Peak results of 15 days and nights of highway construction in Soc Trang

PHƯƠNG ANH |

Soc Trang - From August 15 to August 31, 2024, the construction output of 4 packages of the Chau Doc - Can Tho - Soc Trang expressway component 4 project reached 116 billion VND.

On the afternoon of October 18, the People's Committee of Soc Trang province held a conference to summarize the peak emulation period "15 days and nights to speed up the construction progress of Component Project 4 of the Chau Doc - Can Tho - Soc Trang Expressway Construction Investment Project Phase 1".

Quang canh Hoi nghi. Anh: Phuong Anh
Conference scene. Photo: Phuong Anh

Last August, Soc Trang province launched a 15-day and night peak competition to speed up the construction progress of component project 4 of the Chau Doc - Can Tho - Soc Trang expressway project phase 1 to celebrate National Day on September 2.

Mr. Thach Minh Hoai - Director of Project Management Board 2, project investor - said that during the 15 days of competition, with the spirit of "only discussing progress, not retreat", the project investor, supervising contractor, and construction unit worked day and night, working together to handle difficulties and problems right at the site and implementing the "3 shifts, 4 shifts" regime well.

The management team, engineers, supervisors, and workers of investors and businesses are diligently following the construction site and are enthusiastic in the construction operation. The construction supervision consultant regularly monitors the construction implementation and promptly reports to the investor the progress at the site to achieve technical and labor safety requirements.

San luong 4 goi thau thuoc du an thanh phan 4 cao toc Chau Doc - Can Tho - Soc Trang dat 116 ti dong sau 15 ngay dem. Anh: Phuong Anh
The output of 4 packages of the Chau Doc - Can Tho - Soc Trang Expressway component 4 project reached 116 billion VND after 15 days and nights. Photo: Phuong Anh

The construction unit implemented the spirit of urgency to gather personnel, equipment, and materials to speed up progress, organize construction in "3 shifts, 4 shifts", "not enough work during the day, take advantage of working at night", "eat quickly, sleep urgently", "work continuously 24/7", "work through Tet, through holidays, through September 2nd holiday".

The output from August 15 to August 31, 2024 of the 4 bid packages reached 116 billion VND, of which 4 construction and installation bid packages achieved an average output of over 25 billion VND/bid package (achieving and exceeding the plan by 100 - 142%).

Ong Lam Hoang Nghiep - Pho Chu tich Thuong truc UBND tinh Soc Trang phat bieu tai hoi nghi. Anh: Phuong Anh
Mr. Lam Hoang Nghiep - Permanent Vice Chairman of Soc Trang Provincial People's Committee - spoke at the conference. Photo: Phuong Anh

Speaking at the summary meeting, Mr. Lam Hoang Nghiep - Permanent Vice Chairman of Soc Trang Provincial People's Committee - requested the investor to regularly monitor and organize inspections to work with contractors to resolve difficulties and obstacles as soon as they arise, striving for the unit's disbursement rate to reach 95% or more.

The leaders of Soc Trang Provincial People's Committee requested the consulting and construction units to proactively coordinate closely, unite, be creative, and determined to organize and implement the project in accordance with the Prime Minister's directive of "overcoming the sun, overcoming the rain, not losing to the wind and storm"; not being negligent and subjective, having backup plans in case of adverse weather or damage. Focus on ensuring the health and benefits of workers, ensuring quality and absolute labor safety in accordance with the provisions of law.

Ong Lam Van Man - Uy vien Trung uong Dang, Bi thu Tinh uy Soc Trang tang bang khen cho cac tap the hoan thanh xuat sac nhiem vu. Anh: Phuong Anh
Mr. Lam Van Man - Member of the Party Central Committee, Secretary of Soc Trang Provincial Party Committee - presented Certificates of Merit from the Chairman of the Provincial People's Committee to collectives that excellently completed their tasks. Photo: Phuong Anh

On this occasion, the Chairman of the People's Committee of Soc Trang province awarded Certificates of Merit to 5 collectives and 10 individuals who excellently completed their assigned tasks and had outstanding achievements in the emulation period.

PHƯƠNG ANH
TIN LIÊN QUAN

Chi 13 tỉ di dời bãi rác chắn cao tốc Cần Thơ-Cà Mau đi đâu?

Lê Thanh Phong |

Chi hơn 13 tỉ đồng di dời bãi rác chắn cao tốc Cần Thơ - Cà Mau, hoàn thành bàn giao 100% mặt bằng trước ngày 31.12.

Hơn 13 tỉ đồng di dời bãi rác chắn cao tốc Cần Thơ - Cà Mau

Tạ Quang |

Cần Thơ - Kinh phí thực hiện di dời bãi rác chắn cao tốc Cần Thơ - Cà Mau là 13,08 tỉ đồng và sẽ hoàn thành bàn giao 100% mặt bằng trước ngày 31.12.

Thủ tướng: "Vùng trũng" cao tốc tại ĐBSCL chuyển biến rõ nét

Tạ Quang |

Từ nơi được coi là "vùng trũng" cao tốc, đến nay mạng lưới hạ tầng giao thông tại ĐBSCL đã chuyển biến rõ nét.

Cận cảnh bão Trà Mi gây ngập lụt nặng nề ở Philippines

Thanh Hà - Hữu Chánh (Nguồn: AFP, Zoom Earth, Windy) |

Do ảnh hưởng của bão Trà Mi (tên địa phương là Kristine), ngập lụt nghiêm trọng xảy ra ở nhiều khu vực của Philippines.

Barcelona ngắt chuỗi toàn thua trước Bayern Munich

tam nguyên |

Raphinha tỏa sáng trong chiến thắng 4-1 của Barcelona trước Bayern Munich.

Bình Liêu mùa vàng ngân nga lúa hát

Ninh Phương |

Quảng Ninh - Cuối tháng 10, đầu tháng 11, du khách đến Bình Liêu không chỉ săn mùa cỏ lau mà còn muốn check-in với ruộng bậc thang ngát hương lúa chín.

Thấp thỏm đợi công bố môn thi thứ ba vào lớp 10

Văn Cương |

Nhiều học sinh và phụ huynh bày tỏ lo lắng về hình thức chọn môn thi thứ ba vào lớp 10.

Cập nhật giá vàng sáng 24.10: Đột ngột giảm, nguy cơ lao dốc

Khương Duy |

Cập nhật giá vàng sáng 24.10: Vàng thế giới đêm qua đột ngột sụt giảm. Vàng nhẫn trơn đối diện nguy cơ lao dốc.

Where to spend 13 billion to relocate the garbage dump blocking the Can Tho-Ca Mau highway?

Lê Thanh Phong |

Spending more than 13 billion VND to relocate the landfill blocking the Can Tho - Ca Mau expressway, completing the handover of 100% of the site before December 31.

More than 13 billion VND to relocate the landfill blocking the Can Tho - Ca Mau highway

Tạ Quang |

Can Tho - The cost of relocating the landfill blocking the Can Tho - Ca Mau expressway is 13.08 billion VND and will complete handover of 100% of the site before December 31.

Prime Minister: The "lowland" highway area in the Mekong Delta has clearly changed

Tạ Quang |

From a place considered a "lowland" of highways, the traffic infrastructure network in the Mekong Delta has now changed significantly.