Speed ​​up the progress of key energy projects and projects

Phạm Đông |

On August 23, at the Government headquarters, Member of the Party Central Committee, Deputy Prime Minister Tran Hong Ha chaired the 3rd meeting of the State Steering Committee for important national programs, works and projects. energy sector point.

According to a report by the Ministry of Industry and Trade , the ministry has reviewed and completed legal documents, creating conditions for domestic and foreign investors to participate, determined to build the offshore wind power industry, bringing Vietnam Nam becomes the offshore wind power center of the region.

Regarding the two LNG Thermal Power Plant projects Nhon Trach 3 and 4, the handover, land leasing and infrastructure construction items have been basically completed. However, the work of compensation and site clearance for power grid projects to release capacity for LNG Nhon Trach 3 and 4 Thermal Power Plants has been implemented very slowly. In the coming time, EVN and PVN need to soon agree and sign a power purchase agreement (PPA).

The Deputy Prime Minister requested Dong Nai province to focus on directing and closely coordinating with the Ministry of Natural Resources and Environment to complete site handover for power grid projects to release capacity for Nhon Trach 3 and 4 LNG Thermal Power Plants. by the end of 2024.

For projects in the Quang Trach Power Center, the Quang Trach 1 Thermal Power Plant project has reached 63%, but there are still difficulties in site clearance for some items. Quang Trach 2 Thermal Power Plant Project is adjusting its investment policy to convert to using LNG.

The Steering Committee discussed the gas power development mechanism, firstly to remove remaining difficulties and obstacles of the two LNG thermal power plant projects Nhon Trach 3 and 4; Block B Gas - Electricity project chain; Quang Trach Electricity Center...; solutions to handle power projects that are behind schedule and slow in implementation; Directions to completely resolve a number of renewable energy power projects that violate legal regulations so that they can be put into operation.

The Deputy Prime Minister requested the Ministry of Industry and Trade and localities to coordinate with the Ministry of Public Security and relevant agencies to review the solar power projects mentioned in the conclusions of the Government Inspectorate and transfer them to the investigation agency. .

Classify projects that have no signs of violations or criminal violations and can be remedied according to inspection and examination conclusions... to put them into operation.

For gas thermal power projects, there are problems with the mechanism to determine contract power output (QC), power purchase price... The Deputy Prime Minister requested corporations and businesses to proactively participate. together with the Ministry of Industry and Trade to complete the amendment and promulgation of relevant circulars; Prepare documents to report to the Government to submit to the National Assembly for promulgation of a Resolution on mechanisms and policies for gas power projects.

Regarding the pilot project to develop offshore wind power, the Deputy Prime Minister requires a specific project and model (full export, green fuel production, generation to the national grid), method implementation, thereby determining the "problem" that needs to be solved in terms of legal corridors, surveys, planning... "so that the Prime Minister can approve it so that it can be deployed synchronously and comprehensively." ".

The Deputy Prime Minister assigned the Ministry of Industry and Trade, the Ministry of Planning and Investment, the Ministry of Justice and localities to review and specifically report the number of power projects behind schedule, and propose to competent authorities how to handle them according to regulations of the Government. law.

The Ministry of Industry and Trade urgently researches and develops a project to ensure proactive capacity compensation for power source projects that are behind schedule compared to the Implementation Plan of Electricity Master Plan VIII.

Phạm Đông
TIN LIÊN QUAN

Thủ tướng thúc tiến độ các công trình giao thông trọng điểm

PHẠM ĐÔNG |

Thủ tướng Chính phủ yêu cầu tập trung kiểm điểm, đánh giá các nhiệm vụ được giao và xử lý, thúc đẩy tiến độ triển khai các dự án trọng điểm ngành giao thông.

Thủ tướng Chính phủ kiểm tra 2 công trình điện trọng điểm ở Quảng Bình

CÔNG SÁNG |

Sáng 2.6, Thủ tướng Chính phủ Phạm Minh Chính đã đến kiểm tra tiến độ thi công các dự án Nhà máy Nhiệt điện Quảng Trạch 1 (xã Quảng Đông, huyện Quảng Trạch, tỉnh Quảng Bình) và đường dây 500kV mạch 3 Quảng Trạch - Phố Nối, đoạn qua xã Quảng Đông.

Đẩy nhanh tiến độ các công trình trọng điểm trong vùng Đông Nam Bộ

Cao Huân |

Sáng 5.5, tại hội trường Tỉnh ủy Tây Ninh, Ủy viên Bộ Chính trị, Thủ tướng Chính phủ Phạm Minh Chính, Chủ tịch Hội đồng điều phối vùng Đông Nam Bộ đã chủ trì Hội nghị Hội đồng điều phối vùng Đông Nam Bộ lần 3.

Tuyển Indonesia thua trận đầu tiên tại vòng loại 3 World Cup 2026

NHÓM PV |

Tối 15.10, đội tuyển Indonesia nhận thất bại 1-2 trên sân tuyển Trung Quốc tại vòng loại thứ 3 World Cup 2026.

Ra mắt Tủ sách điện tử Tổng Bí thư Nguyễn Phú Trọng

Vương Trần |

Tủ sách điện tử Tổng Bí thư Nguyễn Phú Trọng là cơ sở dữ liệu quý, phục vụ nghiên cứu, học tập và vận dụng trong sự nghiệp xây dựng và bảo vệ Tổ quốc.

Quảng Ngãi khuyến cáo không ồ ạt trồng cau

VIÊN NGUYỄN |

Giá cau ở Quảng Ngãi đạt mức kỷ lục 80.000 đồng/kg. Tuy nhiên, ngành chức năng khuyến cáo nên đa dạng hóa cây trồng, trong bối cảnh giá cau rất khó lường.

Phá đường dây cờ bạc nghìn tỉ qua mạng, tạm giam 12 người

Thành Nhân |

Bến Tre - Lực lượng Công an vừa triệt xóa đường dây cờ bạc trên không gian mạng với tổng số tiền giao dịch hơn 1.800 tỉ đồng.

Nổ nồi hấp tinh dầu, 1 bé gái bị thương, 5 căn nhà ảnh hưởng

LÝ LINH |

TPHCM - Ngày 15.10, Công an huyện Bình Chánh đang điều tra vụ nổ nồi hấp tại một cơ sở sản xuất tinh dầu trên địa bàn xã Vĩnh Lộc A khiến một bé gái bị thương.

Thủ tướng thúc tiến độ các công trình giao thông trọng điểm

PHẠM ĐÔNG |

Thủ tướng Chính phủ yêu cầu tập trung kiểm điểm, đánh giá các nhiệm vụ được giao và xử lý, thúc đẩy tiến độ triển khai các dự án trọng điểm ngành giao thông.

Thủ tướng Chính phủ kiểm tra 2 công trình điện trọng điểm ở Quảng Bình

CÔNG SÁNG |

Sáng 2.6, Thủ tướng Chính phủ Phạm Minh Chính đã đến kiểm tra tiến độ thi công các dự án Nhà máy Nhiệt điện Quảng Trạch 1 (xã Quảng Đông, huyện Quảng Trạch, tỉnh Quảng Bình) và đường dây 500kV mạch 3 Quảng Trạch - Phố Nối, đoạn qua xã Quảng Đông.

Đẩy nhanh tiến độ các công trình trọng điểm trong vùng Đông Nam Bộ

Cao Huân |

Sáng 5.5, tại hội trường Tỉnh ủy Tây Ninh, Ủy viên Bộ Chính trị, Thủ tướng Chính phủ Phạm Minh Chính, Chủ tịch Hội đồng điều phối vùng Đông Nam Bộ đã chủ trì Hội nghị Hội đồng điều phối vùng Đông Nam Bộ lần 3.