Huu Nghi - Chi Lang expressway misses 27 km traffic opening deadline, focusing efforts on completing the main route

Khánh Linh |

Lang Son - Although the Huu Nghi - Chi Lang expressway missed the 27 km opening milestone on May 19, contractors are focusing their efforts to complete all items on the main route.

Today (May 19), the 27 km long section from the end point of the Bac Giang - Lang Son expressway to the IC03 intersection (adjacent to National Highway 4B) belonging to the Huu Nghi - Chi Lang expressway project cannot be opened to traffic as initially planned.

Talking to PV, Mr. Tran Van Chuan, Deputy Director of the Huu Nghi - Chi Lang Project Management Board, said that the reason for the missed appointment was due to land problems at the level crossing and people's service roads.

Because the locality has not handed over this land fund, the contractor cannot construct a closed system of protective fences and corrugated iron railing.

a
Huu Nghi - Chi Lang expressway has not ensured sufficient traffic safety conditions for operation. Photo: Khanh Linh

The inability to "close" the fence makes this section not meet sufficient traffic safety conditions to be put into operation.

However, according to the latest information from the project enterprise, the pace at the construction site is still being pushed to the highest level.

This week, construction units will focus manpower and equipment to completely complete all items belonging to the main route of the 27 km section.

Also according to the project enterprise, in the overall project, the overall progress is still maintained positively.

As of mid-May 2026, on a scope of 59.2 km, land has been cleared, and contractors are closely monitoring 131 simultaneous construction fronts with 2,599 personnel and 1,195 machinery and equipment.

The total value implemented to date reached more than 5,758 billion VND, equivalent to 72.43% of the contract value.

a
The project progress is still being maintained positively. Photo: Khanh Linh

Complex construction items are basically completed, typically beam casting work reached 100% (822/822 slabs), drilled piles completed 99.98%, the volume of excavation and foundation filling of road K95 both exceeded 95%.

Regarding disbursement, the state budget capital support for construction (VGF) has reached more than 3,311 billion VND.

The Huu Nghi - Chi Lang border gate expressway project is invested under the public-private partnership (BOT) method with a total investment of 11,808 billion VND, with a total length of nearly 60 km.

In which, the main expressway passing through Lang Son is 43.43 km long and the connecting route of Tan Thanh and Coc Nam border gates is 16.44 km long.

Currently, the biggest obstacle hindering the project's acceleration is still site clearance. The entire route still has 16 households that have not moved houses, 15 households encroaching at the IC01 intersection and 7 locations of slow-moving power grid infrastructure.

Vướng mắc mặt bằng vẫn là nút thắt lớn nhất ảnh hưởng đến tiến độ dự án. Ảnh: Khánh Linh
Land disputes are still the biggest bottleneck affecting project progress. Photo: Khanh Linh

Specifically, in the supplementation according to the technical design, the delay in handing over 83 service road locations is the direct cause of the suspension of the construction of the safety fence system.

In parallel with that, the cost problem is also a significant pressure for contractors.

The fluctuation of DO oil and asphalt prices, along with the shortage of stone resources in the locality due to sharing with the Dong Dang - Tra Linh expressway project being implemented, also requires relevant parties to soon have stabilization solutions to ensure the overall progress of the entire project.

Khánh Linh
RELATED NEWS

Son La - Dien Bien expressway project to be implemented soon after many years of waiting

|

Dien Bien - Component project 1 of the Son La - Dien Bien - Tay Trang Border Gate expressway (phase 1) will be started on May 20th after many years of waiting.

Proposal to add 2,200 billion VND for the Huu Nghi - Chi Lang expressway

|

Lang Son - The investor proposed that the Government soon allocate 2,200 billion VND to accelerate the progress of the Huu Nghi - Chi Lang expressway project.

Dong Dang - Tra Linh expressway will be invested in completing emergency stop lanes

|

Cao Bang - Phase 2 of the expressway project will have a complete 22m roadbed invested, with emergency stop lanes on both sides.

People's Artist Thu Hien and many Vietnamese artists have spoken out when they were criticized for copyright

|

People's Artist Thu Hien, singer My Le, Thien Vuong and Vietnamese artists speak out because their music products have been "tipped" (reported of copyright infringement).

Hanoi supports temporary residence with a maximum of 15 million VND/month for households subject to clearance

|

Vice Chairman of Hanoi City People's Committee said that Hanoi has up to 26 specific mechanisms, helping to remove obstacles from the reality of land policy through periods.

Car suddenly catches fire in the middle of the road in Ho Chi Minh City

|

Ho Chi Minh City - A car traveling on Huynh Tan Phat street (Ho Chi Minh City) suddenly caught fire fiercely, completely burning the vehicle.

Trump says stop attacking Iran, reveals opportunity to reach nuclear deal

|

Mr. Trump said he had suspended a planned attack on Iran after Tehran sent a new peace proposal.

Son La - Dien Bien expressway project to be implemented soon after many years of waiting

QUANG ĐẠT - THANH BÌNH |

Dien Bien - Component project 1 of the Son La - Dien Bien - Tay Trang Border Gate expressway (phase 1) will be started on May 20th after many years of waiting.

Proposal to add 2,200 billion VND for the Huu Nghi - Chi Lang expressway

Khánh Linh |

Lang Son - The investor proposed that the Government soon allocate 2,200 billion VND to accelerate the progress of the Huu Nghi - Chi Lang expressway project.

Dong Dang - Tra Linh expressway will be invested in completing emergency stop lanes

Tân Văn |

Cao Bang - Phase 2 of the expressway project will have a complete 22m roadbed invested, with emergency stop lanes on both sides.