Visiting Rach Mieu Bridge construction workers on the first 2 days of the new year

|

Ben Tre - On the morning of January 1, although it was New Year's Day, at the construction site of the Rach Mieu 2 bridge project, workers and engineers were still working non-stop.

Workers quickly ate a bowl of rice, determined to bring Rach Mieu 2 bridge to the finish line

|

Ben Tre - As of December 9, the overall progress of the Rach Mieu 2 bridge project has reached more than 71%, 0.49% faster than planned.

Strive to start construction of Rach Mieu 2 bridge resettlement area in 2024

|

Tien Giang - With only 1 household left, the investor strives to start construction of the resettlement area of ​​Rach Mieu 2 bridge project in 2024.

Another deep flooding point on National Highway 1 through Lam Dong

|

Lam Dong - Floodwaters caused deep flooding at km1700 of National Highway 1, causing traffic congestion.

The BT project of La Vong Group was once clarified for violations

|

Regarding the BT project invested by a company under La Vong Group, the Government Inspectorate has pointed out many violations.

Live football Nam Dinh vs Shan United in the Southeast Asian Cup C1

|

Live match between Nam Dinh and Shan United in the Southeast Asian Cup C1, taking place at 6:30 p.m. today (December 4).

33rd SEA Games and the expectation of a generation transfer of Vietnamese sports

|

Vietnamese sports are entering an important SEA Games period, where young people are expected to continue the success of the previous golden generation.

Exchange experiences in protecting workers' rights in the new context

|

From December 1-4, the Vietnam Trade Union Delegation will work in India at the invitation of the All-India Trade Union Congress (AITUC). At the meeting, the two sides exchanged experiences in protecting workers' rights.

Visiting Rach Mieu Bridge construction workers on the first 2 days of the new year

Thành Nhân |

Ben Tre - On the morning of January 1, although it was New Year's Day, at the construction site of the Rach Mieu 2 bridge project, workers and engineers were still working non-stop.

Workers quickly ate a bowl of rice, determined to bring Rach Mieu 2 bridge to the finish line

Thành Nhân |

Ben Tre - As of December 9, the overall progress of the Rach Mieu 2 bridge project has reached more than 71%, 0.49% faster than planned.

Strive to start construction of Rach Mieu 2 bridge resettlement area in 2024

Thành Nhân |

Tien Giang - With only 1 household left, the investor strives to start construction of the resettlement area of ​​Rach Mieu 2 bridge project in 2024.