Ben Tre proposed that the Ministry of Transport support investment in upgrading and expanding national highways and building bridges in the area to help the locality break the "island" situation.
Morning in the West: Construction through Tet on key projects
|
Morning of the Western Region 2.1: Construction works through Tet on key projects; Kien Giang will soon completely handle over 125,000 tons of waste remaining in Phu Quoc;…
Workers work through Tet on Rach Mieu 2 Bridge project
|
Ben Tre - On the morning of January 1, at the Rach Mieu 2 bridge project, many workers and engineers were working on items such as leveling the ground, bundling cable-stayed cables, etc.
Visiting Rach Mieu Bridge construction workers on the first 2 days of the new year
|
Ben Tre - On the morning of January 1, although it was New Year's Day, at the construction site of the Rach Mieu 2 bridge project, workers and engineers were still working non-stop.
Workers quickly ate a bowl of rice, determined to bring Rach Mieu 2 bridge to the finish line
|
Ben Tre - As of December 9, the overall progress of the Rach Mieu 2 bridge project has reached more than 71%, 0.49% faster than planned.
Strive to start construction of Rach Mieu 2 bridge resettlement area in 2024
|
Tien Giang - With only 1 household left, the investor strives to start construction of the resettlement area of Rach Mieu 2 bridge project in 2024.