, 95% or 99% is still not 100%.

Ho Chi Minh City cannot fight flooding with a project nearing completion and data that soothes people's frustration.

People do not need to take "sedative" drugs equal to the 99% completion rate, but only truly feel secure when the entire system operates synchronously, is accepted and put into operation.

There is another concern from public opinion, the sprint project must strictly control quality, technical safety, operating procedures and coordination between culverts, dykes, pumping systems, and control.

Who is in charge of which items, how the completion milestone is, how the acceptance is, how far the trial operation is, what bottlenecks still exist, all need to be controlled and transparent information.

Workers and engineers do not take holidays to complete the project, but that sacrifice is only meaningful when the management apparatus, investors and related agencies also work with the same spirit.

A project worth nearly 10,000 billion VND cannot only require diligence at the construction site, but also management discipline, public service responsibility and determination to remove obstacles to the end.

If the plan is correct, the project will be handed over in November 2026. The next three months are the time for action, not meetings to make new commitments.

Workers can work through the ceremony, and people are also willing to wait a few more months if they are sure that the wait has an end point.

There has been a lot of time to remove obstacles and people once had hopes for an effective tide prevention project, but also many times disappointed.

Therefore, November 2026 cannot be seen as a milestone of striving, but must become a milestone of responsibility.

People in Ho Chi Minh City do not need more "coming-up" news on newspapers.

Lê Thanh Phong
RELATED NEWS

10,000 billion VND tide prevention project in Ho Chi Minh City constructed through holidays, striving to hand over in November

|

Ho Chi Minh City - During the September 2nd holiday, workers and engineers are still working at the 10,000 billion VND tide prevention project, striving to hand over the project in November 2026.

10,000 billion VND tide prevention project in Ho Chi Minh City must be paid with equitized land fund

|

Ho Chi Minh City - The 10,000 billion VND tide prevention project must be paid to investors with land funds ensuring the principle of equal price according to regulations.

10,000 billion VND tide control sluice project needs a solid commitment

|

Ho Chi Minh City restarts the 10,000 billion VND tide control culvert project after a period of interruption, and puts the Ben Nghe tide control culvert into operation.

14 provinces and cities proactively respond to heavy rain

|

14 provinces and cities need to proactively respond to heavy rain, floods, inundation, flash floods, landslides, tornadoes, lightning, and hail.

Video of Bac Ninh 1-0 Ho Chi Minh City Police goal

|

Bac Ninh Club wins against Ho Chi Minh City Police 1-0. Watch LPBank V.League 1-2026/27 live & full on FPT Play, at https://fptplay.vn.

Thousands of tons of clams raised by people die after storms

|

Thanh Hoa - Mass clam deaths at about 60ha of farming ground of 50 households in Ngoc Son ward, estimated damage output from 2,000-2,400 tons.

Houthi forces completely control the strategic Bab al Mandab strait

|

Houthi forces in Yemen have just seized control of Mayyun Island and taken over the Bab al Mandab Strait, a vital shipping route for global oil exports.

Proposal to discipline Vice Chairman of Phu Tho Provincial People's Committee Nguyen Huy Ngoc

|

The Central Inspection Committee proposed that competent authorities consider and discipline Mr. Nguyen Huy Ngoc - Provincial Party Committee member, Vice Chairman of Phu Tho Provincial People's Committee.

10,000 billion VND tide prevention project in Ho Chi Minh City constructed through holidays, striving to hand over in November

MINH QUÂN |

Ho Chi Minh City - During the September 2nd holiday, workers and engineers are still working at the 10,000 billion VND tide prevention project, striving to hand over the project in November 2026.

10,000 billion VND tide prevention project in Ho Chi Minh City must be paid with equitized land fund

MINH QUÂN |

Ho Chi Minh City - The 10,000 billion VND tide prevention project must be paid to investors with land funds ensuring the principle of equal price according to regulations.

10,000 billion VND tide control sluice project needs a solid commitment

Lê Thanh Phong |

Ho Chi Minh City restarts the 10,000 billion VND tide control culvert project after a period of interruption, and puts the Ben Nghe tide control culvert into operation.