More than 18,000 billion VND invested in expanding 3 roads connecting Long Thanh airport
The project to upgrade and expand DT 769 has a total length of nearly 30km, passing through Thong Nhat and Long Thanh districts, with the starting point intersecting with National Highway 1 at Dau Giay intersection, Thong Nhat district; The end point intersects with National Highway 51 at Loc An intersection, Long Thanh district with a total investment of more than 6,256 billion VND, of which construction costs are more than 2,200 billion VND.
As noted by the reporter, currently DT 769 is the main transportation and travel route from National Highway 51 to the Long Thanh airport project.
However, currently the existing DT 769 route is small and narrow, and the number of vehicles has increased significantly. The project to upgrade and expand DT 769 will enhance traffic capacity between the southern key economic region and the Central Highlands provinces, connecting with Long Thanh airport.
The project to upgrade and expand DT 773 road has a length of more than 39km, the project has a starting point intersecting with National Highway 1 at Xuan Tam commune, Xuan Loc district and the end point is Huong Lo 10 intersecting with Ring Road 4 - Ho Chi Minh City. Construction planning with a scale of 6-8 lanes.
The total investment capital of the project is 4,311 billion VND from the provincial budget (land auction source). Project implementation period is from 2022-2027.
DT 773 is a parallel route and shares traffic with National Highway 1. This is also an important traffic axis connecting Xuan Loc district, Cam My district, Long Khanh city with Long Thanh airport.
The DT 770B road project is a route that will be invested in new construction with a length of more than 42km, with the starting point intersecting with Provincial Road 763 in Suoi Nho commune, Dinh Quan district and the ending point intersecting with National Highway 51 in Phuoc commune. Thai, Long Thanh district, planned to have a road width of 60m, with 4-8 lanes.
The total investment of the 770B road construction project is 8,043 billion VND, of which compensation and site clearance costs are about 3,300 billion VND. The capital source for implementation is the provincial budget capital. Project implementation period is from 2022-2027.
Provincial road 770B is invested in building connections between the eastern and northeastern districts of the province with Long Thanh airport and industrial parks Xuan Que - Song Nhan, Bau Can - Tan Hiep, connecting Bien Hiep expressway. Hoa - Vung Tau, National Highway 51 and Cai Mep - Thi Vai seaport area (Ba Ria - Vung Tau province).
Difficulty in land auction, Dong Nai requested financial support
According to the People's Committee of Dong Nai province, currently to synchronize the transportation system connecting with Long Thanh airport, Dong Nai province is focusing on implementing 3 projects including: DT 769 (total investment 6,256 billion VND), DT 770B (total investment 8,043 billion VND), DT 773 (total investment 4,311 billion VND), with a total investment of 18,610 billion VND (of which site clearance costs are 8,526 billion VND).
However, currently land auctions in Dong Nai province are facing many difficulties due to the quiet real estate market.
Therefore, the People's Committee of Dong Nai province proposed to the National Assembly to support part of the investment costs from the capital saved due to reducing the total investment of the project "Land recovery, compensation, and resettlement support for Long Thanh airport". ” about 3,730 billion VND (adjusted from 22,856 billion VND to 19,207 billion VND).