Deputy Prime Minister inspects progress of Long Thanh airport project

HÀ ANH CHIẾN |

Dong Nai - On the afternoon of January 9, Deputy Prime Minister Tran Hong Ha and a delegation of the Government and ministries worked and inspected the progress of the Long Thanh airport project.

Reporting at the meeting, the representative of the Ministry of Transport said that in component project 1 (headquarters of agencies), 4/5 projects have started construction and committed to be completed before December 31, 2025. The Animal and Plant Quarantine Station is also committed to start construction early and be completed by December 31, 2025.

Pho Thu tuong Chinh phu Tran Hong Ha phat bieu chi dao tai buoi lam viec. Anh: HAC
Deputy Prime Minister Tran Hong Ha gave a speech at the meeting. Photo: HAC

Component 2 project (air traffic management works) is scheduled to be completed before December 31, 2025. The Air Traffic Control Tower has completed the cement concrete part and is preparing to lift the roof.

Component 3, invested by Vietnam Airports Corporation (ACV), is divided into 16 construction and equipment packages. As of the end of December 2024, 3 packages have been basically completed; 7 packages are under construction; 3 packages are selecting construction contractors and 3 other packages are undergoing technical design appraisal.

Pho Thu tuong Chinh phu Tran Hong Ha kiem tra tai du an san bay Long Thanh. Anh: Anh Trong
Deputy Prime Minister Tran Hong Ha inspects the Long Thanh airport project. Photo: Anh Trong

Package 5.10 for the construction of the passenger terminal is considered the heart and the critical path of the entire Long Thanh airport project with many complex, highly technical items, designed with advanced, modern automation technology...

Component 4 project has also opened bidding for packages and committed to completion by December 31, 2025.

Pho Thu tuong Chinh phu Tran Hong Ha trao qua cho cac can bo, ky su nguoi lao dong dang thi cong tai du an san bay Long Thanh. Anh: Anh Trong
Deputy Prime Minister Tran Hong Ha presents gifts to officials, engineers and workers working at the Long Thanh airport project. Photo: Anh Trong

Concluding the working session, regarding the Long Thanh airport project, Deputy Prime Minister Tran Hong Ha requested investors, contractors and relevant ministries and branches to focus on providing solutions and speeding up the progress of component projects according to the direction of the Prime Minister.

The adjustment of the critical path must take package 5.10 - construction of passenger terminal as the center.

Deputy Prime Minister Tran Hong Ha also focused on directing the removal of difficulties and obstacles for the traffic routes connecting Long Thanh airport such as Bien Hoa - Vung Tau expressway, Ben Luc - Long Thanh expressway, Ring Road 3 - Ho Chi Minh City, Ring Road 4, and the expansion of Ho Chi Minh City - Long Thanh - Dau Giay expressway.

Earlier, on the morning of January 9, Deputy Prime Minister Tran Hong Ha visited and presented gifts on the occasion of the Lunar New Year 2025 to policy families, poor households, workers and laborers in difficult circumstances in Long Thanh district, Dong Nai province.

HÀ ANH CHIẾN
RELATED NEWS

Nearly 1,500 billion VND to upgrade the road connecting to Long Thanh airport

|

Dong Nai - The project to upgrade provincial road 25B from the center of Nhon Trach district to National Highway 51, connecting Long Thanh airport, has broken ground.

Deputy Prime Minister Tran Hong Ha gives Tet gifts to the needy

|

Dong Nai - Deputy Prime Minister Tran Hong Ha visited and presented gifts on the occasion of the Lunar New Year 2025 to policy families, poor households, and workers.

Long Thanh airport revealed after more than 1 year of rapid construction

|

Dong Nai - After more than 1 year of rapid construction, the Long Thanh airport passenger terminal has gradually emerged, taking on the traditional lotus shape.

Complicated floods, General Luong Tam Quang requests to protect people's lives above all

|

Amid complicated floods in the Central region, General Luong Tam Quang requested the police force to rescue people and protect people's lives above all, first of all.

Bach Mai Hospital, Viet Duc Facility 2 is expected to be inaugurated on December 19

|

The Deputy Prime Minister requested the preparation of human resource plans, promoting the procurement and bidding of equipment for Bach Mai and Viet Duc Hospitals, Facility 2.

Continue to join hands to support people in provinces affected by storms No. 11, No. 12 and floods

|

The Presidium of the Central Committee of the Vietnam Fatherland Front called for continued support for people in the provinces affected by storms No. 11, No. 12 and floods.

Ke Go Lake increases spillway discharge

|

Ha Tinh - Ke Go Lake operator announced that they will increase the overflow flow to the range of 350m3/s - 800m3/s from 5:00 p.m. on October 31, causing the downstream area to worry.

Jack's return after a series of scandals

|

Jack has announced a temporary hiatus, but is there any chance of this male singer returning after the scandal?

Nearly 1,500 billion VND to upgrade the road connecting to Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - The project to upgrade provincial road 25B from the center of Nhon Trach district to National Highway 51, connecting Long Thanh airport, has broken ground.

Deputy Prime Minister Tran Hong Ha gives Tet gifts to the needy

HÀ ANH CHIẾN |

Dong Nai - Deputy Prime Minister Tran Hong Ha visited and presented gifts on the occasion of the Lunar New Year 2025 to policy families, poor households, and workers.

Long Thanh airport revealed after more than 1 year of rapid construction

HÀ ANH CHIẾN |

Dong Nai - After more than 1 year of rapid construction, the Long Thanh airport passenger terminal has gradually emerged, taking on the traditional lotus shape.