Speed ​​up the progress of key energy projects and projects

Phạm Đông |

On August 23, at the Government headquarters, Member of the Party Central Committee, Deputy Prime Minister Tran Hong Ha chaired the 3rd meeting of the State Steering Committee for important national programs, works and projects. energy sector point.

According to a report by the Ministry of Industry and Trade , the ministry has reviewed and completed legal documents, creating conditions for domestic and foreign investors to participate, determined to build the offshore wind power industry, bringing Vietnam Nam becomes the offshore wind power center of the region.

Regarding the two LNG Thermal Power Plant projects Nhon Trach 3 and 4, the handover, land leasing and infrastructure construction items have been basically completed. However, the work of compensation and site clearance for power grid projects to release capacity for LNG Nhon Trach 3 and 4 Thermal Power Plants has been implemented very slowly. In the coming time, EVN and PVN need to soon agree and sign a power purchase agreement (PPA).

The Deputy Prime Minister requested Dong Nai province to focus on directing and closely coordinating with the Ministry of Natural Resources and Environment to complete site handover for power grid projects to release capacity for Nhon Trach 3 and 4 LNG Thermal Power Plants. by the end of 2024.

For projects in the Quang Trach Power Center, the Quang Trach 1 Thermal Power Plant project has reached 63%, but there are still difficulties in site clearance for some items. Quang Trach 2 Thermal Power Plant Project is adjusting its investment policy to convert to using LNG.

The Steering Committee discussed the gas power development mechanism, firstly to remove remaining difficulties and obstacles of the two LNG thermal power plant projects Nhon Trach 3 and 4; Block B Gas - Electricity project chain; Quang Trach Electricity Center...; solutions to handle power projects that are behind schedule and slow in implementation; Directions to completely resolve a number of renewable energy power projects that violate legal regulations so that they can be put into operation.

The Deputy Prime Minister requested the Ministry of Industry and Trade and localities to coordinate with the Ministry of Public Security and relevant agencies to review the solar power projects mentioned in the conclusions of the Government Inspectorate and transfer them to the investigation agency. .

Classify projects that have no signs of violations or criminal violations and can be remedied according to inspection and examination conclusions... to put them into operation.

For gas thermal power projects, there are problems with the mechanism to determine contract power output (QC), power purchase price... The Deputy Prime Minister requested corporations and businesses to proactively participate. together with the Ministry of Industry and Trade to complete the amendment and promulgation of relevant circulars; Prepare documents to report to the Government to submit to the National Assembly for promulgation of a Resolution on mechanisms and policies for gas power projects.

Regarding the pilot project to develop offshore wind power, the Deputy Prime Minister requires a specific project and model (full export, green fuel production, generation to the national grid), method implementation, thereby determining the "problem" that needs to be solved in terms of legal corridors, surveys, planning... "so that the Prime Minister can approve it so that it can be deployed synchronously and comprehensively." ".

The Deputy Prime Minister assigned the Ministry of Industry and Trade, the Ministry of Planning and Investment, the Ministry of Justice and localities to review and specifically report the number of power projects behind schedule, and propose to competent authorities how to handle them according to regulations of the Government. law.

The Ministry of Industry and Trade urgently researches and develops a project to ensure proactive capacity compensation for power source projects that are behind schedule compared to the Implementation Plan of Electricity Master Plan VIII.

Phạm Đông
TIN LIÊN QUAN

Thủ tướng thúc tiến độ các công trình giao thông trọng điểm

PHẠM ĐÔNG |

Thủ tướng Chính phủ yêu cầu tập trung kiểm điểm, đánh giá các nhiệm vụ được giao và xử lý, thúc đẩy tiến độ triển khai các dự án trọng điểm ngành giao thông.

Thủ tướng Chính phủ kiểm tra 2 công trình điện trọng điểm ở Quảng Bình

CÔNG SÁNG |

Sáng 2.6, Thủ tướng Chính phủ Phạm Minh Chính đã đến kiểm tra tiến độ thi công các dự án Nhà máy Nhiệt điện Quảng Trạch 1 (xã Quảng Đông, huyện Quảng Trạch, tỉnh Quảng Bình) và đường dây 500kV mạch 3 Quảng Trạch - Phố Nối, đoạn qua xã Quảng Đông.

Đẩy nhanh tiến độ các công trình trọng điểm trong vùng Đông Nam Bộ

Cao Huân |

Sáng 5.5, tại hội trường Tỉnh ủy Tây Ninh, Ủy viên Bộ Chính trị, Thủ tướng Chính phủ Phạm Minh Chính, Chủ tịch Hội đồng điều phối vùng Đông Nam Bộ đã chủ trì Hội nghị Hội đồng điều phối vùng Đông Nam Bộ lần 3.

Giá vàng hôm nay 20.9: Vàng nhẫn tăng sốc

Khương Duy |

Giá vàng hôm nay 20.9 tăng mạnh ở thị trường trong nước và thế giới. Giá vàng nhẫn tròn trơn 9999 sáng nay sắp bằng giá vàng miếng SJC.

Giám đốc công ty làm máy nhắn tin cho Hezbollah bị điều tra

Anh Vũ |

Công ty Gold Apollo, có trụ sở tại Đài Loan (Trung Quốc), đang bị điều tra liên quan đến vụ nổ hàng nghìn máy nhắn tin của lực lượng Hezbollah.

Ngắm mùa lúa chín ở Hà Giang vẹn nguyên sau bão lũ

Đan Thanh |

Không chịu ảnh hưởng nhiều sau bão số 3, ruộng bậc thang ở các huyện Vị Xuyên, Hoàng Su Phì đang vào mùa lúa chín đẹp, thu hút khách trở lại Hà Giang.

Điện Biên xuất hiện thêm cung trượt đe dọa nhiều hộ dân

NHÓM PV |

Nhiều vết nứt tạo thành cung trượt lớn đang đe dọa nguy cơ mất an toàn đối với nhiều hộ dân tại TP Điện Biên Phủ, tỉnh Điện Biên.

VĐV bóng chuyền Nguyễn Thị Xuân và sự bền bỉ ở tuổi U40

NHÓM PV |

Góc nhìn thể thao số 181 có buổi trò chuyện với chủ công Nguyễn Thị Xuân về hành trình gắn bó với bóng chuyền cũng như dự định trong tương lai của tay đập 38 tuổi.