The longest canal renovation project in Ho Chi Minh City is deserted of workers, machinery is lying idle

MINH QUÂN |

Ho Chi Minh City - The construction site of the Tham Luong - Ben Cat - Nuoc Len canal renovation project, the longest canal in Ho Chi Minh City, is deserted of workers and machinery is lying idle.

The above situation was recorded by Lao Dong Newspaper reporters on February 24.

Along the construction site from An Nhon, Go Vap, An Hoi Dong, An Hoi Tay wards (former Go Vap district), Tan Son, Tan Binh (former Tan Binh district), Binh Hung Hoa, Binh Tan (former Binh Tan district), no construction workers are seen.

Machinery gathered in the command area and scattered on the route, many cranes on the barges also stopped operating.

Dự án cải tạo kênh Tham Lương - Bến Cát qua quận BÌnh Tân trước đây.  Ảnh: Anh Tú
The project to renovate the Tham Luong - Ben Cat canal through Binh Tan district (HCMC) before. Photo: Anh Tu

Notably, the project to renovate the Tham Luong - Ben Cat - Nuoc Len canal is one of the projects in Ho Chi Minh City registered for construction throughout the Lunar New Year 2026, but the reality at the construction site is completely opposite.

Máy móc nằm đắp chiều trên công trường.  Ảnh: Minh Quân
Machinery is silent on the construction site. Photo: Minh Quan
Cần cẩu nằm nằm “treo cẩu”. Ảnh: Minh Quân
Crane lying "hanging the crane". Photo: Minh Quan

Some sections of road along the canal have been technically opened to traffic. However, in the area near An Loc bridge, the road surface above the drainage culvert is broken, revealing the steel inside, posing a potential safety risk for road users.

Đường ven kênh bị sụt lún. Ảnh: Minh Quân
Road along the canal is subsided. Photo: Minh Quan

Many other sections are under construction, rocks and soil are piled up, creating mud, stagnant water pollution and foul odors.

Đoạn đường ven kênh thi công dang dở, đọng nước gây ô nhiễm.  Ảnh: Minh Quân
The road along the canal is under construction, with stagnant water causing pollution. Photo: Minh Quan

Under the canal, although water hyacinth and weeds had been dredged and removed beforehand, due to slow construction progress, water hyacinth and weeds have grown back lushly.

Kênh Tham Lương - Bến Cát mọc đầy lục bình, cây dại.  Ảnh: Anh Tú
Tham Luong - Ben Cat canal is full of water hyacinths and wild plants. Photo: Anh Tu

Ms. Nguyen Thi Binh (65 years old, living by the canal section passing through Go Vap district before) said that at the time of construction, the construction site was operating bustlingly, and people expected the canal to soon be revived into a green canal, contributing to changing the urban appearance.

But for the past 3 years, the project has been slow, greatly affecting people's lives and travel. The closer to the finish line, the fewer workers. Many road sections along the canal are muddy and very inconvenient to travel. We hope the leaders of Ho Chi Minh City will direct drastically to accelerate progress and complete the project soon" - Ms. Binh said.

Rác thải đổ trộm dọc kênh Tham Lương - Bến Cát.  Ảnh: Minh Quân
Garbage dumped illegally along the Tham Luong - Ben Cat canal. Photo: Minh Quan

The project to improve the environment and build infrastructure along the Tham Luong - Ben Cat - Rach Nuoc Len canal was started in February 2023, with a total initial investment of 8,200 billion VND, after adjusting to more than 9,000 billion VND.

The canal is nearly 32 km long, built with concrete embankments on both banks, dredging the canal bed, building a road along the canal 8 - 12 m wide, installing drainage systems, lighting, green trees; building 19 drainage culverts, 12 wharves and 3 connecting bridges.

According to the initial plan, the project was expected to be completed on April 30, 2025. However, the project was delayed and the implementation time was adjusted to 2026.

The project has a total of 40 bidding packages, of which 10 main construction packages are participated by 69 contractors in the form of a joint venture. Although the number of contractors is large, the overall progress has not yet met expectations.

Dự án thì công ì ạch đoạn qua quận Gò Vấp trước đây.  Ảnh: Minh Quân
The project was slow in progress in the section passing through Go Vap district before. Photo: Minh Quan

According to the Ho Chi Minh City Urban Infrastructure Construction Investment Project Management Board (the investor), after more than 3 years of implementation, the project has achieved about 70% of the volume of main items.

One of the major difficulties is the existing electricity and telecommunications cable system running along the canal. Many underground cable lines and low-voltage power poles have not been relocated, causing obstruction to construction. The investor is coordinating with the electricity sector to accelerate the relocation, rearrangement, and create a clean ground for the remaining items.

In addition, the construction progress of the canal-side road in the past time has also been affected by the lack of supply of sand and construction stone and the high price of materials. Although the city has designated a stone mine to supply the project, the volume still does not meet the demand, and needs to be further supplemented to ensure progress.

MINH QUÂN
RELATED NEWS

Many obstacles surround the project to renovate the longest canal in Ho Chi Minh City

|

HCMC - Lack of sand, rocks, and land clearance problems have caused the Tham Luong - Ben Cat - Nuoc Len canal renovation project, the longest canal in HCMC, to face the risk of further delays.

A series of construction contractors have been revealed who are behind schedule in the project to renovate the longest canal in Ho Chi Minh City

|

HCMC - The Tham Luong - Ben Cat - Nuoc Len canal renovation project is behind schedule when it has only reached nearly 50% of the volume, many contractors have been fined for sluggish construction.

Singer Dan Truong: I want my child to learn to appreciate the meaning of lucky money envelopes

|

In a conversation with a reporter from Lao Dong Newspaper on the occasion of Binh Ngo Tet 2026, singer Dan Truong reviewed his 30-year career journey as well as changes in his life and artistic activities.

Vietnamese beauty buys a few houses and a car thanks to a 2-million VND song

|

This Vietnamese beauty revealed that she changed her life thanks to a song bought for 2 million VND. At the age of over 40, she possesses an admirable young and beautiful beauty.

Nord Stream has a chance to revive from Russia-US agreement

|

An agreement between Russia and the US to end the Ukraine conflict could pave the way for the revival of the Nord Stream gas pipeline.

Gold prices skyrocket before the God of Wealth Day, buyer sentiment changes

|

Gold prices are high before the God of Wealth Day. Businesses said that shopping behavior tends to be more cautious instead of buying according to crowd psychology.

Ho Chi Minh City removes difficulties for grassroots levels, ensuring people's voting rights

|

Ho Chi Minh City removes obstacles in listing voters' names, organizes polling stations at hospitals and creates maximum conditions for people to exercise their voting rights.

Unusual reddish-brown water appears at sea in Gia Lai

|

Gia Lai - A long red-brown water strip stretching across the coast of Hoai Nhon Bac ward caused a stir on social networks, many opinions said that this is a red tide phenomenon.

Dự án kênh nghìn tỉ Tham Lương - Bến Cát chạy đua với tiến độ, gỡ nút thắt mặt bằng

Tú Tâm |

TPHCM - Dự án cải tạo kênh Tham Lương - Bến Cát đã đạt gần 70% khối lượng, đang khẩn trương thi công, để kịp về đích đúng hẹn.

Many obstacles surround the project to renovate the longest canal in Ho Chi Minh City

MINH QUÂN |

HCMC - Lack of sand, rocks, and land clearance problems have caused the Tham Luong - Ben Cat - Nuoc Len canal renovation project, the longest canal in HCMC, to face the risk of further delays.

A series of construction contractors have been revealed who are behind schedule in the project to renovate the longest canal in Ho Chi Minh City

MINH QUÂN |

HCMC - The Tham Luong - Ben Cat - Nuoc Len canal renovation project is behind schedule when it has only reached nearly 50% of the volume, many contractors have been fined for sluggish construction.