3 years have not completed the 778m long road, capital of 130 billion VND in Nha Trang

Hữu Long |

Khanh Hoa - The route is longer than 778m connecting two major roads in Nha Trang city with a capital of 130 billion VND. The road has been under construction for 3 years but has not been completed yet due to land problems.

The contractor stopped construction and demanded an adjustment to the contract unit price

Route named D30, 778.5m long, 30m wide, belongs to Vinh Hiep commune and Vinh Trung commune (Nha Trang city). The route connects two major roads in the city, October 23 with Vo Nguyen Giap. The project has a total estimated investment of nearly 130 billion VND from the provincial budget. Of which, the construction cost is nearly 80.7 billion VND, the rest is compensation for clearance, resettlement, project management,...

When the road is completed, the foundation will be asphalt concrete, with a rainwater drainage system, lighting and a bridge over the Quan Truong river made of reinforced concrete.

Route D30 is still in disarray, the contractor does not have a construction site. Photo: Huu Long
Route D30 is still in disarray, the contractor does not have a construction site. Photo: Huu Long

The project was started at the end of 2020, expected to be completed in 360 days. Because the project has not been cleared, the investor and contractor have signed to extend the completion time many times. The value of completed volume by contractors to date has reached 40.93 billion VND (reaching 78.34%).

According to the report of the investor, the Management Board of Investment and Construction of Agricultural and Rural Development Works of Khanh Hoa province, this project has 37 cases that must be cleared. Up to now, there are only 3 households on 23/10 street that just handed over the premises on June 27, 2024.

The remaining volume of items has not been constructed from October 23 Street to Quan Truong bridge; gravel foundation, asphalt concrete for road surface, tiled sidewalks, sidewalk soil embankment, traffic signal lights at 2 intersections...

For this unconstructed part, the contractor said that it will carry out the construction when price adjustment is allowed because otherwise, it will incur heavy losses due to increased raw material prices compared to the time of signing the contract in 2020.

In the report sent to the People's Committee of Khanh Hoa province, the investor said that if the contract with the contractor is terminated, the project will not be completed in July 2024 as required by the province.

Not to mention, terminating the contract will lead to a higher re-estimation value compared to the time the contract was signed in November 2020 and the procedure for organizing and selecting a contractor to construct the remaining volume will take some time.

After calculation, the investor still proposed that Khanh Hoa province allow the termination of the construction contract for the remaining volume.

Road D30 has been under construction for 3 years but has not been completed yet, the contractor has asked to stop the project
Road D30 has been under construction for 3 years but has not been completed yet. The contractor has asked to stop construction due to increased construction costs. Photo: Huu Long

Khanh Hoa province does not agree to terminate the construction contract

Mr. Tran Hoa Nam - Vice Chairman of Khanh Hoa Provincial People's Committee requested the leaders of the Project Management Board to work again with the contractors to speed up the remaining volume of the D30 road project, ensuring completion. completed in July 2024.

Mr. Nam requested that, in case of failure to complete within the above deadline, the board's leaders must take full responsibility related to implementing the investor's tasks before the Chairman of Khanh Hoa Provincial People's Committee.

According to the leader of the People's Committee of Khanh Hoa province, the above project is not subject to unit price adjustment according to the above legal regulations. Therefore, the province does not agree to terminate the construction contract with the contractor as requested by the investor.

Mr. Quach Thanh Son - Director of Construction Investment Management Board of Agriculture and Rural Development Works of Khanh Hoa province said that after receiving instructions from the province, the investor organized a mobilization and the contractor agreed to work again.

Regarding the timeline of 7.2024 that Khanh Hoa province set for completion, Mr. Son assessed that it will be difficult to achieve but will work with the contractor to bring the project to completion as soon as possible.

Hữu Long
TIN LIÊN QUAN

Gia hạn cho thuê hơn 8.000m2 đất vàng dọc bãi biển Nha Trang

Hữu Long |

Khánh Hòa - Hơn 8.000m2 đất mặt biển dọc bãi biển Nha Trang vừa được địa phương gia hạn thời gian sử dụng đất đến hết năm 2024.

Sau kiện sơ thẩm, Nha Trang điều chỉnh đối tượng thu hồi đất

Hữu Long |

Trước phiên phúc thẩm vụ công dân kiện TP Nha Trang về thu hồi đất thuộc diện vắng chủ, đến nay địa phương bất ngờ điều chỉnh đối tượng thu hồi đất.

Nha Trang đặt thêm biển cấm đậu đỗ ôtô trên 16 chỗ

Hữu Long |

Khánh Hòa – Trước phản ánh của dân về việc các xe du lịch trên 16 chỗ đậu, đỗ gây ùn tắc giao thông, TP Nha Trang thống nhất lắp thêm biển báo cấm...

Vụ công trình làm nứt nhà dân ở Hà Nội, chính quyền nói gì?

NHÓM PV |

Theo chính quyền phường Quang Trung, hình ảnh công nhân đang làm việc tại công trình số nhà 19, ngõ 136/98 Tây Sơn là để hút nước phòng dịch sốt xuất huyết.

Triều Tiên cho nổ tung tuyến đường bộ nối với Hàn Quốc

Khánh Minh |

Triều Tiên cho nổ tung các tuyến đường nối với Hàn Quốc vốn từng được coi là biểu tượng của sự hợp tác liên Triều.

Thân tín của bà trùm ma túy Oanh "Hà" được trả công 15 tỉ

Việt Dũng |

Trong số hơn 626kg ma túy mua bán xuyên quốc gia do bà trùm Oanh "Hà" cầm đầu, Nguyễn Văn Nam có mặt hầu hết ở các chuyến hàng, nhận công hậu hĩnh.

Bất cập tiền công đức 2 đền ở Ninh Bình do nguồn thu quá lớn

NGUYỄN TRƯỜNG |

Ninh Bình - Những tồn tại, bất cập trong việc quản lý tiền công đức tại đền Dâu và đền Quán Cháo (thành phố Tam Điệp) là do nguồn thu quá lớn.

Chánh văn phòng hãng luật bị tố đe dọa, xúc phạm phụ nữ

TRÍ MINH |

Một chánh văn phòng hãng luật bị tố cáo có hành vi đe dọa, xúc phạm danh dự, nhân phẩm phụ nữ. Người dân đã trình báo sự việc tới cơ quan công an.

Gia hạn cho thuê hơn 8.000m2 đất vàng dọc bãi biển Nha Trang

Hữu Long |

Khánh Hòa - Hơn 8.000m2 đất mặt biển dọc bãi biển Nha Trang vừa được địa phương gia hạn thời gian sử dụng đất đến hết năm 2024.

Sau kiện sơ thẩm, Nha Trang điều chỉnh đối tượng thu hồi đất

Hữu Long |

Trước phiên phúc thẩm vụ công dân kiện TP Nha Trang về thu hồi đất thuộc diện vắng chủ, đến nay địa phương bất ngờ điều chỉnh đối tượng thu hồi đất.

Nha Trang đặt thêm biển cấm đậu đỗ ôtô trên 16 chỗ

Hữu Long |

Khánh Hòa – Trước phản ánh của dân về việc các xe du lịch trên 16 chỗ đậu, đỗ gây ùn tắc giao thông, TP Nha Trang thống nhất lắp thêm biển báo cấm...