The bottom spillway of Hoa Binh hydroelectric reservoir and the bottom spillway of Tuyen Quang hydroelectric reservoir are ordered to be closed

Huy Hùng |

1 bottom spillway of Hoa Binh hydroelectric reservoir and 1 bottom spillway of Tuyen Quang hydroelectric reservoir were ordered to close at 5:00 p.m. on October 16.

The Ministry of Agriculture and Environment has just issued a telegram on closing the bottom spillway of Tuyen Quang hydroelectric reservoir and closing the bottom spillway of Hoa Binh hydroelectric reservoir.

The dispatch clearly stated that at 10:00 on October 16, 2025, the upstream water level of Tuyen Quang Lake was at elevation of 116.81m, downstream water level was 52.28m, downstream water was 1,110m3/s, total downstream flow was 1,218m3/s; the upstream water level of Hoa Binh Lake was at elevation of 115.51m, downstream water was 13.24m, downstream water was 491m3/s, total downstream water was 4,220m3/s.

Implementing the Inter-reservoir operation process in the Red River basin in Decision No. 740/QD-TTg dated June 17, 2019 of the Prime Minister, Decision No. 922/QD-TTg dated May 14, 2025 of the Prime Minister amending and supplementing a number of articles of the Inter-reservoir operation process in the Red River basin, the Minister of Agriculture and Environment ordered the Director of Tuyen Quang Hydropower Company and the Director of Hoa Binh Hydropower Company:

Closing 1 bottom spillway of Tuyen Quang hydroelectric reservoir at 5:00 p.m. on October 16, 2025.

Closing 1 bottom spillway of Hoa Binh Hydropower Reservoir at 5:00 p.m. on October 16, 2025.

Closely monitor the developments of floods, construction safety, flow to the reservoir, water levels upstream and downstream of the reservoir and promptly report to the Ministry of Agriculture and Environment (through the Department of Dyke Management and Natural Disaster Prevention and Control) and relevant agencies according to regulations.

To ensure safety downstream when operating Tuyen Quang and Hoa Binh hydroelectric reservoirs, in an official dispatch sent to Tuyen Quang, Phu Tho, Hanoi, Bac Ninh, Hai Phong, Hung Yen, Ninh Binh, the Ministry of Agriculture and Environment requested the People's Committees of provinces and cities:

Notify authorities at all levels, people, and organizations operating on rivers and along rivers to know information to proactively take measures to ensure safety and adjust operations accordingly.

Timely report any unusual situations to the Ministry of Agriculture and Environment (through the Department of Dyke Management and Natural Disaster Prevention and Control).

Huy Hùng
RELATED NEWS

Order to open the bottom spillway of Hoa Binh hydroelectric reservoir this afternoon, 6 provinces and cities must ensure safety

|

The bottom spillway of Hoa Binh hydroelectric reservoir was opened at 3:00 p.m. on October 14.

Tuyen Quang Hydropower Plant is ordered to close another bottom spillway this afternoon

|

Another bottom spillway of Tuyen Quang hydroelectric reservoir was ordered to close at 4:00 p.m. on October 12.

The bottom spillway of Tuyen Quang hydroelectric reservoir is ordered to be closed immediately, 3 provinces and cities must ensure safety

|

A bottom spillway of Tuyen Quang hydroelectric reservoir was ordered to close at 5:00 p.m. on October 11.

Vietnam promotes the establishment of a cooperation mechanism to combat fraud crimes in Cambodia

|

Vietnam is in talks with partners to establish a cooperation mechanism to combat organized crime and high-tech crimes in Cambodia.

Hundreds of container trucks gathered abnormally in an industrial cluster in Dak Lak

|

Dak Lak - About 170 heavy-duty container trucks carrying agricultural products are illegally gathered inside Tan An Industrial Cluster.

From 2026, electronic signatures and trust services must be periodically audited

|

The Ministry of Science and Technology (MTST) has just issued a Circular regulating technical auditing for electronic signatures and trust services.

Temporarily suspending the construction of Ban Kieng hydropower plant to overcome people's problems

|

Tuyen Quang - The investor of the Ban Kieng hydropower project said that construction will be temporarily suspended until recovery is achieved to ensure safety.

Strengthening the organization and enhancement of press activities in the Front

|

Vice President of the Central Committee of the Vietnam Fatherland Front Ha Thi Nga aims to strengthen the organization and improve the quality of press activities in the Front, contributing to building the great solidarity bloc.

Order to open the bottom spillway of Hoa Binh hydroelectric reservoir this afternoon, 6 provinces and cities must ensure safety

Huy Hùng |

The bottom spillway of Hoa Binh hydroelectric reservoir was opened at 3:00 p.m. on October 14.

Tuyen Quang Hydropower Plant is ordered to close another bottom spillway this afternoon

Huy Hùng |

Another bottom spillway of Tuyen Quang hydroelectric reservoir was ordered to close at 4:00 p.m. on October 12.

The bottom spillway of Tuyen Quang hydroelectric reservoir is ordered to be closed immediately, 3 provinces and cities must ensure safety

Huy Hùng |

A bottom spillway of Tuyen Quang hydroelectric reservoir was ordered to close at 5:00 p.m. on October 11.