Progress of High-Speed Highway and Ring Road projects connecting the southeastern region of Vietnam

MINH QUÂN |

Highway Biên Hòa - Vũng Tàu, Bến Lức - Long Thành, Ho Chi Minh City - Chơn Thành, Ring Road 3, 4 is currently and will soon be implemented to increase connectivity in the Southeastern region of Vietnam.

On August 10, in Ho Chi Minh City, Prime Minister Pham Minh Chinh chaired the Fourth Meeting of the East South Central Region Coordination Council.

Prime Minister Pham Minh Chinh visits delegates attending the East South Central Region Coordination Council Meeting. Photo: Minh Quan
Prime Minister Pham Minh Chinh visits delegates attending the East South Central Region Coordination Council Meeting. Photo: Minh Quan
Prime Minister chairs the East South Central Region Coordination Council Meeting. Photo: Minh Quan
Prime Minister Pham Minh Chinh chairs the East South Central Region Coordination Council Meeting. Photo: Minh Quan

At the meeting, Minister of Planning and Investment Nguyen Chi Dung reported on the progress of a series of important infrastructure projects with a connecting function in the East South Central Region.

Regarding the Ho Chi Minh City Ring Road 3 project, which spans four localities of Ho Chi Minh City, Binh Duong, Dong Nai, and Long An, the project has a length of over 76km, with a total investment of over 75,300 billion VND, including land clearance and construction.

The project has been started by localities since June 2023, with a target of being basically completed in 2025 and completed in full in 2026.

The section through Ho Chi Minh City has implemented 4/10 packages started in June 2023, with an achievement of approximately 17.51% of the workload. 6 packages began construction in late January 2024, with an achievement of 5.1%.

Construction site of Ho Chi Minh City Ring Road 3, section through Thu Duc City (Ho Chi Minh City). Photo: Minh Quan
Construction site of Ho Chi Minh City Ring Road 3, section through Thu Duc City (Ho Chi Minh City). Photo: Minh Quan

The section through Binh Duong Province has achieved 13.7% of the workload; the section through Long An Province has achieved over 35.9% of the workload. Specifically, the section through Dong Nai Province has only achieved 4.52% of the workload.

The progress of land compensation, support, and resettlement for Ho Chi Minh City Ring Road 3 project is basically in line with the set target, with the exception of the section through Dong Nai Province, which has only achieved 32.6% of the land handover.

The Biên Hòa - Vũng Tàu Expressway project, with a length of over 53km, passes through Dong Nai and Bà Rịa - Vũng Tàu provinces, with a total investment of over 17,800 billion VND. According to the plan, the expressway is expected to be basically completed in 2025 and put into operation in 2026.

The section through Bà Rịa - Vũng Tàu Province has over 90% of the road surface area paved with gravel, with a target of putting the entire section into operation in April 2025, 8 months ahead of the deadline set by the government and 4 months ahead of the initial commitment of the contractor.

The section through Dong Nai Province has only handed over over 53ha/151ha of land for the project component 1 and approximately 70ha of land for the project component 2 of the Biên Hòa - Vũng Tàu Expressway, continuing to "miss the deadline" for completing land handover.

The Bến Lức - Long Thành Expressway project, with a length of nearly 58km, passes through three localities: Long An, Ho Chi Minh City, and Dong Nai, with a total investment of 31,300 billion VND.

As of July 2024, the project has achieved over 80% of the production volume, 8.6% behind schedule due to numerous obstacles in the process of selecting contractors, material sources, leading to delays in progress.

This expressway is expected to be put into operation in 2025, connecting the East South Central Region - the West South Central Region and connecting the entire region with major expressways such as Ho Chi Minh City - Trung Lương, Ho Chi Minh City - Long Thanh - Dau Giay, and Bien Hoa - Vung Tau, contributing to the development of the entire region's economy.

The Vành đai 4 project passes through Ho Chi Minh City, Long An, Binh Duong, Dong Nai, and Bà Rịa - Vũng Tàu, with a length of nearly 207km, with a total investment of over 127,000 billion VND in the first phase.

The section through Binh Duong Province is expected to start construction in the third quarter of 2024. Currently, the provincial People's Committee has approved the land clearance plan for two batches, with a progress of 67% in implementing the design boundary plan. The other localities are expected to start construction of Vành đai 4 in 2025.

MINH QUÂN
TIN LIÊN QUAN

Hình hài 3,5km cao tốc Bến Lức - Long Thành đi qua khu rừng ngập mặn xanh mát

HÀ ANH CHIẾN |

Đồng Nai - Tuyến đường cao tốc Bến Lức - Long Thành nhánh phía Đông kết nối miền Đông Nam bộ và miền Tây Nam bộ đi qua tỉnh Đồng Nai dài 27 km, trong đó có hơn 3,5 km đi xuyên qua rừng ngập mặn sắp đưa vào sử dụng sau 7 năm khởi công.

Đồng Nai bàn giao toàn bộ mặt bằng cao tốc Biên Hòa - Vũng Tàu trong tháng 7

HÀ ANH CHIẾN |

Đồng Nai - Ngày 29.6, tại cuộc họp tổng kết kế hoạch 30 ngày đêm về bồi thường giải phóng mặt bằng đối với dự án đường cao tốc Biên Hòa - Vũng Tàu, quyền Chủ tịch UBND tỉnh Đồng Nai Võ Tấn Đức đề nghị hoàn thành giải phóng mặt bằng, bàn giao cho đơn vị thi công trong tháng 7.2024.

Đẩy nhanh tiến độ các công trình trọng điểm trong vùng Đông Nam Bộ

Cao Huân |

Sáng 5.5, tại hội trường Tỉnh ủy Tây Ninh, Ủy viên Bộ Chính trị, Thủ tướng Chính phủ Phạm Minh Chính, Chủ tịch Hội đồng điều phối vùng Đông Nam Bộ đã chủ trì Hội nghị Hội đồng điều phối vùng Đông Nam Bộ lần 3.

Chủ tịch Tổng LĐLĐVN thăm, tặng quà người dân bị thiên tai tại Hà Giang

Nguyễn Tùng |

Ngày 14.9, ông Nguyễn Đình Khang, Ủy viên Trung ương Đảng, Chủ tịch Tổng Liên đoàn Lao động Việt Nam (Tổng LĐLĐVN) cùng đoàn công tác tới thăm, tặng quà đoàn viên, công nhân viên chức lao động và người dân bị thiệt hại do lũ lụt tại Hà Giang.

Haaland lập cú đúp giúp Man City đánh bại Brentford

NGUYỄN ĐĂNG |

Brentford đã không thể tạo nên cú sốc trước Man City tại vòng 4 Ngoại hạng Anh, dù đã dẫn trước ngay ở giây thứ 22.

Thị trường ế ẩm, bánh Trung thu truyền thống vẫn đắt hàng

Phương Anh |

Hà Nội - Trái với cảnh nhiều điểm bán bánh Trung thu ế ẩm dù giảm giá, khách vẫn xếp hàng dài chờ mua bánh Trung thu truyền thống trên phố Thụy Khuê.

Giờ thứ 9: Trả về nguyên quán - Phần 2

Nhóm PV |

Giờ thứ 9 - Cô gái trẻ tiến tới hôn nhân khi vừa học hết cấp 3. Cô bị gia đình phản đối vì quyết định này. Diễn biến tiếp theo của câu chuyện sẽ ra sao?

Di dời cả bản hơn 100 hộ ở Sơn La trước nguy cơ sạt trượt

Minh Nguyễn |

Sơn La - Lực lượng chức năng đang khẩn trương di dời người dân một bản ở huyện Bắc Yên để tránh nguy hiểm do xuất hiện vị trí nứt gãy có nguy cơ sạt trượt.

Hình hài 3,5km cao tốc Bến Lức - Long Thành đi qua khu rừng ngập mặn xanh mát

HÀ ANH CHIẾN |

Đồng Nai - Tuyến đường cao tốc Bến Lức - Long Thành nhánh phía Đông kết nối miền Đông Nam bộ và miền Tây Nam bộ đi qua tỉnh Đồng Nai dài 27 km, trong đó có hơn 3,5 km đi xuyên qua rừng ngập mặn sắp đưa vào sử dụng sau 7 năm khởi công.

Đồng Nai bàn giao toàn bộ mặt bằng cao tốc Biên Hòa - Vũng Tàu trong tháng 7

HÀ ANH CHIẾN |

Đồng Nai - Ngày 29.6, tại cuộc họp tổng kết kế hoạch 30 ngày đêm về bồi thường giải phóng mặt bằng đối với dự án đường cao tốc Biên Hòa - Vũng Tàu, quyền Chủ tịch UBND tỉnh Đồng Nai Võ Tấn Đức đề nghị hoàn thành giải phóng mặt bằng, bàn giao cho đơn vị thi công trong tháng 7.2024.

Đẩy nhanh tiến độ các công trình trọng điểm trong vùng Đông Nam Bộ

Cao Huân |

Sáng 5.5, tại hội trường Tỉnh ủy Tây Ninh, Ủy viên Bộ Chính trị, Thủ tướng Chính phủ Phạm Minh Chính, Chủ tịch Hội đồng điều phối vùng Đông Nam Bộ đã chủ trì Hội nghị Hội đồng điều phối vùng Đông Nam Bộ lần 3.