Prime Minister inspects Long Thanh airport, must be basically completed by 2025

HÀ ANH CHIẾN |

Dong Nai - Prime Minister Pham Minh Chinh requested the Airports Corporation of Vietnam (ACV) to basically complete the Long Thanh airport project before December 31, 2025.

On the afternoon of September 24, Prime Minister Pham Minh Chinh and the Central working delegation inspected the progress of the Long Thanh airport project in Long Thanh district, Dong Nai province.

Thu tuong quan tam, tham hoi cong nhan lao dong dang thi cong tren cong truong san bay Long Thanh. Anh: HAC
The Prime Minister paid attention to and visited workers at the Long Thanh airport construction site. Photo: Ha Anh Chien

At the Long Thanh airport project construction site, Prime Minister Pham Minh Chinh visited, encouraged and presented gifts to officers, engineers, workers and laborers working at the construction site.

Reporting to the Prime Minister and the working delegation, Mr. Vu The Phiet - Chairman of the Board of Directors of ACV said that currently, the construction packages at the construction site are ensuring progress, by December 31, 2025, the entire rough construction will be completed and specialized aviation equipment will be installed and tested to put Long Thanh airport into official operation by April 30, 2026.

ACV representative also proposed to soon deploy traffic routes connecting Long Thanh airport such as Ho Chi Minh City - Long Thanh - Dau Giay expressway, Bien Hoa - Vung Tau expressway to be completed in 2025; Proposed to deploy runway number 2 of Long Thanh airport...

Thu tuong kiem tra thi cong goi thau 5.10 nha ga hanh khach san bay Long Thanh. Anh: HAC
The Prime Minister inspected the construction of package 5.10 of Long Thanh airport passenger terminal. Photo: Ha Anh Chien
Thu tuong tang qua cho can bo, ky su nguoi lao dong tai du an san bay Long Thanh. Anh: HAC
The Prime Minister presents gifts to officials, engineers and workers at the Long Thanh airport project. Photo: Ha Anh Chien

Mr. Vo Tan Duc - Chairman of Dong Nai Provincial People's Committee also proposed to approve the Ministry of Transport and ACV to implement the second phase of the land leveling project to avoid dust and smoke; agree to build runway number 2, level terminal T3, and expand the Ho Chi Minh City - Long Thanh - Dau Giay expressway to avoid traffic jams.

ACC contractor representative also committed to ensuring construction progress - quality - safety.

Thu tuong yeu cau trong qua trinh thi cong phai kiem soat chat luong, quan tam toi nguoi lao dong. Anh: HAC
The Prime Minister requested that during the construction process, quality control and care for workers must be ensured. Photo: Ha Anh Chien

Concluding the meeting, Prime Minister Pham Minh Chinh welcomed Dong Nai province for basically handing over 5,000 hectares of Long Thanh airport land, thanked Dong Nai people for giving up their farming and living space to build Long Thanh airport, and asked Dong Nai Provincial Party Secretary Nguyen Hong Linh and Dong Nai province to pay attention to people after they relocate to a new place to have a better life than their old place.

Thu tuong Pham Minh Chinh yeu cau co ban hoan thanh du an san bay Long Thanh truoc ngay 31.12.2025. Anh: HAC
Prime Minister Pham Minh Chinh requested that the Long Thanh airport project be basically completed before December 31, 2025. Photo: Ha Anh Chien

Prime Minister Pham Minh Chinh requested that the Long Thanh airport project must be basically completed by December 31, 2025.

The Prime Minister also requested that during the construction process, quality control must be ensured on the project site, environmental hygiene and safety, and technical safety on the construction site. At the same time, attention must be paid to workers to avoid loss and waste...

Regarding the proposal to deploy runway number 2, the Prime Minister proposed to register to add this content to the National Assembly's working program.

The Prime Minister also requested Dong Nai province to plan the construction of Long Thanh airport city and review the projects connecting Long Thanh airport...

Previously, also on the afternoon of September 24, Prime Minister Pham Minh Chinh and the Central working delegation inspected the progress of the Bien Hoa - Vung Tau expressway project.

HÀ ANH CHIẾN
TIN LIÊN QUAN

A series of trees in the commune headquarters were cut down: officials only negotiated prices, not yet sold

|

Binh Dinh - Commune officials involved in the case of sawing and selling trees in the commune headquarters before the merger have admitted their errors and committed to buying native trees for replacement planting.

answered the Geography exam for the 2025 high school graduation exam with a complete set of questions

|

Suggestions for answers to the Geography subject of the 2025 high school graduation exam with the most complete and accurate 48 exam codes are updated on Lao Dong Electronic Newspaper.

answered the full set of codes for the History exam for the 2025 high school graduation exam

|

Suggestions to answer all 48 questions for the most accurate History of the 2025 high school graduation exam are updated on Lao Dong Electronic Newspaper. Readers welcome to watch.

Dong Nai needs to promote administrative procedure reform and investment

HÀ ANH CHIẾN |

Dong Nai - Prime Minister Pham Minh Chinh requested Dong Nai province to promote administrative procedure reform, improve the investment and business environment...

Prime Minister suggests Dong Nai promote the spirit of "3 pioneers"

HÀ ANH CHIẾN |

On the morning of September 24, Prime Minister Pham Minh Chinh attended and directed the conference to announce the planning and promote investment in Dong Nai province.

Thi công xuyên lễ ở sân bay Long Thành với hơn 6.000 nhân sự

HÀ ANH CHIẾN |

Đồng Nai - Đợt nghỉ lễ 2.9, trên công trường sân bay Long Thành vẫn duy trì thi công xuyên lễ, với hơn 6.000 nhân sự và 2.200 thiết bị thi công.