With this result, Da Nang city ranked 5th/34 localities and higher than the same period in 2025 by 25.53 percentage points.
According to the Da Nang City Department of Finance, the total planned public investment capital of the state budget for 2026 of Da Nang assigned and supplemented by the Prime Minister in the year is 17,191,915 billion VND. As of August 31, the city has disbursed 11,351,059 billion VND.
Of which, central budget capital disbursed 1,350.553 billion VND, reaching 39.8%. Local budget capital disbursed 10,000.506 billion VND, reaching 72.5%.
Compared to the end of July 2026, the disbursed value increased by more than 2,537 billion VND, equivalent to 28.79%. Meanwhile, the average disbursement rate nationwide reached 51.9% and the average of 34 localities reached 56.9%.
Some project management boards have high disbursement rates. The Management Board of Priority Infrastructure Investment Projects reached 76.16%. The Management Board of Investment Projects for Construction of Transport and Agricultural Works reached 75.88%.
However, progress in wards and communes is still low. The total capital plan of 93 wards and communes is more than 6,903 billion VND. By the end of August, only 3,536.766 billion VND had been disbursed, reaching 51.23%.
Only 12/93 wards and communes achieved a disbursement rate above the city's average level. 81 localities are lower than the level of 66.03%.
The city requests localities to focus on removing obstacles, especially compensation, site clearance, investment procedures, acceptance and payment. These are the stages that determine the ability to complete the disbursement plan for 2026.