A series of construction contractors have been revealed who are behind schedule in the project to renovate the longest canal in Ho Chi Minh City

MINH QUÂN |

HCMC - The Tham Luong - Ben Cat - Nuoc Len canal renovation project is behind schedule when it has only reached nearly 50% of the volume, many contractors have been fined for sluggish construction.

The above information is stated in the report of the Ho Chi Minh City Urban Infrastructure Construction Investment Project Management Board ( urban Infrastructure Board - investor) sent to the Ho Chi Minh City People's Committee on the progress of key projects invested by this unit.

The environmental improvement and infrastructure construction project along the Tham Luong - Ben Cat - Nuoc Len canal was started in February 2023, with a total initial investment of VND 8,200 billion and then adjusted to more than VND 9,000 billion.

With a length of nearly 32 km, this is the longest canal in Ho Chi Minh City, flowing through 7 districts including: District 12, Binh Tan, Tan Phu, Tan Binh, Go Vap, Binh Thanh and Binh Chanh District.

According to the Urban Infrastructure Board, the project has only reached about 49.43% of the total volume. Of which, some sections along the canal, more than 4 km long, passing through District 12, Go Vap and Binh Tan, were opened to traffic on April 29, 2025.

The Urban Infrastructure Board assessed that currently, the project items are behind schedule compared to the set plan, and there are still many difficulties and problems that need to be resolved.

One of the main reasons is that some contractors do not meet the requirements. Despite being repeatedly urged and reminded, many units are still slow, forcing the Urban Infrastructure Board to apply handling measures, including penalties for contract violations.

Hai Dang Joint Stock Company constructed the XL-03, XL-04, XL-05 packages that did not meet requirements and was fined more than VND681 million.

Hoang Ngan Transport Construction Joint Stock Company constructed the XL-05 package that did not meet requirements and was fined nearly 32 million VND.

Cong Chanh Traffic Construction Joint Stock Company and Hai Duong dyke Construction and Rural Development Joint Stock Company did not meet the schedule for the XL-01 package and were notified of breach of contract.

Thoi Binh Construction and Trading Joint Stock Company constructed the XL-01 and XL-03 packages behind schedule and was notified of a breach of contract.

559 Investment Joint Stock Company and 201 Construction Joint Stock Company both constructed the XL-09 package but did not meet requirements and were notified of contract violations.

Saigon Traffic Construction Joint Stock Company and Seafood Construction and Installation Joint Stock Company II are behind schedule in constructing package XL-01, and have been notified of contract violations.

Mot doan kenh Tham Luong - Ben Cat qua Go Vap va Tan Binh dang duoc ke bo va duong hai ben. Anh: Anh Tu
A section of Tham Luong - Ben Cat canal through Go Vap and Tan Binh is being embanked and roads on both sides. Photo: Anh Tu

In addition to the contractor problem, the project is currently stuck with 15 cases that have not yet handed over the site, including: 1 case in Binh Thanh district, 13 cases in Binh Tan district and 1 case in Binh Chanh district.

In addition, the canal is also stuck with low-voltage and medium-voltage power systems, transformer stations, and telecommunication cables installed along the power poles along the canal. These technical infrastructure needs to be relocated soon to ensure site clearance and construction safety.

According to the Urban Infrastructure Board, the project was allocated a disbursement capital plan for 2025 of 3,567 billion VND, but so far only nearly 164 billion VND has been disbursed.

The Tham Luong - Ben Cat - Rach Nuoc Len canal renovation project includes the following main items: building concrete embankments on both banks, dredging the canal bed, building a 7-12 m wide parallel road, installing drainage, lighting, and tree systems; building 19 drainage culverts, 12 boat docks, and 3 bridge over the canal.

When completed, the project will drain water for about 15,000 hectares, reduce flooding, improve traffic in the area, reduce pressure on National Highway 1 and promote waterway transport connecting Ho Chi Minh City with Long An, Binh Duong and Dong Nai.

MINH QUÂN
TIN LIÊN QUAN

Technical traffic opening of 6 longest canalside roads in Ho Chi Minh City

|

HCMC - 6 sections of the Tham Luong - Ben Cat - Rach Nuoc Len canal through Binh Tan district, District 12 and Go Vap are open to traffic, contributing to reducing traffic congestion in the area.

The longest canal improvement project in Ho Chi Minh City has 25 ground

|

The project to renovate Tham Luong - Ben Cat - Rach water canal, the longest canal in Ho Chi Minh City is facing difficulties when 25 ground has not been handed over or re -encroached.

Tham Luong - Ben Cat Canal gradually revives after 2 years of construction

|

This year, Ho Chi Minh City will complete the renovation of Tham Luong - Ben Cat - Nuoc Len canal and start two major projects: Xuyen Tam canal and the North bank of Doi canal. When completed, these canals will become as clear and clean as Nhieu Loc - Thi Nghe canal.

Verifying the case of paragliders with the engine using Bai Chay beach as a runway

|

Quang Ninh - After the motorized paraglider crashed in Bai Chay, a video clip appeared this morning of the paraglider taking off right on the crowded Bai Chay beach.

Chairman of Lao Cai issued a letter of the week about many units that owe banks billions of dong

|

Lao Cai - After the reflection, the Chairman of Lao Cai Provincial People's Committee issued instructions on resolving debts for printing houses in Bao Yen district.

Victim of a horrifying accident on the highway tries to squeeze through the driver's body to escape

|

Quang Nam - After the accident between a passenger bus and a tractor-trailer on the highway, the victims trembled over the bodies of the two drivers who died in the cabin to escape.

Admiring the new name signs of wards, communes, and special zones in Quang Ninh

|

Quang Ninh - Many new commune-level administrative units in Quang Ninh have completed the attachment of new name signs after merging administrative units.

Fire in a house and office for rent in Ho Chi Minh City, rescued 2 people trapped

|

HCMC - A fire broke out on the ground floor of a house on Nguyen Gia Tri Street (Binh Thanh District). Fire police promptly rescued 2 trapped people.

Technical traffic opening of 6 longest canalside roads in Ho Chi Minh City

MINH QUÂN - ANH TÚ |

HCMC - 6 sections of the Tham Luong - Ben Cat - Rach Nuoc Len canal through Binh Tan district, District 12 and Go Vap are open to traffic, contributing to reducing traffic congestion in the area.

The longest canal improvement project in Ho Chi Minh City has 25 ground

MINH QUÂN |

The project to renovate Tham Luong - Ben Cat - Rach water canal, the longest canal in Ho Chi Minh City is facing difficulties when 25 ground has not been handed over or re -encroached.

Tham Luong - Ben Cat Canal gradually revives after 2 years of construction

MINH QUÂN |

This year, Ho Chi Minh City will complete the renovation of Tham Luong - Ben Cat - Nuoc Len canal and start two major projects: Xuyen Tam canal and the North bank of Doi canal. When completed, these canals will become as clear and clean as Nhieu Loc - Thi Nghe canal.