Workers speed up construction of drainage culverts to prevent sand floods

Duy Tuấn |

Binh Thuan - Workers are speeding up the construction of a drainage culvert to complete the drainage line, ending sand overflow when it rains in Phan Thiet.

On the afternoon of September 10, at the construction site of the drainage line, there were 2 teams of workers installing drainage pipes on 1/5 Street, Phu Hai Ward and Nguyen Thong Street branch.

Location of drainage construction. Photo: Duy Tuan
Location of drainage construction. Photo: Duy Tuan

After digging the ground, large pipes are lowered into the trench, supports are installed, the connectors are aligned and concrete is poured into the joints.

Excavator lowering the pedestal into the sewer. Photo: Duy Tuan
Excavator lowering the pedestal into the sewer. Photo: Duy Tuan
Sewer pipes waiting to be installed. Photo: Duy Tuan
Sewer pipes waiting to be installed. Photo: Duy Tuan

The Binh Thuan Province Civil and Industrial Construction Investment Project Management Board has mobilized a large number of workers to speed up the construction. Because when it rains, the drainage system is not yet complete, a large amount of rainwater from Vo Nguyen Giap Street will flow down to Nguyen Thong Street, bringing sand, causing red sand floods to continuously flow down the street on September 3, 4 and 5. Although the locality has implemented temporary solutions such as building stone embankments, they only temporarily block the flow.

Excavator lifting materials for construction. Photo: Duy Tuan
Excavator lifting materials for construction. Photo: Duy Tuan

Mr. Nguyen Minh Nguyen, Deputy Director of the Management Board of Investment and Construction of Civil and Industrial Works of Binh Thuan province, said that to speed up the construction progress by dividing into 2 construction teams and these 2 teams will be connected together, the construction progress time will end on September 30, 2024, to facilitate the settlement of drainage route No. 1 for people in the downstream area and Nguyen Thong street area.

Measuring the distance under the trench to place the culvert. Photo: Duy Tuan
Measuring the distance under the trench to place the culvert. Photo: Duy Tuan

Although the construction was urgent, according to records, the details placed in the sewer were all measured correctly by workers.

Pouring concrete joints between sewers. Photo: Duy Tuan
Pouring concrete joints between sewers. Photo: Duy Tuan
Workers mixing fresh concrete. Photo: Duy Tuan
Workers mixing fresh concrete. Photo: Duy Tuan

"There is still a short section left, we will try to finish the construction by the full moon of the Mid-Autumn Festival, connect to construction point number 2 and complete the drainage line," a worker at the construction site shared.

A manhole on a sewer. Photo: Duy Tuan
A manhole on a sewer. Photo: Duy Tuan

As Lao Dong reported, heavy rain and water from the high hills on Vo Nguyen Giap Street (706B) overflowed, carrying red sand from along 706B Street down to Nguyen Thong Street, causing local flooding. The strong floodwaters carried a large amount of red sand onto the road.

A section of the sewer has been installed. Photo: Duy Tuan
A section of the sewer has been installed. Photo: Duy Tuan
Machinery is mobilized for construction. Photo: Duy Tuan
Machinery is mobilized for construction. Photo: Duy Tuan

The reason is that the stormwater drainage system in the area has not been connected to the drainage line of exit 1, road 706B, so the overflowing water carries red sand and mud from the high hills down to the lowlands. Therefore, the units are speeding up the construction to complete the drainage line as soon as possible to end the situation of sand flooding during heavy rains.

Duy Tuấn
TIN LIÊN QUAN

Nhiều tuyến đường đấu nối vào quốc lộ dừng thi công

PHÚC ĐẠT - NGUYỄN LUÂN |

HUẾ - Nhiều dự án đầu tư xây dựng nút giao thông đường ngang đấu nối vào Quốc lộ 1A (đoạn qua địa phận Thừa Thiên Huế) buộc phải tạm ngưng thi công.

Hoàn thành kè rọ đá làm giảm lực dòng chảy khi lũ cát tràn

Duy Tuấn |

Bình Thuận - Một kè bằng rọ đá tức tốc được hoàn thành để giảm lực dòng chảy cát tràn, hạn chế lượng cát tràn xuống đường.

Cận cảnh dòng chảy cát tràn cuốn trôi người và xe máy

Duy Tuấn |

Bình Thuận - Chiều 3.9, dòng chảy cát đỏ lại đổ tràn xuống đường ra khu du lịch Mũi Né khi mưa lớn, cuốn trôi người và xe máy.

Chốt phương án tái định cư cho Làng Nủ sau thiên tai

Bảo Nguyên |

Lào Cai - Khu tái định cư này trước mắt dự kiến bố trí 40 ngôi nhà cho 40 gia đình Làng Nủ bị thiệt hại trong trận lũ quét, sạt lở đất vừa qua.

Thông đường sắt Hà Nội - Lào Cai, đưa hàng cứu trợ đến vùng lũ

Đinh Đại |

Đường sắt Hà Nội - Lào Cai đã được thông tuyến, khai thác trở lại để vận chuyển hàng cứu trợ đến người dân vùng lũ.

Mưa lớn, đường Vành đai 3 ở Hà Nội ngập nặng

NHÓM PV |

Trận mưa lớn diễn ra đêm qua, rạng sáng nay (16.9) khiến nhiều tuyến phố trên địa bàn TP Hà Nội bị ngập nặng, ùn tắc nghiêm trọng.

Một doanh nghiệp công bố 97 lần mua lại trái phiếu trước hạn

Lục Giang |

Chỉ trong hơn 6 tháng, Saigon Glory đã 97 lần công bố mua lại trái phiếu trước hạn với tổng giá trị mua lại đạt 991,27 tỉ đồng.

Dự báo địa điểm bão Bebinca đổ bộ Trung Quốc sáng nay

Thanh Hà |

Theo dự báo bão mới nhất, bão Bebinca có khả năng đổ bộ vào đất liền Trung Quốc, ở khu vực giữa Bình Hồ, Chiết Giang và Thượng Hải trong sáng 16.9.