Chau Doc - Can Tho - Soc Trang Expressway
How is the progress of the 11,900 billion VND expressway in the West?
|
Soc Trang - Component 4 project of Chau Doc - Can Tho - Soc Trang expressway section through Soc Trang province reached 6.6% of contract value.
Peak results of 15 days and nights of highway construction in Soc Trang
|
Soc Trang - From August 15 to August 31, 2024, the construction output of 4 packages of the Chau Doc - Can Tho - Soc Trang expressway component 4 project reached 116 billion VND.
Progress of nearly 10 trillion VND expressway through Can Tho
|
Can Tho - The Chau Doc - Can Tho - Soc Trang expressway project through Can Tho city has achieved 12.40% progress. 15.49% behind schedule, according to the plan, the progress is 27.89%.