Officially from 0:01 on August 19, Lien Khuong airport resumes operation

Tô Thế |

After more than 5 months of suspension for repair, Lien Khuong airport will reopen from 0:01 on August 19.

On the afternoon of August 18, information from the Civil Aviation Authority of Vietnam (CAAV) said that after a period of suspension of operation to implement the Repair Project, runways, and taxiways, the CAAV issued a decision to restore the runways and taxiways at Lien Khuong International Airport to operation from 00:00 on August 19, 2026 (local time).

The Civil Aviation Authority of Vietnam requests Lien Khuong International Airport to be responsible for organizing the management and operation of runways and taxiways to ensure aviation safety and service quality, meeting operating standards according to regulations.

At the same time, organize the maintenance of the project according to regulations; update the above contents into the relevant document system at Lien Khuong International Airport and notify the above contents to airlines, agencies, and related units to coordinate in operating operations at the Airport to ensure safety and efficiency.

Đường băng cất hạ cánh sân bay Liên Khương đã sẵn sàng phục vụ ngày hoạt động trở lại vào 19.8 tới đây. Ảnh: Phúc Khánh
The runway for Lien Khuong airport to take off and land is ready to serve the reopening day on August 19. Photo: Phuc Khanh
Khu vực đón khách làm thủ tục tại sân bay Liên Khương đã được nâng cấp hiện đại hơn. Ảnh: Phúc Khánh
The check-in area at Lien Khuong airport has been upgraded to be more modern. Photo: Phuc Khanh

The Civil Aviation Authority of Vietnam also requested the Vietnam Air Traffic Management Corporation to be responsible for notifying domestic and international aviation news in accordance with current regulations. At the same time, directing the Southern Air Traffic Management Company to organize flight operations to ensure safety, regulation, and efficiency.

In addition, the Civil Aviation Authority of Vietnam requested the Southern Airport Authority to inspect and supervise the operation of Lien Khuong International Airport to ensure flight safety according to its functions, tasks and legal regulations.

Tô Thế
RELATED NEWS

Lien Khuong airport completes runway, counting down the days to welcome return flights

|

Lam Dong - After more than 5 months of temporary closure for upgrading and repairing, Lien Khuong airport has completed more than 99% of its volume, ready to reopen on August 19.

Lam Dong proposes to invest in Terminal T2 of Lien Khuong airport in 2027

|

Lam Dong - The Provincial People's Committee requested ACV to allocate resources and soon invest in Passenger Terminal T2 and Cargo Terminal at Lien Khuong International Airport in 2027.

ACV sprints to bring Lien Khuong airport back to operation from August 19

|

Lam Dong - After more than 5 months of repairs, ACV is completing the final items, striving to bring Lien Khuong airport back into operation from August 19.

Giant lantern cluster "telling folk stories" in a communal house over 160 years old in Ho Chi Minh City

|

In the space of Son Tra communal house, Ho Chi Minh City, over 160 years old, a 3.5m high lantern cluster with a giant toad attracts people and young people to admire the Mid-Autumn Festival.

Ho Chi Minh City Traffic Police will divert traffic around schools from 5:30 am on the opening day

|

Ho Chi Minh City Traffic Police will deploy forces from 5:30 am, divert traffic, handle violations, and limit congestion at schools on the opening day.

Eagerly awaiting the opening day in the open sea in Truong Sa Special Zone

|

Khanh Hoa - In Truong Sa Special Zone, officials, soldiers, teachers, parents and students are also busy preparing for the opening day.

Miss World 2026 stage by the Nha Trang beach

|

Khanh Hoa - The stage serving the Miss World 2026 final night located along Nha Trang beach has been completed and is ready to serve the competition.

Lien Khuong airport completes runway, counting down the days to welcome return flights

Phúc khánh |

Lam Dong - After more than 5 months of temporary closure for upgrading and repairing, Lien Khuong airport has completed more than 99% of its volume, ready to reopen on August 19.

Lam Dong proposes to invest in Terminal T2 of Lien Khuong airport in 2027

Phúc Khánh |

Lam Dong - The Provincial People's Committee requested ACV to allocate resources and soon invest in Passenger Terminal T2 and Cargo Terminal at Lien Khuong International Airport in 2027.

ACV sprints to bring Lien Khuong airport back to operation from August 19

Phúc Khánh |

Lam Dong - After more than 5 months of repairs, ACV is completing the final items, striving to bring Lien Khuong airport back into operation from August 19.