Lang Son - Thai Nguyen expressway is expected to be completed before 2030

Khánh Linh |

Lang Son - The expressway is about 120 km long, with a scale of 4 lanes, proposed for investment in the form of public-private partnership and to be completed before 2030.

On August 7, Lang Son Provincial People's Committee said it had agreed with Thai Nguyen Provincial People's Committee on the plan and plan to implement the Lang Son - Thai Nguyen expressway project.

According to the plan, the starting point of the route connects to the CT10 intersection on the Dong Dang - Tra Linh expressway, in Lang Son province; the ending point connects to the CT07 route in Thai Nguyen.

The project connection location between the two provinces is located in the border area of Nhat Hoa commune, Lang Son province and Dan Tien commune, Thai Nguyen province.

The expressway is about 120 km long, designed with 4 lanes, with a total estimated investment of 29,000 billion VND.

The two localities agreed to report to competent authorities to assign the People's Committee of Thai Nguyen province to be the competent agency to implement the project according to the public-private partnership (PPP) method.

The central budget is proposed to support about 20,720 billion VND, equivalent to about 70% of the total investment.

The remaining capital will be mobilized according to the financial plan of the PPP project after being considered by competent authorities.

Regarding compensation, support, resettlement and site clearance, the route section belonging to the administrative boundaries of which province will be proactively implemented by that locality.

Lang Son and Thai Nguyen will coordinate to determine the scope, boundaries and progress in the adjacent area, ensuring synchronous handover of land.

The project is expected to deploy procedures in 2026 and be completed before 2030. Thai Nguyen Provincial People's Committee will continue to complete the dossier and report to the Government and central ministries and branches.

The Lang Son - Thai Nguyen expressway is one of the strategic transport projects agreed upon and implemented by three provinces Lang Son, Cao Bang and Thai Nguyen.

The route will connect with the Dong Dang - Tra Linh expressway, Bac Kan - Cao Bang along with the national highway, provincial road, border gate and industrial park system.

When completed, the project is expected to form the inter-regional traffic axis Lang Son - Cao Bang - Thai Nguyen - the Capital region, shortening the transportation time of goods and expanding the development space for northern localities.

Khánh Linh
RELATED NEWS

Huu Nghi border gate upgrades infrastructure to welcome expressway worth 11,808 billion VND

|

Lang Son - Huu Nghi - Chi Lang expressway is accelerating completion, leading to the requirement to expand internal roads, warehouses and customs clearance capacity at Huu Nghi border gate.

Accelerate the construction progress of the Hoa Binh - Moc Chau expressway

|

Son La - Locality is accelerating the construction progress of the Hoa Binh - Moc Chau expressway.

Huu Nghi - Chi Lang expressway misses 27 km traffic opening deadline, focusing efforts on completing the main route

|

Lang Son - Although the Huu Nghi - Chi Lang expressway missed the 27 km opening milestone on May 19, contractors are focusing their efforts to complete all items on the main route.

Accelerate the construction of a new bridge to replace a 25-year-old suspension bridge in Hue

|

HUE - After nearly 5 months of construction, Binh Thanh bridge has reached more than 60% of the construction value, aiming to replace the dilapidated suspension bridge after about 25 years of operation.

Main attacker Tang Ngoc Hieu: The SEA V.Cup championship is a stepping stone for career development

|

The SEA V.Cup 2026 championship with the Vietnamese men's volleyball team is a stepping stone for main hitter Tang Ngoc Hieu to improve himself and develop his career.

Total solar eclipse on August 12 opens the door to decoding the biggest mysteries of the Sun

|

Scientists plan to use the full solar eclipse next week to learn more about the volatile and unpredictable nature of the Sun.

Weather today August 7: Northern region heavy rain in the morning

|

Weather today August 7, Northern region, Thanh Hoa and Nghe An morning with moderate rain, heavy rain and thunderstorms, locally very heavy rain; afternoon rain decreases.

Close-up of Hoa Binh Hydropower Plant discharging floodwater

|

On August 6, Hoa Binh Hydropower Company opened 1 bottom discharge gate of Hoa Binh Hydropower Reservoir at 4:00 PM to regulate the reservoir.

Huu Nghi border gate upgrades infrastructure to welcome expressway worth 11,808 billion VND

Khánh Linh |

Lang Son - Huu Nghi - Chi Lang expressway is accelerating completion, leading to the requirement to expand internal roads, warehouses and customs clearance capacity at Huu Nghi border gate.

Accelerate the construction progress of the Hoa Binh - Moc Chau expressway

Thành An |

Son La - Locality is accelerating the construction progress of the Hoa Binh - Moc Chau expressway.

Huu Nghi - Chi Lang expressway misses 27 km traffic opening deadline, focusing efforts on completing the main route

Khánh Linh |

Lang Son - Although the Huu Nghi - Chi Lang expressway missed the 27 km opening milestone on May 19, contractors are focusing their efforts to complete all items on the main route.