Nearly 1,500 billion VND to upgrade the road connecting to Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - The project to upgrade provincial road 25B from the center of Nhon Trach district to National Highway 51, connecting Long Thanh airport, has broken ground.

On January 9, the Dong Nai Province Traffic Construction Investment Project Management Board broke ground on the project to upgrade Provincial Road 25B from the center of Nhon Trach District to National Highway 51.

The provincial road 25B upgrade project will invest in the section through Long Thanh and Nhon Trach districts with a length of more than 9.2km.

The project has a starting point at Km0+000 intersecting with National Highway 51, an end point at Km9+290 in the center of Nhon Trach district, the cross-section scale of the completed route is 80m.

Total project investment is nearly 1,500 billion VND.

According to schedule, the project will be basically completed in 2025 and put into synchronous operation from 2026.

According to the Management Board of Traffic Construction Investment Projects of Dong Nai province, this is a particularly important project to connect traffic according to the planning, gradually complete the infrastructure, and contribute to socio-economic development according to the general planning orientation of Nhon Trach new urban area.

Provincial Road 25B is also an important route serving traffic connection to Long Thanh airport, expected to be put into operation in 2026.

HÀ ANH CHIẾN
TIN LIÊN QUAN

New Year's Eve fireworks at Long Thanh airport resettlement area

|

Dong Nai will set off fireworks on New Year's Eve at 5 locations, including Loc An - Binh Son Resettlement Area (resettlement of Long Thanh airport project).

Long Thanh airport revealed after more than 1 year of rapid construction

|

Dong Nai - After more than 1 year of rapid construction, the Long Thanh airport passenger terminal has gradually emerged, taking on the traditional lotus shape.

Bidding for 2 packages of Long Thanh airport project in the first quarter of 2025

|

Dong Nai - Vietnam Airports Corporation is preparing to bid for package 7.8 of cargo terminal No. 1 and package 11.5 of Long Thanh airport parking lot.

Parents are upset and worried about the 6th grade admissions crisis

|

According to a new circular from the Ministry of Education and Training, secondary schools will have to stop the entrance exam for grade 6 and switch to the selection method from 2025.

The role with the most actors in Tao Quan

|

Thien Loi is a role that frequently appears in Tao Quan and is also the role with the most actors.

Withdrawal, not daring to buy golden land apartment in 2 districts in Hanoi

|

Hanoi - Many investors have had to quickly withdraw as long-standing apartment buildings in Dong Da and Cau Giay districts are seriously deteriorating.

Broken traffic lights, fear of being fined

|

Quang Tri - Traffic lights on many central routes in the province are flickering, causing people to worry about being fined and causing traffic insecurity.

A canal polluted for decades in Ho Chi Minh City has been revived

|

HCMC - A section of the Hang Bang Canal renovation project through District 5 is urgently completing the final stages to prepare for inauguration on January 17.

New Year's Eve fireworks at Long Thanh airport resettlement area

HÀ ANH CHIẾN |

Dong Nai will set off fireworks on New Year's Eve at 5 locations, including Loc An - Binh Son Resettlement Area (resettlement of Long Thanh airport project).

Long Thanh airport revealed after more than 1 year of rapid construction

HÀ ANH CHIẾN |

Dong Nai - After more than 1 year of rapid construction, the Long Thanh airport passenger terminal has gradually emerged, taking on the traditional lotus shape.

Bidding for 2 packages of Long Thanh airport project in the first quarter of 2025

HÀ ANH CHIẾN |

Dong Nai - Vietnam Airports Corporation is preparing to bid for package 7.8 of cargo terminal No. 1 and package 11.5 of Long Thanh airport parking lot.