Operate Terminal T3 of Tân Sơn Nhất Airport on April 30, 2025.

MINH QUÂN |

HCM - Focus on human resources, construct 3 shifts 4 teams, work throughout holidays and festivals to put T3 Tan Son Nhat station into operation on April 30, 2025.

These requirements were put forward by Prime Minister Pham Minh Chinh during his inspection of the progress of the T3 terminal project at Tan Son Nhat Airport on August 10.

The project, which broke ground in late 2022, has a total investment of nearly 11,000 billion VND from the capital of Vietnam Airlines Corporation (ACV).

This is the largest domestic terminal in the country, capable of serving 20 million passengers per year upon completion. The terminal will increase the total capacity of Tan Son Nhat Airport to 50 million passengers per year, in addition to the existing T1 and T2 terminals.

According to ACV, the T3 project has completed all rough construction work. The system of equipment and machinery is being imported and installed according to the schedule of each project component.

The units are striving to complete the steel structure installation by September 2, 2024, and put the project into operation on April 30, 2025.

Prime Minister Pham Minh Chinh inspects the construction of the T3 terminal.  Photo: VGP/Nhat Bac
Prime Minister Pham Minh Chinh inspects the construction of the T3 terminal. Photo: VGP/Nhat Bac

Prime Minister Pham Minh Chinh praised the relevant agencies, the investor ACV, and the contractors for their implementation of the project, making up for the previous delay and especially the 3,000 enthusiastic workers on the construction site.

To put the project into operation on April 30, 2025, the Prime Minister requested ACV to focus on human resources, continue to promote the spirit of "only discussing, not retreating," "overcoming the sun, overcoming the rain," "eating while hurrying, sleeping while urgent," and constructing "three shifts, four shifts," working through holidays and Tet.

Installing the steel structure and roof of the T3 terminal.  Photo: VGP/Nhat Bac
Installing the steel structure and roof of the T3 terminal. Photo: VGP/Nhat Bac

The Prime Minister noted that the construction time is not long, with only over 7 months left (including 1 month of Tet), while the workload is still quite large (about 45.7%). This is a part of the work that requires high technical and aesthetic standards, as well as close coordination and synchronization between contractors and construction units.

Therefore, it is necessary to direct more resolutely, supervise more strictly, and promptly handle any emerging issues to ensure the construction progress and quality of the project.

When the T3 terminal is put into operation, the Prime Minister reminded that it is necessary to connect and organize the traffic inside the airport and the urban road system in a synchronized manner to avoid congestion.

To create convenience for users and reduce the number of personnel operating the terminal, it is necessary to promote digital transformation, invest in smart management and monitoring systems, and automation.

It is necessary to complete the greenery and landscape of the terminal's surroundings, at parking lots and roads, to ensure synchronization when it is put into use.

The T3 terminal's design when completed.  Photo: ACV
The T3 terminal's design when completed. Photo: ACV

The Ho Chi Minh City People's Committee was assigned to promptly implement and complete the connecting roads, ensuring that they are put into use in a synchronized manner, meeting the travel needs when the T3 terminal is put into operation.

The Ministry of National Defense is responsible for coordinating with the Ho Chi Minh City People's Committee and relevant ministries and agencies to research and resolve the issues related to national defense land to allocate roads and scenic areas around the T3 terminal and effectively exploit Tan Son Nhat Airport.

MINH QUÂN
TIN LIÊN QUAN

Vượt khó thi công dự án nhà ga thứ 3, giảm tải cho sân bay Tân Sơn Nhất

MINH QUÂN |

TPHCM – Bất chấp gặp nhiều trở ngại như mặt bằng chật hẹp, thi công sát sân bay đang khai thác, dự án nhà ga T3 sân bay Tân Sơn Nhất vẫn được nỗ lực để thi công vượt tiến độ, đang băng băng về đích dịp 30.4.2025.

Vẻ hoành tráng của dự án ga T3 Tân Sơn Nhất đang thẳng tiến về đích

MINH QUÂN |

TPHCM - Nhà ga T3 sân bay Tân Sơn Nhất có quy mô 1 tầng hầm, 4 tầng nổi đã xây dựng xong phần thô, đang tiến hành lắp khung phần mái. Đây là ga quốc nội lớn nhất nước phục vụ 20 triệu lượt khách mỗi năm, sẽ hoàn thành đưa vào khai thác vào dịp 30.4.2025.

Diện mạo nhà ga T3 phục vụ 20 triệu hành khách ở sân bay Tân Sơn Nhất

MINH QUÂN (NGUỒN ẢNH: ACV) |

TPHCM – Chiều 31.8, Tổng công ty hàng không Việt Nam (ACV – chủ đầu tư) khởi công gói thầu thi công xây dựng và lắp đặt thiết bị nhà ga T3 sân bay Tân Sơn Nhất. Đây là ga hành khách quốc nội có công suất 20 triệu hành khách mỗi năm, dự kiến hoàn thành đầu năm 2025, giúp nâng công suất khai thác ở sân bay Tân Sơn Nhất lên 50 triệu khách mỗi năm.

Bão số 3 ảnh hưởng thế nào đến đường dây 500kV

Anh Tuấn |

Tập đoàn Điện lực Việt Nam cho biết, bão số 3 (Yagi) đã gây ra một số sự cố lưới điện 500kV, tập trung chủ yếu ở Quảng Ninh, Hải Phòng.

Lần đầu thiết lập cầu vận chuyển miễn phí hàng cứu trợ bão lũ

phóng viên |

Lần đầu thiết lập cầu vận chuyển miễn phí hàng cứu trợ bão lũ.

Bảo hiểm bồi thường 945 triệu đồng vụ sạt lở vùi ôtô ở Cao Bằng

Lục Giang |

Nhiều doanh nghiệp bảo hiểm đã triển khai các biện pháp khẩn cấp để hỗ trợ khách hàng như khẩn trương giám định tổn thất, tạm ứng bồi thường cho khách hàng.

Ngó lơ cảnh báo, nhiều chủ phương tiện bị ngập gần hết xe

Thế Kỷ |

Một số đoạn đường gom Đại lộ Thăng Long (Hà Nội) vẫn đang bị ngập sâu, lực lượng chức năng cảnh báo phương tiện hạn chế hoặc không đi vào.

Ukraina cạn kiệt tên lửa Storm Shadow

Cao Thảo |

Số lượng tên lửa Storm Shadow trong kho vũ khí của Ukraina đang ở mức tương đối thấp.