Speeding up the construction progress of the North-South expressway through Quang Binh

CÔNG SÁNG |

Quang Binh - The North-South Expressway construction unit through the area is mobilizing maximum human resources and equipment, working 3 consecutive shifts to ensure the project's progress.

The Ho Chi Minh Road Project Management Board (Ministry of Transport) is the investor of the Van Ninh - Cam Lo Expressway Component Project.

On February 24, speaking with a reporter from Lao Dong Newspaper, Mr. Chu Van Long - Deputy Head of Project Management Department 4, Ho Chi Minh Road Project Management Board said that up to now, Quang Binh province has handed over the entire 33.017 km of site, reaching 100% of the required progress. However, some additional service routes are still in the process of completing approval documents.

In addition, the relocation of technical infrastructure also has some problems. In Quang Binh, there is still a telecommunications infrastructure location at Km693+425 and some power lines after meters have not been relocated.

Nhieu mui thi cong tren cong truong cao toc Bac - Nam duoc trien khai. Anh: Phi Xuan
Many construction teams at the North - South Expressway construction site have been deployed. Photo: Phi Xuan

Mr. Long said that currently, the construction contractors have organized 67 construction teams, including 29 bridge construction teams, 20 road construction teams, 14 underpass construction teams and box culverts, and 4 round culverts.

The total construction force includes 1,468 officers, engineers, workers and about 641 pieces of equipment and machinery such as excavators, road rollers, bulldozers, cranes, cars, generators, etc.

May moc duoc huy dong de kip tien do Thu tuong giao. Anh: Phi Xuan
Machinery is mobilized to keep up with the progress assigned by the Prime Minister. Photo: Phi Xuan

The main volumes achieved are the roadbed, which is 94.67% complete; the road foundation, which is 89.25% complete.

The project on the route has been completed: culvert 222/240 at 92.5%; underpass: 41/42 at 98%...

However, the weather in Quang Binh in recent days has had rain, affecting some construction areas, especially road and asphalt concrete items.

Despite unfavorable weather, workers at the construction site are still working hard day and night to ensure progress. Worker Nguyen The Gian - working in the empty asphalt concrete project on the expressway section through Le Thuy district - shared: "We work 3 shifts a day from morning to night. At noon, take a break to eat, rest and then continue work. Everyone is trying to ensure the project's progress".

The North-South expressway construction project in the East phase 2021 - 2025, the section passing through Quang Binh province, will be implemented from 2022, including 3 component projects with a length of 126.43km through 6/8 districts, towns, cities and 35 communes, wards/151 communes, wards and towns. The project is expected to open to traffic on April 30, 2025.

CÔNG SÁNG
TIN LIÊN QUAN

Prime Minister requests "just work" to complete North-South Expressway

|

The Prime Minister requested units to concentrate human and material resources to soon complete the North-South expressway.

Workers work through Tet on the North-South Expressway

|

Quang Binh - Even though it was the days before and during Lunar New Year, workers still stayed at the construction site, working through the holiday to ensure the progress of the expressway project.

Completion of North-South expressway through Quang Binh

|

Quang Binh - The last meters of the North-South expressway through the area have been handed over to the contractor.

Hanoi announces 10th grade exam schedule for the 2025 - 2026 school year

|

Hanoi will organize the 10th grade entrance exam for high school in the 2025-2026 school year on June 7 and 8.

Mr. Nguyen Thanh Nghi holds new responsibility in Ho Chi Minh City

|

HCMC - Mr. Nguyen Thanh Nghi - Standing Deputy Secretary of the HCMC Party Committee - has just been assigned additional tasks by the Standing Committee of the HCMC Party Committee.

Phu Yen farmers are in trouble because thousands of hectares of crops are flooded

|

Prolonged heavy rain caused flooding in many areas in Phu Yen, causing thousands of hectares of people's crops to be submerged in water, causing severe damage.

People receive support of 1 million VND after the metro tunnel excavation incident

|

After the incident of the Nhon - Hanoi Railway Station metro tunnel excavation, households received support of 1 million VND/household.

Colonel Nguyen Duc Hai becomes Secretary of the Dong Nai Police Party Committee

|

Colonel Nguyen Duc Hai was appointed to hold the position of Secretary of the Dong Nai Provincial Police Party Committee for the 2020 - 2025 term.

Prime Minister requests "just work" to complete North-South Expressway

Khánh Linh |

The Prime Minister requested units to concentrate human and material resources to soon complete the North-South expressway.

Workers work through Tet on the North-South Expressway

CÔNG SÁNG |

Quang Binh - Even though it was the days before and during Lunar New Year, workers still stayed at the construction site, working through the holiday to ensure the progress of the expressway project.

Completion of North-South expressway through Quang Binh

CÔNG SÁNG |

Quang Binh - The last meters of the North-South expressway through the area have been handed over to the contractor.