969 billion VND parking lot project in Dai Co Viet to be cleared soon

Minh Hạnh |

Hanoi is implementing site clearance for the static parking lot project along the south of Dai Co Viet street, meeting over 1,000 parking spaces.

The static parking lot project along the south side of Dai Co Viet street has a total investment of more than 969 billion VND, including one overhead floor serving landscape and 3 basements, meeting more than 1,000 parking spaces.

On June 10, the People's Committee of Bach Mai ward (Hanoi) announced information about the Static parking project along the south side of Dai Co Viet street. The project is planned on an area of 6,844m2, with a total investment of more than 969 billion VND.

According to the plan, the project includes one above-ground floor serving the landscape garden and vertical traffic points, along with 3 basements with an area of about 5,673m2 each floor. The total floor area of the basement is more than 17,000m2, meeting the parking needs of over 1,000 vehicles.

On November 30, 2017, Hanoi City People's Committee approved Tan Hoang Minh Hotel Trading and Service Co., Ltd. as the project investor. However, the project has not yet been implemented on the ground despite a long period of research and preparation.

The project has a recovered land area of 6,843.6m2, affecting 110 households. In order to promote the implementation progress, on March 25, the Steering Committee for Site Clearance of Bach Mai Ward worked with representatives of the investor to urge the implementation of the contents according to the direction of the Hanoi People's Committee.

Regarding land acquisition, compensation and site clearance, on March 5, 2026, Tan Hoang Minh Hotel and Service Trading Co., Ltd. requested the Hanoi Department of Agriculture and Environment to guide the implementation of related procedures. By March 30, 2026, the Hanoi Department of Agriculture and Environment had a document guiding the land acquisition, compensation and site clearance for the project.

On March 31, the Hanoi Department of Construction reported and proposed that the Hanoi People's Committee approve the allocation of 110 social housing units to serve resettlement for households subject to land acquisition.

Currently, the Bach Mai Ward Investment - Infrastructure Project Management Board is coordinating with the investor to review all legal documents, and at the same time inspect the current status and site clearance process for 110 affected households.

On that basis, relevant units will identify land users, land plots and advise the Ward People's Committee to issue land recovery notices to implement the next steps of the project.

Minh Hạnh
RELATED NEWS

Complete site clearance for bridge projects over the Red River before May 30

|

Hanoi - Standing Deputy Secretary of the City Party Committee requested 4 localities related to the Red River overpass projects to complete the site clearance work completely before May 30.

People are worried because a power pole blocks a road worth more than 20,000 billion VND in Ho Chi Minh City

|

Ho Chi Minh City - Nguyen Thi Dinh street is being expanded, many power poles have not been moved, and construction materials are scattered for a long time, making it difficult for people to travel.

Vietnam Fatherland Front innovates activities in ethnic affairs

|

Conclusion No. 01/KL-MTTW-ĐCT sets out the requirement to innovate the activities of the Vietnam Fatherland Front and socio-political organizations in ethnic affairs to 2030, with a vision to 2045.

157 students from remote islands in An Giang pack their bags and go ashore to take the high school graduation exam

|

An Giang - 157 students in Kien Hai special zone enter Rach Gia ward to take the 2026 high school graduation exam.

Hà Nội kiểm tra, xử lý nhà siêu mỏng, siêu méo sau giải phóng mặt bằng

Minh Hạnh |

Hà Nội yêu cầu kiểm tra, rà soát và xử lý các trường hợp nhà siêu mỏng, siêu méo, thửa đất không đủ điều kiện xây dựng tại các dự án mở đường.

Complete site clearance for bridge projects over the Red River before May 30

HOÀI ANH |

Hanoi - Standing Deputy Secretary of the City Party Committee requested 4 localities related to the Red River overpass projects to complete the site clearance work completely before May 30.

Phường Thanh Xuân gửi thư đến các hộ gia đình trong diện giải phóng mặt bằng Vành đai 2,5

HOÀI ANH |

Hà Nội - Phường Thanh Xuân gửi thư cảm ơn đến nhân dân vì đã thấu hiểu, tin tưởng và đồng thuận trong quá trình giải phóng mặt bằng Vành đai 2,5.