Expressway construction bustling, workers determined to open to traffic at the end of June 2026

Thành Nhân |

An Giang - The construction site of the Chau Doc - Can Tho - Soc Trang expressway through An Giang is under urgent construction, determined to open to traffic on June 30, 2026.

Bustling from early morning

Recorded by reporters at package 42 of the Chau Doc - Can Tho - Soc Trang expressway project (section passing through An Giang province), from early morning, the sound of rollers, bulldozers, and dump trucks carrying soil and rocks has echoed continuously. On the main route, groups of workers divided up to take on the items: roadbed construction workers, drainage culvert installation workers, taluy reinforcement workers...

Mr. Hoang Quoc Viet - bulldozer operator - shared: "The workers determined that this is a key national project, so everyone is clearly aware of their responsibilities. During Tet, the team of workers still works across the construction site, determined to maintain progress to promptly open the entire route to traffic on June 30, 2026 according to the direction of the Prime Minister.

Không khí lao động khẩn trương tại công trường cao tốc Châu Đốc – Cần Thơ – Sóc Trăng. Ảnh: Thành Nhân
Urgent working atmosphere at the construction site at package 42 of the Chau Doc - Can Tho - Soc Trang expressway project. Photo: Thanh Nhan

Under the harsh sun of the Mekong Delta, sweat soaks our backs, but we still stick to the construction site. Many people have been attached for many months, gradually getting used to the'3 shifts, 4 shifts' working schedule, throughout the holidays to ensure progress," Mr. Viet added.

Mr. Duong Van Huy - Construction Technical Team of package 42 of the Chau Doc - Can Tho - Soc Trang expressway project - confided: "Working at the construction site is hard, with erratic sunshine and rain, but the brothers always encourage each other to try harder. Being able to contribute a part of their efforts to complete the expressway soon, helping people travel more conveniently, and the local economy develop, everyone is proud.

Maintain construction pace, stick to progress

The Chau Doc - Can Tho - Soc Trang expressway project is expected to open a strategic traffic axis, connecting the Southwest border area with the delta center and the seaport system. The section through An Giang province plays an important role in completing the transport infrastructure network, creating motivation for socio-economic development of the locality.

Captain Tran Minh Thanh - Deputy Director of the Truong Son 11 Steering Committee (12th Corps) - said that currently there are about 150 officials, engineers, and workers at the construction site, along with nearly 100 vehicles and machinery and equipment mobilized. Taking advantage of favorable weather conditions, the unit organizes continuous construction "3 shifts, 4 crews", working day and night. During the Binh Ngo Tet 2026, the team of officials, engineers, and workers will not return to their hometowns but will continue to stick to the construction site.

Các phương tiện cơ giới hoạt động đồng loạt trên tuyến dự án cao tốc.
Motorized vehicles operate simultaneously at package 42 of the Chau Doc - Can Tho - Soc Trang expressway project. Photo: Thanh Nhan

Up to now, package 42 of the Chau Doc - Can Tho - Soc Trang expressway project has reached a construction volume of 73.8%. We identify this as a project of particular importance to the people of the Mekong Delta, especially the people of the border area of An Giang province. Therefore, despite many difficulties, the collective of officials, engineers and workers is determined to strive to complete and open the entire route to traffic on June 30, 2026 according to the direction of the Prime Minister," Captain Tran Minh Thanh emphasized.

According to Captain Tran Minh Thanh, to ensure progress, many construction teams are arranged to work in flexible shifts. At night, under the lights of the construction site, vehicles carrying materials still line up to enter and exit. Construction teams are continuously deployed, ensuring technical quality and labor safety.

Thành Nhân
RELATED NEWS

200 workers construct the Chau Doc - Can Tho - Soc Trang expressway during the New Year holiday

|

An Giang - 200 officials, engineers, and workers constructing the Chau Doc - Can Tho - Soc Trang expressway, determined to stick to the construction site throughout the New Year.

Mobilizing machinery and human resources to construct the Chau Doc - Can Tho - Soc Trang expressway

|

An Giang - At the Chau Doc - Can Tho - Soc Trang expressway construction site (through An Giang), the contractor mobilized all resources to aim for the end of June 2026.

Overcoming the southwest sun, workers speed up the progress of the Chau Doc - Can Tho - Soc Trang expressway

|

An Giang - Amid the severe heat in the West, hundreds of workers are still stuck at the construction site at package 42 of the Chau Doc - Can Tho - Soc Trang Expressway project.

Draft Report of the Executive Committee of the Vietnam General Confederation of Labor (XIII term) at the XIV Congress of the Vietnam Trade Union, term 2026 - 2031

|

Building a comprehensively strong Vietnam Trade Union; focusing on representing, caring for, and protecting union members and workers; promoting the pioneering role, spirit of innovation and creativity, contributing to realizing the aspiration to build a rich, prosperous, civilized, and happy country.

Head of the Hanoi Party Committee's Organization Committee Ha Minh Hai becomes Deputy Head of the Central Organization Committee

|

Head of the Hanoi Party Committee's Organization Committee Ha Minh Hai was transferred and appointed by the Secretariat to hold the position of Deputy Head of the Central Organization Committee.

Lao Dong Newspaper organizes Green Transformation Day 2026 with many attractive activities

|

On May 16, 2026, Lao Dong Newspaper organized Green Transformation Day 2026 with the participation of many famous singers, along with electric vehicle experience activities and the "Gasoline exchange for electricity" program.

Dong Thap Provincial People's Council unanimously agrees on the policy of establishing 11 wards

|

Dong Thap - The Provincial People's Council unanimously established 11 wards to meet the requirements of urban development and improve the efficiency of state management in the area.

200 workers construct the Chau Doc - Can Tho - Soc Trang expressway during the New Year holiday

Thành Nhân |

An Giang - 200 officials, engineers, and workers constructing the Chau Doc - Can Tho - Soc Trang expressway, determined to stick to the construction site throughout the New Year.

Mobilizing machinery and human resources to construct the Chau Doc - Can Tho - Soc Trang expressway

Thành Nhân |

An Giang - At the Chau Doc - Can Tho - Soc Trang expressway construction site (through An Giang), the contractor mobilized all resources to aim for the end of June 2026.

Overcoming the southwest sun, workers speed up the progress of the Chau Doc - Can Tho - Soc Trang expressway

Thành Nhân |

An Giang - Amid the severe heat in the West, hundreds of workers are still stuck at the construction site at package 42 of the Chau Doc - Can Tho - Soc Trang Expressway project.