The Cam Khe District Stadium project, Phu Tho province was approved by the old Cam Khe District People's Committee according to Decision No. 210/QD-UBND dated February 7, 2025.
This project belongs to Group C, with a total investment of 35 billion VND invested by Cam Khe Commune People's Committee.
From the end of August 2025, Package No. 05 - Construction of the project has completed the contractor selection and construction work to date.

According to the Decision approving the contractor selection results, the Cam Khe project consortium is the winning unit of package No. 05 with a price of more than 30.2 billion VND, the implementation time of the package is 270 days.
According to records of Lao Dong Newspaper reporters in the last days of April 2026, after exactly 8 months of construction, the stadium project in Cam Khe commune is almost completed.

It can be seen that in the center of the project, an 11-a-side football field has been completed. This football field is designed with dimensions of 90x50m, a 2m wide surrounding boundary, artificial turf...

Items such as: Stands, covered stands, functional rooms serving the stadium, gates, fences... are being constructed and completed by engineers and workers.

Mr. Vinh - a resident of Cam Khe commune - shared: "The new stadium is spacious and clean, hoping that the project will be completed soon, becoming a place to organize sports activities of the commune, meeting the sports needs of the people".
According to Mr. Nguyen Anh Tuan - Vice Chairman of Cam Khe Commune People's Committee, to date, the stadium has completed the ground leveling, the entire rough construction of items: Covered stands, gates, fences, electricity supply, water supply, technical infrastructure, sports field....

Along with that, the contractor is completing the interior of the canoe with a roof, painting technical rooms; installing camera systems, fire prevention and fighting systems, plaster ceilings; painting completion inside the house; installing doors, rolling doors, sanitary equipment, and interior furniture in the room.
Estimated implementation volume reaches 90%. Project progress ensures completion before June 10, 2026.
The investment objective of the Cam Khe District Stadium project, Phu Tho province is to create facilities for training and competing in sports, improving the sports life for people in the area.

Also a stadium, previously, from the beginning of 2026, the project to renovate and upgrade Phu Tho town stadium (now Phu Tho ward) was completed.
The project to renovate and upgrade the stadium in Phu Tho ward has a total investment of 44 billion VND. Unlike the stadium in Cam Khe commune, this stadium has 2 covered stands and a football field planted with natural grass.