Racing for progress at the 280 billion VND fishing port project in Ha Tinh

TRẦN TUẤN |

Ha Tinh - Taking advantage of favorable weather, contractors are racing to progress the construction of Cua Nhuong fishing port project with a total investment of 280 billion VND.

On July 26, at the construction site of Cua Nhuong Fishing Port (Cam Nhuong commune, Cam Xuyen district, Ha Tinh province), machinery and workers are focusing on constructing ship landing items, sand protection dikes, and dredging. suck the channel...

Present at the construction site, Mr. Nguyen Hong Son - technical officer of the Management Board of Agricultural Construction and Rural Development Investment Projects in Ha Tinh province - said that up to now the project has achieved construction volume. 60%.

“The Board is always closely monitoring and urging progress, contractors are also proactive, taking advantage of favorable weather to concentrate on construction. Hopefully by the end of the year, the storm situation will not be complicated so that the project can be completed on schedule" - Mr. Son shared.

According to Mr. Son, currently every day at the Cua Nhuong Fishing Port Project construction site, there are about 100 technical staff and workers focusing on construction to speed up progress as much as possible.

Cua Nhuong Fishing Port project has a total investment of 280 billion VND, invested by the Management Board of Agricultural Construction and Rural Development Investment Projects of Ha Tinh province, and started construction on January 20, 2024. According to schedule, the project must be completed before December 31, 2024.

This is a project using capital from compensation for marine environmental incidents of Hung Nghiep Formosa Ha Tinh Iron and Steel Company Limited.

This fishing port project has a capacity of 400 CV ships that can enter and exit the port during the dry season, the capacity to dock 100 ships/day, the amount of seafood passing through the port is about 16,000 tons/year, meeting a level 2 fishing port.

In addition to building a fishing port, the project also includes dredging the channel into the port and the water area in front of the port, and sand prevention dikes.

Some images captured by Lao Dong Newspaper reporters at the Cua Nhuong fishing port construction site on July 26:

The sand protection dike project has completed about 60% of its volume. Photo: Tran Tuan.
The sand protection dike project has completed about 60% of its volume. Photo: Tran Tuan.
Structural crane for sand protection dike construction. Photo: Tran Tuan.
Structural crane for sand protection dike construction. Photo: Tran Tuan.
The sand-dumping barge performs the task of clearing the channel. Photo: Tran Tuan.
The sand-dumping barge performs the task of clearing the channel. Photo: Tran Tuan.
Dock category. Photo: Tran Tuan.
Dock category. Photo: Tran Tuan.
Construction of wastewater treatment items. Photo: Tran Tuan.
Construction of wastewater treatment items. Photo: Tran Tuan.
The construction area of ​​Cua Nhuong fishing port has been leveled. Photo: Tran Tuan.
The construction area of ​​Cua Nhuong fishing port has been leveled. Photo: Tran Tuan.
TRẦN TUẤN
TIN LIÊN QUAN

Dự án nâng cấp cảng cá 460 tỉ đồng ở Quảng Ngãi đình trệ vì vướng mặt bằng

VIÊN NGUYỄN |

Vướng mặt bằng khiến dự án Nâng cấp, mở rộng khu neo đậu tránh trú bão kết hợp cảng cá Tịnh Hòa, TP Quảng Ngãi giậm chân tại chỗ.

Hối hả thi công Dự án cảng cá từ nguồn bồi thường của Formosa Hà Tĩnh

TRẦN TUẤN |

Hà Tĩnh - Sau nhiều năm chậm triển khai, Dự án đầu tư xây dựng mở rộng Cảng cá Thạch Kim (huyện Lộc Hà) đang được tập trung thi công để kịp hoàn thành theo tiến độ giao vào cuối năm 2024 này.

Vẫn chưa làm hệ thống xử lý nước thải ở cảng cá lớn nhất tỉnh Quảng Trị

HƯNG THƠ |

Cảng cá lớn nhất ở tỉnh Quảng Trị được nâng cấp, nhưng thiếu hạng mục xử lý nước thải, nếu hoạt động sẽ vi phạm Luật Bảo vệ môi trường năm 2020. Để khắc phục, phải bổ sung hạng mục nhà máy xử lý nước thải, nhưng hiện vẫn chưa triển khai thi công.

Trực tiếp bóng chuyền U23 Thể Công Tân Cảng vs U23 Ninh Bình

Nhóm PV |

Trực tiếp chung kết giải bóng chuyền U23 quốc gia giữa U23 Thể Công Tân Cảng vs U23 Ninh Bình vào lúc 20h ngày 19.9.

Chậu hoa giấy trên phố đi bộ ở Đà Nẵng đồng loạt "nằm" tránh bão

Nguyễn Linh |

UBND quận Hải Châu, TP Đà Nẵng cho biết đã chủ động đặt nằm các chậu hoa giấy tại phố đi bộ Bạch Đằng để tránh thiệt hại bởi ảnh hưởng của cơn bão số 4.

Nợ chế độ giáo viên Bình Định: Trách nhiệm "chảy" về trường

Hoài Phương |

Bình Định - Về việc giáo viên huyện miền núi Vân Canh bị nợ lương, chế độ kéo dài, các cơ quan, đơn vị liên quan đều cho rằng trách nhiệm chính thuộc về trường.

Chơi dưới chung cư, bé gái bị vật cứng rơi trúng, lõm sọ não

Hoàng Xuyến - Việt Anh |

Mới đây, tại một chung cư trên địa bàn Hà Nội xảy ra trường hợp bé gái bị một vật cứng như bát, đĩa sứ rơi trúng vào đầu, gây lõm sọ não.

Kỷ luật nguyên Thứ trưởng Bộ Tài chính Vũ Thị Mai

PHẠM ĐÔNG |

Bà Vũ Thị Mai - nguyên Thứ trưởng Bộ Tài chính - bị kỷ luật bằng hình thức Khiển trách do đã có những vi phạm, khuyết điểm trong công tác.