For 15 years, the billion-dollar hospital project in Bac Lieu is still vacant

NHẬT HỒ |

Bac Lieu - Awarded an investment certificate in 2010, started construction in 2018, up to now, the hospital construction location is still an empty lot.

Start construction and leave it there

The Bac Lieu - Saigon General Hospital construction project was granted an investment certificate by the Bac Lieu Provincial People's Committee in 2010 with a total investment of nearly 1,370 billion VND. The project has an area of over 37,000m2, located in Hoang Phat New Urban Area, in Ward 1, Bac Lieu City (Bac Lieu Province). The project construction scale is 10 floors, with a capacity of 400 outpatient beds/day and 436 inpatient beds...; expected to be completed and put into operation by the end of 2020.

On June 24, 2018, Bac Lieu - Saigon General Hospital Joint Stock Company organized the groundbreaking ceremony. However, after the groundbreaking ceremony, the investor did not build anything but abandoned the land, causing waste of the state's clean land fund for many years.

Phoi canh Benh vien Sai Gon - Bac Lieu. Anh: Nhat Ho
Perspective of Saigon - Bac Lieu Hospital. Photo: Nhat Ho

On November 26, 2021, the People's Committee of Bac Lieu province issued Decision No. 511 on the revocation of the hospital construction land for Bac Lieu - Saigon General Hospital Joint Stock Company, assigning the Provincial Housing and Land Fund Development Center to manage.

After receiving the decision, Bac Lieu - Saigon General Hospital Joint Stock Company complained, Bac Lieu Provincial People's Committee issued Decision No. 302/QD-UBND affirming that the settlement was correct. Meanwhile, the investor believes that the two decisions of the Bac Lieu Provincial People's Committee to reclaim land without compensation are not in accordance with the law, so they should file a lawsuit in court.

The court of first instance believes that Decision 511/QD-UBND is within its authority, order and content. The company's delay in putting the land into use is well-founded.

At the appeal hearing, the High-level People's Court in Ho Chi Minh City determined that the company submitted a request to return land for hospital construction and housing construction to experts in order for the People's Committee of Bac Lieu province to return the invested money, but was not accepted by the Provincial People's Committee, which was not in accordance with the provisions of law; the People's Committee of Bac Lieu province did not accept the company to extend the land use period, with the reason that not putting the land into use was not in accordance with the provisions of law.

Sau khoi cong, Benh vien Da khoa Sai Gon - Bac Lieu bo hoang khong xay dung gi. Anh: Nhat Ho
After the groundbreaking, Saigon - Bac Lieu General Hospital was abandoned and under construction. Photo: Nhat Ho

According to the Board of Directors, the company's request for an extension is during the COVID-19 epidemic prevention period (in case of force majeure), but it was not accepted by the People's Committee of Bac Lieu province as inappropriate. On the other hand, according to the provisions of law, the company has the right to extend the project for 24 months when the state terminates the operation of the project. The Bac Lieu Provincial People's Committee's failure to grant an extension, not to receive land back, and not to base on the COVID-19 epidemic situation to withdraw the entire project without compensation is not in accordance with the law.

After winning the lawsuit, continue to leave the land vacant

After winning the lawsuit, from April 2024 until now, the Saigon - Bac Lieu General Hospital project has remained inactive. The investor has not shown any signs in the field even though the winning lawsuit has been nearly a year.

Du an Benh vien Da khoa Sai Gon- Bac Lieu chiem giu khu dat vang tai trung tam thanh pho Bac Lieu. Anh: Nhat Ho
The Saigon - Bac Lieu General Hospital project occupies a prime land in the center of Bac Lieu city. Photo: Nhat Ho

The People's Committee of Bac Lieu province said that the court's ruling must be followed, but this is an administrative judgment, the plaintiff who won the lawsuit is considered the revoking decision of the Provincial People's Committee to no longer be valid, the investor must complete the procedures according to regulations to conduct investment in the project. However, up to now, the investor has not taken further steps while the government is ready.

NHẬT HỒ
TIN LIÊN QUAN

Exemption from second-round fees for candidates who have lost their BDNL test time

|

Candidates who have wasted time taking the first round of the Ho Chi Minh City National University's competency assessment test will be exempted from exam fees in the second round.

Sudden checking around school gates in Hanoi

|

Hanoi - The city will conduct a surprise inspection of food safety control work in and around school gates.

Phu Yen receives the First Class Labor Medal

|

Phu Yen - On the evening of April 1, at April 1 Square (Tuy Hoa City), Phu Yen province solemnly held a ceremony to celebrate the 50th anniversary of the Provincial Liberation Day (April 1, 1975 - April 1, 2025).

10 workers of Nghe An Fishing Inspectorate hope to have their rights guaranteed

|

Nghe An - 10 workers working on the province's fishing vessels are currently only allowed to sign contracts each year, and have not signed long-term labor contracts.

Vietnamese architects admire the colors of Lao culture

|

Mr. Nguyen Hong Nhat (35 years old, architect in Hanoi) and his family had memorable experiences when traveling to Laos for 6 days.

Assigning Hanoi to build a roadmap to collect fees for cars entering the inner city

|

The Deputy Prime Minister requested Hanoi to develop a roadmap to gradually reduce motorbikes in the inner city, collecting fees for cars entering the central area during rush hour.

The maximum average retail price of electricity is VND 2,444.09/kWh

|

According to the new regulations, the minimum average retail price for electricity is VND 1,826.22/kWh; the maximum average retail price for electricity is VND 2,444.09/kWh.

Pay attention to training cadres, meeting the requirements of restructuring the apparatus

|

In the coming time, it is necessary to pay attention to training and fostering cadres, meeting the requirements of restructuring the apparatus...

Hàng loạt dự án khởi động rồi... bất động ở Bạc Liêu

NHẬT HỒ |

Bạc Liêu - Các dự án được cho là điểm sáng trong thu hút đầu tư, nhưng qua nhiều năm vẫn nằm bất động.

Hiện trạng khu đất vàng dự án bệnh viện mà chủ đầu tư kiện UBND tỉnh khi bị thu hồi

NHẬT HỒ |

Bạc Liêu - Khu đất rộng gần 7 ha nằm kẹp giữa hai dự án đô thị danh giá nhất tỉnh Bạc Liêu, một mặt của khu đất là đường vành đai trong của Thành phố Bạc Liêu. Tuy nhiên, khu đất bị bỏ hoang 12 năm nay thay vì xây dựng bệnh viện như mục đích ban đầu.

Thu hồi dự án bệnh viện trên đất vàng bỏ hoang, UBND tỉnh Bạc Liêu bị kiện

NHẬT HỒ |

Bạc Liêu - Ngay khi bà Trần Thiện Niềm - Phó Ban bảo vệ sức khỏe Tỉnh ủy Bạc Liêu - còn tại vị, tỉnh Bạc Liêu đã chấp nhận cho bà làm dự án bệnh viện. Ôm đất vàng từ 2010 đến nay không làm gì, khi tỉnh thu hồi lập tức tỉnh bị kiện.