Vietnam's highest vertical cable-stayed bridge accelerates to wait for assembly after nearly 11 years

Anh Tú |

Ho Chi Minh City - Phuoc Khanh bridge (belonging to Ben Luc - Long Thanh expressway) has reached about 96% of the volume, and is focusing all efforts on construction waiting for completion in May 2026.

According to the Southern Expressway Project Management Board, on the Phuoc Khanh bridge construction site (belonging to the Ben Luc - Long Thanh expressway), there are currently hundreds of engineers and workers clinging to construction continuously. To date, the total volume of works has reached about 96%.

Vị trí cầu Phước Khánh bắc qua sông Lòng Tàu, kết nối xã Bình Khánh (TPHCM) và xã Đại Phước (Đồng Nai). Ảnh: Anh Tú
Location of Phuoc Khanh bridge across the Long Tau River, connecting Binh Khanh commune (HCMC) and Dai Phuoc commune (Dong Nai). Photo: Anh Tu

In the cable-stay item, contractors are focusing maximum manpower and equipment to construct and stretch the last bundles of cables at the main pillars in Dong Nai and Ho Chi Minh City. Along with that, the approach bridge pillars have completed the girder blocks. In the approach road area at both ends of the bridge, the work of asphalting the road surface, installing reinforced steel, pouring concrete for railings and lighting systems is in the basic completion phase. All resources are currently being maximized by units, aiming to officially close the main span of Phuoc Khanh bridge in May 2026.

Nhịp độ thi công được duy trì liên tục, khối lượng tổng thể dự án hiện đã vượt mức 95%.
The construction pace is maintained continuously, the overall project volume has now exceeded 96%. Photo: Anh Tu
Công tác căng kéo những bó cáp dây văng cuối cùng đang được các nhà thầu đẩy nhanh tiến độ.
The work of stretching the last bundles of cables is being accelerated by contractors. Photo: Anh Tu

Phuoc Khanh bridge spans the Long Tau River, connecting Binh Khanh commune (HCMC) with Dai Phuoc commune (Dong Nai). The bridge has a total length of 3,186 m, a width of nearly 22 m, a scale of 4 lanes, and a design speed of 100 km/h. The technical highlight of the project is the main span 300 m long with a navigation clearance of 55 m - the highest in Vietnam today.

This design ensures a safe corridor for ships with a tonnage of up to 30,000 tons to conveniently circulate into upstream port systems, especially the Cai Mep - Thi Vai international port cluster. The bridge pillars are also calculated to withstand impacts from ships over 20,000 tons.

Hạng mục kết cấu bê tông, xà mũ tại các trụ cầu dẫn đã cơ bản hoàn thiện.
Concrete structure items and beams at the approach bridge pillars have been basically completed. Photo: Anh Tu
Đường dẫn phía bờ Nhờn Trạch (Đồng Nai) đang thi công cốt thép và đổ bê tông hạng mục lan can.
The access road on the Dong Nai bank is undergoing steel reinforcement and concrete pouring for the railing item. Photo: Anh Tu

Looking back at the implementation process, Phuoc Khanh bridge was officially started in July 2015. However, the project progress was interrupted for many years due to problems when belonging to the old J3 package. After Vietnam Expressway Corporation (VEC) implemented the new J3-1 package (constructing the remaining part) in May 2023, the project accelerated again.

Đường dẫn 2 đầu cầu đã hoàn thành đang chờ kết nối. Ảnh: Anh Tú
Access roads at both ends of the bridge have been completed and are waiting for connection. Photo: Anh Tu
 Cầu Phước Khánh có tĩnh không thông thuyền lên tới 55 m. Ảnh: Anh Tú
Phuoc Khanh bridge has a navigation clearance of up to 55 m. Photo: Anh Tu

The Ben Luc - Long Thanh expressway has a total length of nearly 58 km. Currently, the project has completed about 55 km, of which 30 km have been put into temporary operation. Phuoc Khanh Bridge is identified as the "key" to close the entire route. Ensuring the closing milestone in May 2026 will create a decisive premise to bring the project to traffic on the entire route in the third quarter of 2026.

This strategic transport corridor axis, when completed, will be directly interconnected with the Ho Chi Minh City - Trung Luong expressway, Ring Road 3 of Ho Chi Minh City and Bien Hoa - Vung Tau expressway, helping to reduce the load on the inner city of Ho Chi Minh City, shortening the time from the Mekong Delta provinces to Long Thanh International Airport, creating a breakthrough momentum for the entire Southern region.

Anh Tú
RELATED NEWS

Accelerate construction of Ring Road 2.5 section passing through Cau Giay, Yen Hoa

|

Hanoi - Ring Road 2.5 project section passing through Cau Giay and Yen Hoa wards is being implemented urgently, mobilizing maximum manpower, machinery and continuous construction.

Progress of the intersection worth more than 565 billion VND belonging to the Nguyen Trai bridge project in Hai Phong City

|

Hai Phong - By the end of March 2026, the site clearance progress of the Nguyen Trai - Le Hong Phong intersection will only reach about 60%.

Throughout Tet on the large construction site of Ring Road 3 and Phuoc Khanh bridge

|

Ho Chi Minh City - Leaving aside personal matters, many workers are still diligently constructing throughout Tet on Ring Road 3 and Phuoc Khanh bridge, determined to open traffic on schedule.

Live football Man City vs Liverpool in the FA Cup quarterfinals

|

The match between Man City and Liverpool in the FA Cup quarter-finals, takes place at 6:45 PM on April 4 (Vietnam time).

Land acquisition from 9 communes and wards in Dong Nai to open a road connecting Long Thanh airport

|

Dong Nai - The project of compensation, support, resettlement, and site clearance for DT. 770B road recovers about 271.6 ha of land.

Iran accuses 2 neighboring countries of aiding the US and Israel

|

The Iranian Foreign Ministry believes that some Middle Eastern countries may have directly supported the military campaign of the US and Israel targeting this country.

Early summer, young people invite each other to cycle around West Lake after work

|

Hanoi - Cool summer afternoon weather makes the cycling trend around West Lake return, attracting many young people to come to exercise and relax after a long day.

President Trump declares Britain is no longer America's "best ally

|

US President Donald Trump affirmed that the United Kingdom is not currently the best ally of the US after disagreements over the military campaign in Iran.

Accelerate construction of Ring Road 2.5 section passing through Cau Giay, Yen Hoa

Hữu Vũ |

Hanoi - Ring Road 2.5 project section passing through Cau Giay and Yen Hoa wards is being implemented urgently, mobilizing maximum manpower, machinery and continuous construction.

Progress of the intersection worth more than 565 billion VND belonging to the Nguyen Trai bridge project in Hai Phong City

Mai Dung |

Hai Phong - By the end of March 2026, the site clearance progress of the Nguyen Trai - Le Hong Phong intersection will only reach about 60%.

Throughout Tet on the large construction site of Ring Road 3 and Phuoc Khanh bridge

Minh Tâm - Anh Tú |

Ho Chi Minh City - Leaving aside personal matters, many workers are still diligently constructing throughout Tet on Ring Road 3 and Phuoc Khanh bridge, determined to open traffic on schedule.