Chairman of Ben Tre requested to promote disbursement of public investment capital

Thành Nhân |

Chairman of Ben Tre requested maximum concentration of resources to accelerate the progress of 11 works, projects and programs, especially the Rach Mieu 2 bridge project.

According to Notice No. 81 of the People's Committee of Ben Tre province, as of July 15, the disbursement result of public investment capital in Ben Tre province reached 36.81% of the plan. Investors have a higher disbursement rate than the province's average, including: Ben Tre Agricultural and Rural Development Investment Project Management Board, Binh Dai District People's Committee, Project Management Board Civil and industrial projects, People's Committee of Cho Lach district, People's Committee of Ba Tri district.

According to the People's Committee of Ben Tre province, although economic growth has achieved good results, it still faces many difficulties and challenges. The results achieved by the locality have not had a breakthrough, ranking 12/13 provinces and cities in the Mekong Delta region. Sectors and levels need to review and evaluate more objectively why growth results are low, while there is still a lot of room for development in the province. In addition, many policies and projects are slowly being removed, especially site clearance work to speed up the progress of works and projects and put them into use soon.

In particular, in the performance of tasks, there is still a situation of avoiding and pushing work, "going around in circles", not daring to advise or propose definitive handling, and not deciding on work within one's authority. occurs in a number of agencies, units and localities, in a section of officials, civil servants and public employees. Although decentralization and decentralization have been implemented, it is not really strong or drastic...

Previously, giving a directive speech at the Conference summarizing the implementation of socio-economic development tasks in the first 6 months of the year, implementing key tasks in the last 6 months of 2024 on July 18, Chairman of the Provincial People's Committee Ben Tre Tran Ngoc Tam requested that the Heads of departments, branches and branches of the province, Chairman of the People's Committees of districts and cities need to be more determined, make greater efforts, act more decisively, promote acceleration and breakthroughs. in leadership, direction and administration, strengthening inspection and supervision, getting things done, focusing on removing difficulties and obstacles in the process of implementing tasks.

Chairman of Ben Tre Provincial People's Committee Tran Ngoc Tam. Photo: Thanh Nhan
Chairman of Ben Tre Provincial People's Committee Tran Ngoc Tam. Photo: Thanh Nhan

“Concentrate maximum resources to accelerate the implementation of 11 works, projects and programs according to the Resolution of the 11th Congress of the Provincial Party Committee, especially the Rach Mieu 2 bridge project and the Road access road project. to Rach Mieu 2 bridge, Phu Thuan Industrial Park project and 3 industrial clusters Tan Thanh Binh, Phong Nam and Town - An Duc, Lac Dia Area Investment project, urban projects (especially the project Investment in developing new urban areas My An and My Hoa - Ben Tre city), wind power; Cho Lach Cultural and Tourism Village Project. Deploy construction of Ba Lai 8 bridge. At the same time, continue to complete investment preparations for coastal roads in Ben Tre province, launch the Ben Tre Green Hydrogen Plant project, and conduct bidding Ben Tre General Hospital project, speeding up the construction progress of Ben Tre Waste Treatment Plant and urban projects.

Wherever there are any difficulties or problems, the agency or unit assigned to preside over them must proactively coordinate with relevant departments, branches and localities to come up with solutions and solutions. ensure compliance with current regulations. On that basis, promptly report and propose the Provincial People's Committee to consider and give opinions to continue directing quick and effective implementation," Chairman of Ben Tre Provincial People's Committee Tran Ngoc Tam requested.

The Chairman of Ben Tre Provincial People's Committee also requested investors to drastically promote disbursement of public investment capital , promptly handle difficulties and obstacles to speed up the progress of important infrastructure works and projects, key and national target programs, striving to disburse over 95% of the assigned plan. In particular, for the 23 units disbursing public investment capital that are still low, any unit that does not complete the capital plan and does not report promptly will be responsible to the Provincial People's Committee and Chairman of the Provincial People's Committee. At the same time, the Department of Planning and Investment was assigned to closely monitor the progress of disbursement of public investment capital and advise on the effective use of allocated public investment capital.

Thành Nhân
TIN LIÊN QUAN

Nguyên nhân Khánh Hòa giải ngân vốn đầu tư công thấp

Hữu Long |

Khánh Hòa - Đề xuất các chủ đầu tư phải cam kết giải ngân vốn năm 2024 đạt 95% trở lên và chịu trách nhiệm về việc không hoàn thành giải ngân kế hoạch năm.

Giải ngân đầu tư công ở Bạc Liêu: 16 sở, ban, ngành chỉ 1 đơn vị đạt 100%

NHẬT HỒ |

Nhiều dự án chậm kế hoạch, chủ đầu tư xin điều chỉnh thời gian tiến độ thực hiện, trong khi người dân nhìn vào thấy cầu, đường làm mãi không xong. Chủ tịch Bạc Liêu Phạm Văn Thiều cho rằng, người dân bức xúc là đúng, chúng ta không thể để xây dựng cơ bản lúc nào cũng chậm.

Đến ngày 30.5, Bến Tre giải ngân vốn đầu tư công đạt gần 30% kế hoạch

Thành Nhân |

Đến ngày 30.5.2024, giải ngân các nguồn vốn đầu tư công theo kế hoạch (bao gồm cả vốn kéo dài) là 1.291.321 triệu đồng, đạt tỉ lệ 27,88% so với kế hoạch. Có 12 đơn vị chủ đầu tư có tiến độ giải ngân vốn đầu tư công tốt.

Vụ công trình làm nứt nhà dân ở Hà Nội, chính quyền nói gì?

NHÓM PV |

Theo chính quyền phường Quang Trung, hình ảnh công nhân đang làm việc tại công trình số nhà 19, ngõ 136/98 Tây Sơn là để hút nước phòng dịch sốt xuất huyết.

Triều Tiên cho nổ tung tuyến đường bộ nối với Hàn Quốc

Khánh Minh |

Triều Tiên cho nổ tung các tuyến đường nối với Hàn Quốc vốn từng được coi là biểu tượng của sự hợp tác liên Triều.

Thân tín của bà trùm ma túy Oanh "Hà" được trả công 15 tỉ

Việt Dũng |

Trong số hơn 626kg ma túy mua bán xuyên quốc gia do bà trùm Oanh "Hà" cầm đầu, Nguyễn Văn Nam có mặt hầu hết ở các chuyến hàng, nhận công hậu hĩnh.

Bất cập tiền công đức 2 đền ở Ninh Bình do nguồn thu quá lớn

NGUYỄN TRƯỜNG |

Ninh Bình - Những tồn tại, bất cập trong việc quản lý tiền công đức tại đền Dâu và đền Quán Cháo (thành phố Tam Điệp) là do nguồn thu quá lớn.

Chánh văn phòng hãng luật bị tố đe dọa, xúc phạm phụ nữ

TRÍ MINH |

Một chánh văn phòng hãng luật bị tố cáo có hành vi đe dọa, xúc phạm danh dự, nhân phẩm phụ nữ. Người dân đã trình báo sự việc tới cơ quan công an.

Nguyên nhân Khánh Hòa giải ngân vốn đầu tư công thấp

Hữu Long |

Khánh Hòa - Đề xuất các chủ đầu tư phải cam kết giải ngân vốn năm 2024 đạt 95% trở lên và chịu trách nhiệm về việc không hoàn thành giải ngân kế hoạch năm.

Giải ngân đầu tư công ở Bạc Liêu: 16 sở, ban, ngành chỉ 1 đơn vị đạt 100%

NHẬT HỒ |

Nhiều dự án chậm kế hoạch, chủ đầu tư xin điều chỉnh thời gian tiến độ thực hiện, trong khi người dân nhìn vào thấy cầu, đường làm mãi không xong. Chủ tịch Bạc Liêu Phạm Văn Thiều cho rằng, người dân bức xúc là đúng, chúng ta không thể để xây dựng cơ bản lúc nào cũng chậm.

Đến ngày 30.5, Bến Tre giải ngân vốn đầu tư công đạt gần 30% kế hoạch

Thành Nhân |

Đến ngày 30.5.2024, giải ngân các nguồn vốn đầu tư công theo kế hoạch (bao gồm cả vốn kéo dài) là 1.291.321 triệu đồng, đạt tỉ lệ 27,88% so với kế hoạch. Có 12 đơn vị chủ đầu tư có tiến độ giải ngân vốn đầu tư công tốt.