10,000 billion VND tide prevention project in Ho Chi Minh City constructed through holidays, striving to hand over in November

MINH QUÂN |

Ho Chi Minh City - During the September 2nd holiday, workers and engineers are still working at the 10,000 billion VND tide prevention project, striving to hand over the project in November 2026.

Recorded on September 1, at large tide-preventing culverts such as Muong Chuoi, Tan Thuan, Phu Xuan, Phu Dinh... the construction atmosphere was urgent.

Many workers and engineers are arranged to work throughout the holidays, focusing on completing the remaining items to bring the project to completion.

At Muong Chuoi tide control culvert - the largest culvert in 6 main culverts - it reaches about 95% of the volume. Units are completing embankment protection, anchorage, operating road, operating house, control room and electrical system - MEP; synchronizing SCADA system and landscape embellishment.

Cống Mương Chuối đạt 95% khối lượng.  Ảnh: Minh Quân
Muong Chuoi sewer reaches 95% volume. Photo: Minh Quan

Tan Thuan sluice gate reached about 96%, completing the boat dock, pumping room, anchorage, operating house and auxiliary items; connecting and synchronizing the pumping system, SCADA and monitoring system. The construction site has also been cleaned up, planted trees and landscaped.

Cống ngăn triều Tân Thuận.  Ảnh: Minh Quân
Tan Thuan tide control gate. Photo: Minh Quan
Cống Tân Thuận đang hoàn thiện nhà điều hành, trồng cây xanh và chỉnh trang cảnh quan. Ảnh: Minh Quân
Tan Thuan culvert is completing the operating house, planting trees and embellishing the landscape. Photo: Minh Quan
Công nhân thi công tại cống Tân Thuận
Construction workers at Tan Thuan culvert. Photo: Minh Quan
Lắp đặt biển báo giao thông, đèn tín hiệu tại cống Tân Thuận.  Ảnh: Minh Quân
Installing traffic signs and traffic lights at Tan Thuan culvert. Photo: Minh Quan

The Phu Xuan, Cay Kho and Phu Dinh culverts reached about 91 - 93%, focusing on completing the culvert embankment, reinforcing the riverbed, pumping chambers, boat holds and control systems.

Hoàn thiện cống Cây Khô.  Ảnh: Minh Quân
Cống Cây Khô reached 91%. Photo: Minh Quân
Cống Phú Xuân đạt 93% khối lượng.  Ảnh: Minh Quân
Phu Xuan sluice reaches 93%. Photo: Minh Quan

Ben Nghe sluice gate reaches 99%, is being accepted, SCADA system is being adjusted, operating procedures and transfer dossiers are being completed.

Cống Bến Nghé hoàn thành 99% khối lượng.  Ảnh: Minh Quân
Ben Nghe sluice gate completed 99%. Photo: Minh Quan

Two small culverts Cau Kinh and Ba Buom reached about 95%. The dyke - embankment along the Saigon River is about 6km long, reaching 87% of the volume.

According to Trung Nam Construction Investment Joint Stock Company (Trungnam Group) - the project investor, currently the entire project has about 800 workers and engineers under construction. The project is entering the final completion phase when most of the main items have been basically completed.

During the September 2nd holiday, the investor continues to maintain construction forces at 6 large culverts, 2 small culverts, dyke sections and the central management house.

The construction teams focused on the remaining items such as completing the operating house, control room, office, architectural details, sanitation, planting trees and landscape embellishment.

The project is entering the final completion phase when most of the main items have been basically completed.

In September, the investor plans to connect the SCADA automatic control system, monitoring system and deploy trial operation of the next culverts, including Tan Thuan and Phu Xuan.

In the final sprint phase, units continue to complete, inspect, adjust and test operate items, ensuring quality, technical and aesthetic requirements.

The entire project aims to complete synchronously and hand over the project in November 2026.

Cống Phú Định hoàn thành 92%.  Ảnh: Minh Quân
Phu Dinh culvert completed 92%. Photo: Minh Quan

When put into operation, the project will help prevent tides, control flooding, and proactively respond to climate change in the inner city area and the South of Ho Chi Minh City, including Saigon, Tan Dinh, Ben Thanh, Cau Ong Lanh wards; Xom Chieu, Khanh Hoi, Vinh Hoi; Tan Thuan, Phu Thuan, Tan My, Tan Hung; Chanh Hung, Phu Dinh, Binh Dong and Nha Be, Hiep Phuoc, Tan Nhut, Binh Chanh, Hung Long, Binh Hung communes.

The project also helps regulate and lower water levels on rivers, canals, and ditches, improve the efficiency of rainwater drainage according to Plan 752; supports water storage when heavy rain combines with tides, reducing pressure on existing drainage systems.

At the same time, the project contributes to limiting saltwater intrusion, improving the water environment, embellishing the landscape and improving the quality of living space in the area.

MINH QUÂN
RELATED NEWS

10,000 billion VND tide prevention project in Ho Chi Minh City must be paid with equitized land fund

|

Ho Chi Minh City - The 10,000 billion VND tide prevention project must be paid to investors with land funds ensuring the principle of equal price according to regulations.

Prime Minister requests to complete the 10,000 billion VND tide prevention project in 2026

|

Ho Chi Minh City - Prime Minister Le Minh Hung requests to remove all bottlenecks and bring the nearly 10,000 billion VND tide prevention project to completion in 2026.

Ho Chi Minh City urgently supplements land fund to pay for 10,000 billion VND tide prevention project

|

Ho Chi Minh City - In addition to 3 land plots already allocated to investors, Ho Chi Minh City plans to bring 2 land plots at 257 Tran Hung Dao and 79B Ly Thuong Kiet to pay for the tide prevention project.

Many strong whirlpools appear, possibility of new storms in the next 2 weeks

|

On September 1, low pressure Pilandok officially strengthened into a tropical storm, warning of 4 more monsoon zones likely to form in the next 2 weeks.

Birds suddenly run amidst traffic on National Highway 18 in Quang Ninh

|

Quang Ninh - A ostrich suddenly ran amidst traffic on National Highway 18, traffic police promptly warned and regulated vehicles to ensure safety.

Current status of the nearly 4.6km long riverside road passing through the super ward in Dong Nai

|

Dong Nai - The Cai riverside road project is nearly 4.6km long, passing through Tran Bien and Tam Hiep wards, with a total investment of nearly 574 billion VND.

10,000 billion VND tide prevention project in Ho Chi Minh City must be paid with equitized land fund

MINH QUÂN |

Ho Chi Minh City - The 10,000 billion VND tide prevention project must be paid to investors with land funds ensuring the principle of equal price according to regulations.

Prime Minister requests to complete the 10,000 billion VND tide prevention project in 2026

MINH QUÂN |

Ho Chi Minh City - Prime Minister Le Minh Hung requests to remove all bottlenecks and bring the nearly 10,000 billion VND tide prevention project to completion in 2026.

Ho Chi Minh City urgently supplements land fund to pay for 10,000 billion VND tide prevention project

MINH QUÂN |

Ho Chi Minh City - In addition to 3 land plots already allocated to investors, Ho Chi Minh City plans to bring 2 land plots at 257 Tran Hung Dao and 79B Ly Thuong Kiet to pay for the tide prevention project.