Speeding up the completion of the trillion-dong hospital project in Ben Tre

Thành Nhân |

Ben Tre - The Provincial People's Committee will direct the establishment of a working group to speed up the completion of the Ben Tre Provincial General Hospital project.

Speaking to Lao Dong Newspaper reporters on January 9, Mr. Nguyen Truc Son - Permanent Vice Chairman of Ben Tre Provincial People's Committee - said that the construction package of Ben Tre Provincial General Hospital project started construction on December 28, 2024, and is expected to be completed in 18 months (June 2026). Ben Tre Provincial People's Committee has assigned the Ben Tre Provincial Civil and Industrial Construction Investment Project Management Board to represent the project investor, responsible for coordinating with consulting and construction units to develop a master plan, as well as detailed construction progress for each item of the package according to the signed contract.

At the same time, the Ben Tre Provincial People's Committee will direct the establishment of a working group to urge, inspect, supervise and promptly handle issues arising during the construction process, to ensure that the project is implemented on schedule, meeting quality, technical and aesthetic requirements. In addition, the investor also requires relevant units to work with a spirit of urgency, clear progress, ensuring requirements and achieving the best results.

Pho Chu tich Thuong truc UBND tinh Ben Tre Nguyen Truc Son. Anh: Thanh Nhan
Permanent Vice Chairman of Ben Tre Provincial People's Committee Nguyen Truc Son. Photo: Thanh Nhan

“At the beginning of 2025, the Ben Tre Provincial People's Committee directed the investor's representative to closely coordinate with relevant departments and branches to prepare bidding documents and send them to Korea Eximbank for comments. At the same time, prepare, appraise and approve the medical equipment estimate. In early 2026, this bid package must complete the selection of contractors, supply and installation of equipment in sync with the hospital construction progress, meeting the deadline specified in the Loan Agreement,” Mr. Son informed.

Nha thau tap trung huy dong may moc, nhan luc,...thi cong du an Benh vien Da khoa tinh Ben Tre. Anh: Thanh Nhan
Contractors focus on mobilizing machinery, human resources... to construct the Ben Tre General Hospital project. Photo: Thanh Nhan

Mr. Son added that the Provincial People's Committee is assigning specialized agencies to propose the establishment of an interdisciplinary technical council to review the list, quantity, and technical specifications of medical equipment, ensuring that it is suitable for the needs of use, technology for medical treatment, as well as the instructions in the Loan Agreement and Vietnamese laws.

“The goal of phase 1 is to build a new Provincial General Hospital with 500 beds, meeting grade II standards with a system of modern, synchronous medical equipment, best meeting the needs of medical examination, treatment and health care of Ben Tre province people.

Currently, Nguyen Dinh Chieu General Hospital (1,400 beds, currently overloaded - PV) will be restructured and rearranged to make effective use of existing facilities. At the same time, the entire system of the province's leading general hospitals will be rearranged to serve the needs of specialized medical examination and treatment, as well as aiming to provide high-tech medical services to the people" - Mr. Son shared.

Previously in 2015, the People's Committee of Ben Tre province issued Decision No. 1594 approving the content of the investment project document for the construction of Ben Tre General Hospital using preferential loans from the Korean Government. The project has a total investment of more than 1,658 billion VND, of which the preferential credit loan to support development of the Korean Government is more than 1,331 billion VND. The project is located in Binh Phu commune (Ben Tre city, Ben Tre province). The Prime Minister has approved this project to extend the loan agreement disbursement period to December 31, 2026.

Thành Nhân
TIN LIÊN QUAN

Billion-dollar hospital in Ben Tre officially launched

|

Ben Tre - Ben Tre General Hospital project with a total investment of more than 1,658 billion VND has officially started.

Billion-dollar hospital in Ben Tre extends disbursement until December 31, 2026

|

Ben Tre - The Ben Tre Provincial General Hospital project has selected a construction contractor and has been granted an extension of disbursement until December 31, 2026.

Proposal to add 2 groups of law-making to receive 100% salary support coefficient

|

National Assembly delegate To Ai Vang proposed 2 more groups to receive monthly salary support coefficient when participating in law-making work.

A major fire at a furniture factory in Ho Chi Minh City, dozens of firefighters urgently put out the fire

|

HCMC - A major fire at a furniture factory on Nguyen Thi Ai Street (Hoc Mon). Dozens of firefighters responded and controlled the situation after 30 minutes. Property damage is being counted.

Completing the law for the press to develop in the digital age

|

On the morning of May 16, a workshop on "Improving the law for press development in the digital age" took place in Hanoi.

Minister of Home Affairs Pham Thi Thanh Tra receives new duties

|

The Minister of Home Affairs is the Head of the Administrative Reform Working Group. The task of the Group is to research and propose to the Government on the development of science, technology, etc.

Billion-dollar hospital in Ben Tre officially launched

Thành Nhân |

Ben Tre - Ben Tre General Hospital project with a total investment of more than 1,658 billion VND has officially started.

Billion-dollar hospital in Ben Tre extends disbursement until December 31, 2026

Thành Nhân |

Ben Tre - The Ben Tre Provincial General Hospital project has selected a construction contractor and has been granted an extension of disbursement until December 31, 2026.

Đấu thầu không thành, dự án bệnh viện ngàn tỉ ở Bến Tre xin thêm thời gian

Thành Nhân |

Kết quả đấu thầu lần 1 không lựa chọn được nhà thầu phải tổ chức đấu thầu lại lần 2, để đảm bảo hoàn thành dự án bệnh viện ngàn tỉ, tỉnh Bến Tre kiến nghị Bộ Tài chính xem xét, thống nhất với Ngân hàng Xuất nhập khẩu Hàn Quốc (KEXIM) về việc kéo dài thời gian giải ngân thỏa thuận vay đến tháng 12.2026.