Trillion-VND pedestrian bridge across Saigon River misses completion plan

MINH QUÂN |

Ho Chi Minh City - The pedestrian bridge across the Saigon River, with a total capital of nearly 1,000 billion VND, is late for completion and commissioning on September 2nd.

Started in March 2025, the pedestrian bridge across the Saigon River is located between Ba Son Bridge and the Saigon River tunnel, connecting the center of Ho Chi Minh City and Thu Thiem New Urban Area.

In May 2026, leaders of the Ho Chi Minh City People's Committee, when inspecting the project, requested units to focus manpower and equipment to ensure the completion of the project on National Day September 2nd.

Thi công các trụ cầu và cầu dẫn ở hai bờ sông Sài Gòn.  Ảnh: Anh Tú
Construction of bridge pillars and approach bridges on both banks of the Saigon River. Photo: Anh Tu
Phối cảnh cầu đi bộ khi hoàn thành.  Ảnh: Nhà đầu tư
Perspective of the pedestrian bridge when completed. Photo: Investor

However, on August 25, according to investor Nutifood, the plan to tow the main bridge, mooring and technical clearance by the end of August 2026 must be adjusted because the specialized barge cannot be handed over on schedule.

According to the initial plan, the main span is 187 m long, weighing nearly 1,350 tons, along with a support system of about 1,700 tons, which will be towed from Dong Xuyen Industrial Park, former Ba Ria - Vung Tau area, to two bridge abutments already built in Ho Chi Minh City.

Nhịp chính dài 187 m, nặng gần 1.350 tấn được thi công tại nhà máy ở Vũng Tàu.  Ảnh: Nhà đầu tư
The main span is 187 m long, weighing nearly 1,350 tons, constructed at a factory in Vung Tau. Photo: Investor
Phối cảnh cầu đi bộ qua sông Sài Gòn sau khi lắp đặt nhịp chính mang hình tượng lá dừa nước.  Ảnh: Nhà đầu tư
Perspective of the pedestrian bridge across the Saigon River after installing the main span bearing the image of water coconut leaves. Photo: Investor

The total volume of the main span complex and support system is about 3,000 tons. The transportation of large structural blocks on maritime routes with high ship density requires coordination, towing and strict safety assurance plans.

In addition to tidal and tidal factors, the transportation plan also depends on the type of barge with specific size and load capacity. The whole country currently only has two vehicles meeting this requirement, including the Trung Nam S05 barge.

Thi công trụ và đường dẫn đầu cầu phía Bến Bạch Đằng.  Ảnh: Anh Tú
Construction of pillars and approach roads at the beginning of Ben Bach Dang bridge (center of Ho Chi Minh City). Photo: Anh Tu

A representative of Vietrantimex - a barge supplier, said that Trung Nam S05 is serving key oil and gas projects. Bad weather at sea slows down the loading process at the mine, causing the time of handover of the barge to the pedestrian bridge project to be postponed.

Therefore, the towing, fusing and technical ventilation of the main span could not be carried out in time for National Day 2. 9.

Nutifood said it is coordinating with construction units to proactively prepare manpower, equipment and technical plans. As soon as the barge is handed over, the towing of the main span will be deployed to shorten delays and limit the impact on the overall progress.

Thi công trụ và đường dẫn đầu cầu phía Khu đô thị mới Thủ Thiêm.  Ảnh: Anh Tú
Construction of pillars and approach roads at the bridge head of Thu Thiem New Urban Area. Photo: Anh Tu

The pedestrian bridge is designed in the shape of water coconut leaves, a typical image of the South, combining traditional features with modern architecture, creating highlights for the central area of Ho Chi Minh City.

The project has open space, increasing visibility and ventilation for pedestrians; and also arranges lanes for bicycles, people with disabilities and can serve ambulances in case of emergency.

With a space steel arch structure, this design is applied for the first time in Vietnam and is expected to create one of the unique pedestrian bridges.

During the design process, the Chodai and Takashi Niwa Architects consortium and Chodai Kisojiban Vietnam calculated factors such as wind, earthquakes, ship collisions... to ensure the safety of the project and meet aesthetic requirements.

When completed, the bridge will not only serve the travel needs between the two banks of the Saigon River but is also expected to become a new public space, increasing access to the riverine landscape and creating more highlights for the central area of Ho Chi Minh City.

MINH QUÂN
RELATED NEWS

Saigon River pedestrian bridge enters key structural construction phase

|

Ho Chi Minh City - In the afternoon of May 11, the Saigon River pedestrian bridge project poured concrete for the first main pier base, aiming to be completed on September 2, 2026.

Pouring the first batch of concrete for the pedestrian bridge pillars worth nearly 1,000 billion VND across the Saigon River

|

Ho Chi Minh City - In the afternoon of May 11, the pedestrian bridge project across the Saigon River poured the first batch of concrete base pillars, striving to be inaugurated in 2026.

HCMC starts construction of a pedestrian bridge across the Saigon River worth nearly VND1,000 billion

|

HCMC - On the morning of March 29, the City People's Committee held a groundbreaking ceremony for the 720m long pedestrian bridge across the Saigon River with a total investment of nearly 1,000 billion VND, expected to be completed on April 30, 2026.

13 martyrs' remains found at Dien Khanh Citadel

|

Khanh Hoa - After a week of searching in the old prison area in Dien Khanh Citadel, functional forces discovered and exhumed 13 sets of remains of martyrs.

Lao Dong Newspaper acts as a bridge for readers to send "Words from the Heart" to parents during Vu Lan season

|

Write loving words from your heart during the Vu Lan season, Lao Dong Newspaper will help you convey messages to your parents on live television...

Saigon River pedestrian bridge enters key structural construction phase

Bảo Tú |

Ho Chi Minh City - In the afternoon of May 11, the Saigon River pedestrian bridge project poured concrete for the first main pier base, aiming to be completed on September 2, 2026.

Pouring the first batch of concrete for the pedestrian bridge pillars worth nearly 1,000 billion VND across the Saigon River

Bảo Tú |

Ho Chi Minh City - In the afternoon of May 11, the pedestrian bridge project across the Saigon River poured the first batch of concrete base pillars, striving to be inaugurated in 2026.

HCMC starts construction of a pedestrian bridge across the Saigon River worth nearly VND1,000 billion

MINH QUÂN |

HCMC - On the morning of March 29, the City People's Committee held a groundbreaking ceremony for the 720m long pedestrian bridge across the Saigon River with a total investment of nearly 1,000 billion VND, expected to be completed on April 30, 2026.